All Electrical and Instruments Reports
Date Group Name Equipment Title Action
2024-07-22
1 year ago
NR.EL-01 Wahyu Adi Triono 453-SG1-&-453-BV1 Solenoid valve stuck for SG and connect bV1
Check at local order of SG still open, service slide gate test open and close result ok. 453 BV1 connect unit at local. test open and close, result closed ok no error but when order open still error indication at CCR it is meaning solenoid valve to open is not touch. We think maybe mechanical problem when order pen some materials hold valve ( ADI & EVE RIZKY )
2024-07-22
1 year ago
NR.EL-01 Wahyu Adi Triono L63-WF1 Fabrication belt drift weight feeder
Fabrication belt drift for weight feeder at work shop ( PENY & FIRMAN )
2024-07-22
1 year ago
NR.EL-01 Wahyu Adi Triono WARE-HOUSE Continue connect cable power input, cable heater to motor
Connected cable power input and cable heater to motor ( AGUS & ANDRI & EVE RIZKY )
2024-07-22
1 year ago
NR.EL-01 Wahyu Adi Triono 463-2K1-&-443-2K1 PMR service analyzer
PMR service analyzer. Clean up flange, probe, filter probe, sample line, diaphragm pump, filter balston, dryer gas from dirt of dust. Check humidity sensor and filter, replace filter if found bad condition with spare filter ( RIZAL )
2024-07-22
1 year ago
NR.EL-01 Wahyu Adi Triono 463-KL1 PMR service medium voltage motor
PMR service medium and DC motor. Clean up area motor and filter motor. Measure vibration, noise and temperature free and load side motor. Add grease 15 times for free and load side motor ( PENY & EVE IQBAL )
2024-07-22
1 year ago
NR.EL-01 Wahyu Adi Triono 363-RM1 PMR service medium voltage motor
PMR service medium voltage motor. Clean up area motor, filter motor. Measure vibration, noise and temperature free and load side. Add grease 10 times to 15 times for free and load side motor 363 FN1-363 FN2-423 FN1 and 443 FN1 ( ADI )
2024-07-19
1 year ago
NR.EL-01 Wahyu Adi Triono 423-2K1 CEMS problem at temperature indication
Trouble shooting for problem, result ok ( RIZAL & EVE IQBAL )
2024-07-19
1 year ago
NR.EL-01 Wahyu Adi Triono WARE-HOUSE Install panel lighting for heater power
Fabrication support panel at work shop. Install panel lighting at ware house ( ANDRI )
2024-07-19
1 year ago
NR.EL-01 Wahyu Adi Triono 363-RM1 PMR service medium voltage motor
PMR service medium voltage motor. Clean up area and filter motor. Measure vibration, noise and temperature free and load side motor. Add grease 10 times to 30 times for free side and load side motor ( AGUS )
2024-07-19
1 year ago
NR.EL-01 Wahyu Adi Triono 423-FN1 Take data for TPM
Take data for TPM belong to RMK Nr1. Make data TPM AM, safety at computer save data ( YOGA & EVE DAVID )
2024-07-19
1 year ago
NR.EL-01 Wahyu Adi Triono 473-GQ1 WBI electrical and instrumentation bottom blending, cooler, clinker silo
WBI electrical and instrumentation area bottom blending, cooler and clinker silo. Measure vibration, noise and temperature free and load side motor. Check tank auto grease, result ok ( RIZAL & EVE IQBAL )
2024-07-19
1 year ago
NR.EL-01 Wahyu Adi Triono 443-PH1 WBI electrical and instrumentation top blending, GCT, CT, pre heater, kiln, burner floor
WBI electrical and instrumentation area top blending, pre heater, GCT, CT, kiln and burner floor. Measure vibration, noise and temperature free and load side motor. Check auto grease tank, some motor at low level need to be refill auto grease tank ( ADI & EVE RIZKY )
2024-07-18
1 year ago
NR.EL-01 Wahyu Adi Triono 333-AC1;-363-BC1 Install auto grease
Installing auto grease for motor ( AGUS & FIRMAN & RIZAL & ANDRI )
2024-07-18
1 year ago
NR.EL-01 Wahyu Adi Triono 363-FA2-AND-363-MD-1 Clean up filter and carbon brush room man drive
Clean up filter 363 fA2. Clean up area, filter and carbon brush 363 MD1 from dirty dust ( YOGA & ADI )
2024-07-18
1 year ago
NR.EL-01 Wahyu Adi Triono 363-FN1;363-FN2 Clean up bearing motor free and load side
Clean up area, filter and bearing motor of free and load side ( EMIS )
2024-07-18
1 year ago
NR.EL-01 Wahyu Adi Triono 333-AC1;-333-WF1;-363-BE1;-363-CV1;-393-SC8 Check noise bearing motor, discouple coupling if posible
Check noise bearing motor at free and load side motor. Add grease 10 times to 30 times at free and load side. Result noise below 2 gE ( AGUS & FIRMAN )
2024-07-18
1 year ago
NR.EL-01 Wahyu Adi Triono 363-BC1 Check safety device and noise bearing motor
Check safety device at 363 BC1 and noise bearing motor, add grease 25 times result noise below 2 gE ( RIZAL & ANDRI )
2024-07-18
1 year ago
NR.EL-01 Wahyu Adi Triono 463-2K1-AND-443-2K1 PMR service analyzer
PMR service analyzer. Clean up flange, probe, filter probe, diaphragm pump from dirty dust. Replace seal for filter probe 2 at 443 2K1 result reading O2 decrease from 3.34 % to 2.54 % also replace connector sample line at diaphragm pump 463 2K1 result reading O2 decrease from 4.16 % to 3.26 % ( YOGA & ADI  )
2024-07-17
1 year ago
NR.EL-01 Wahyu Adi Triono L63-WF1 Check or replace lighting lamp are off
Replace lighting lamp off with spare lamp. Test on lighting lamp result ok ( YOGA & FIRMAN )
2024-07-17
1 year ago
NR.EL-01 Wahyu Adi Triono 463-KL1 PMR service medium voltage motor are kiln and coal mill
PMR service medium voltage motor area kiln and coal mill. Measure vibration-noise and temperature free side and load side motor. Add grease 10 times to 30 times for free side and load side motor if found vibration > 4 mm/s and noise > 2 gE ( AGUS & EVE DAVID )
2024-07-17
1 year ago
NR.EL-01 Wahyu Adi Triono 443-PR1-T3 Pulling cable purging
Pulling cable for purging from location sensor to panel I/O continue connected at I/O panel ( RIZAL & ANDRI & EVE IQBAL )
2024-07-17
1 year ago
NR.EL-01 Wahyu Adi Triono 363-RM1 WBI area raw mill, feed bin and bag filter
WBI are raw mill, feed bin and bag filter. Measure vibration-noise and temperature for free side and load side for some motor, screw, and rotary feeder that are not normal condition for vibration and noise. Area motor 333 AC1-333 AC2, 333 WF1 to WF4 are dirty form dust process need to be clean up area motor ( ADI & EVE RIZKY )
2024-07-16
1 year ago
NR.EL-01 Wahyu Adi Triono 473-FA1,FA2,FA3,FA4,FA6,FA8,FA9 Level auto grease low
Change tank auto grease with spare unit ( ADI & EVE IQBAL )
2024-07-16
1 year ago
NR.SHIFT Wahyu Adi Triono L63-RM1 PMR service coal mill
PMR service analyzer L63 2k1, L63 2K2, L63 2K3 and 483 2K1. Clean up flange probe, sample line, filter probe, diaphragm pump, dryer gas, filter balston from coal dust. Check filter humidity sensor, replace filter with spare filter if found bad condition ( ADI & EVE IQBAL )
2024-07-15
1 year ago
NR.EL-02 Yurizal Rachman 496-VT3 Service and repair
Replace valve kinetrol
2024-07-15
1 year ago
NR.EL-02 Yurizal Rachman 444-P13A Service and repair
Replace pressure transmitter
2024-07-15
1 year ago
NR.EL-02 Yurizal Rachman 444-FN2-T3 Service aand repair
Replace temperature transmitter
2024-07-15
1 year ago
NR.EL-01 Wahyu Adi Triono 464-KL1-TI-8,-TI-9,-TI-10 Connected cable from sensor to temperature transmitter Endess Hauser
Connected cable from sensor to temperature transmitter. Result reading at display temperature transmitter ok ( YONRI & ADI & SOBUR )
2024-07-13
1 year ago
NR.EL-02 Yurizal Rachman 444-TI18 Servicw dan repair
Continue prepare relocation
2024-07-13
1 year ago
NR.EL-02 Yurizal Rachman 444-MW1 Service dan repair
Replace Limit switch COG 2 eah
2024-07-13
1 year ago
NR.EL-02 Yurizal Rachman 444-PI13A Relocation
Relocation probe dan sample line
2024-07-12
1 year ago
NR.EL-02 Yurizal Rachman 444-PH1-T18 Modifikasi
Prepare relocation probe thermocouple
2024-07-12
1 year ago
NR.EL-02 Yurizal Rachman 464-KL1 Service dan repair
Instal thermocouple ujung kiln
2024-07-12
1 year ago
NR.EL-02 Yurizal Rachman 444-BE1 Service dan repair
Service dan repair safety device,replace speed sensor
2024-07-11
1 year ago
NR.EL-02 Yurizal Rachman 434-FM6 Kalibrasi dan check
Clean up panel
Kalibrasi zero span
2024-07-11
1 year ago
NR.EL-02 Yurizal Rachman 434-FM5 Kalibrasi dan Check
Clean up panel
Kalibrasi zero span
2024-07-11
1 year ago
NR.EL-02 Yurizal Rachman 434-BF3 Service dan repair
Check all solenoid purging
Replace all selang
Replace connector bocor
2024-07-11
1 year ago
NR.EL-01 Yurizal Rachman L3C-RE1 Finalising Ta Rizky
Download modifikasi program
Wiring control dan test run
2024-07-11
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Complete data PMR service analyzer 463 2K1 - 443 2K1 and CM analyzer for June & July 2024
Completing data PMR service analyzer at June-July 2024 for 463 2K1 & 443 2K1 also June 2024 for coal mill 
2024-07-10
1 year ago
NR.EL-02 Yurizal Rachman 434-FM1,2,3,4 Kalibrasi
Kalibrasi fm 434 fm1 - 4
2024-07-10
1 year ago
NR.EL-02 Yurizal Rachman 434-PG1-4 Service dan repair
Check, service dan setting posisi dan indikasi damper
2024-07-10
1 year ago
NR.N2-OH AGUS SUMIAJI SARBINI 404-3E1_ER4-NAR2 MCC & Switchgear Maintenance
1. Clean up MCC (100%)
2. Clean up Switchgear (100%)
3. Clean up Transformer (100%)
4. LV Protection Relay Testing (95%)
5. LV Protection Relay Replacement (60%)
2024-07-10
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP complete data TBM at shesig.sig.id
Complete data for TBM at shesig.sig.id for 3rd of meeting
2024-07-10
1 year ago
NR.EL-01 Wahyu Adi Triono 363-MD1 Tank auto grease level low level
Replace tank  auto grease with spare unit. Install at local set timer grease same with existing
2024-07-10
1 year ago
NR.EL-01 Wahyu Adi Triono L63-RM1 PMR service coal mill
PMR service analyzer coal mill, clean up flange probe, filter probe, sample line, diaphragm pump, filter balston, dryer gas from dust coal. Check filter humidity sensor, check filter replace if found bad condition with spare filter. Write data PMR service analyzer at form PMR service analyzer Coal Mill
2024-07-09
1 year ago
NR.EL-02 Yurizal Rachman 444-PH1 Relokasi probe
Relokasi probe yg menghalangi
2024-07-09
1 year ago
NR.EL-02 Yurizal Rachman 464-KL1 Replace Thermocouple
Replace thermocouple ujung kiln
2024-07-09
1 year ago
NR.EL-02 Yurizal Rachman 414-3S1 Service dan repair
Service solenoid aerasi cone blending timur,check dan service level material,check dan service shut off valve(434 SG1 SG2)
2024-07-09
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Scan data calibration pressure transmitter OH Nr2
Scan data calibration pressure transmitter zero and span OH Nr2 save at computer D: Wahyu Adi T & Emis under name OH Nr2 calibration pressure transmitter 
2024-07-09
1 year ago
NR.EL-01 Wahyu Adi Triono 473-FN7-&-463-MD1 Clean up area and filter motor
Clean up area and filter motor from dust process use instrument air supply, check carbon brush condition result all condition ok. Add grease 10 time for free and load side at 463 MD1 ( PENY & ADI )
2024-07-09
1 year ago
NR.EL-01 Wahyu Adi Triono L1C-BC7 PM tripper and reclaimer coal 7 days information from production department
Clean up panel near L1C BC7 from dust coal use cleaning cloth and hand blower ( PENY & ADI )
2024-07-09
1 year ago
NR.EL-01 Wahyu Adi Triono 463-2K1-&-443-2K1 PMR service analyzer
463 2K1: found flow gas at 0 L/H CO: -0.15 PPM, NO: 25 PPM and O2: 20.90 %, clean up probe, filter probe from hard dust. Insert analyzer flow gas 100 L/H, all gas reading back to normal. 443 2K1: clean up flange probe, filter probe, sample line, diaphragm pump, dryer gas, filter balston from dust process, check filter humidity replace filter if found bad condition ( PENY & ADI & YOGA )
2024-07-08
1 year ago
NR.EL-01 Yurizal Rachman 423-2K3 Yearly maintenance
Service mcs dan prepare calibration mcs
2024-07-08
1 year ago
NR.EL-02 Yurizal Rachman 434-BF1,BF2 Service dan repair
Check service dan replace solenoid purging
2024-07-08
1 year ago
NR.EL-02 Yurizal Rachman 444-PH1 Service dan repair
Continue replace thermocouple Lt.6
2024-07-08
1 year ago
NR.EL-02 Yurizal Rachman 444-PH1 Service dan repair
Relokasi probe tubing pressure transmitter Lt.6
2024-07-07
1 year ago
NR.EL-02 Yurizal Rachman L3C-RE1 Test run
Readykan dan test run L3C RE1 setelah mekanik ada modifikasi
2024-07-07
1 year ago
NR.EL-02 Yurizal Rachman 444-PH1 Service dan repair
Continue replace thermocouple Lt.7 dan 8
2024-07-08
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Write data calibration pressure transmitter Over Haul Nr2
Write data for calibration pressure transmitter area pre heater-kiln-raw mill-cooler and coal mill  ( ADI )
2024-07-08
1 year ago
NR.EL-01 Wahyu Adi Triono L63-MD1 Auto grease low level
Replace tank of auto grease with spare unit. Refill existing tank auto grease at work shop ( EMS & ADI )
2024-07-06
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP-NR2 Calibration pressure transmitter zero and span area cooler and coal mill Nr2
Calibration pressure transmitter zero and span area cooler and coal mill Nr2 get around 6 each ( YOGA & ADI )
2024-07-04
1 year ago
NR.SHIFT Peny Prasetyo 463-MD1 pmr critical motor kiln
clean up motor kiln,  fn7, 
analyser ph2 wiring
2024-07-05
1 year ago
NR.SHIFT Peny Prasetyo 444-AN1 pasang analyzer redundant Ana12
wiring di er4, tarik kabel
2024-07-06
1 year ago
NR.EL-01 Peny Prasetyo 444-AN1 pasang Analyzer redundant An1 2
wiring, contineuty kabel, blackkout PLN
2024-07-05
1 year ago
NR.EL-02 Yurizal Rachman 444-PH1 Service dan repair
Replace thermocouple Lt.10 dan 11
2024-07-05
1 year ago
NR.EL-02 Yurizal Rachman 444-PH1 Service dan repair
Instal pressure transmitter Lt1 - Lt12
2024-07-05
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP-NR2 Calibration pressure zero and span transmitter area cooler and coal mill Nr2
Calibration pressure zero and span transmitter area cooler and coal mill Nr2 get around 20 each transmitter ( YOGA & ADI )
2024-07-04
1 year ago
NR.EL-02 Yurizal Rachman 444-PH1 Instal pressure transmitter
Instal pressure transmitter lantai 12,11,10,9
2024-07-04
1 year ago
NR.EL-02 Yurizal Rachman 444-LD2 Service dan repair
Greasing gear motor,check open close kondisi masih OK
2024-07-04
1 year ago
NR.EL-02 Yurizal Rachman 444-LD-1- Service dan repair
Replace bearing motor beck actuator,greasing gear motor,test open close
2024-07-04
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP-NR2 Calibration pressure transmitter area COAL MILL and Cooler Nr2
Calibration pressure transmitter for area coal mill and cooler for NR2 get around 30  ( YOGA & ADI )
2024-07-03
1 year ago
NR.EL-02 Yurizal Rachman 434-VA1-,VA2 Service dan repair
Replace solenoid bray
2024-07-03
1 year ago
NR.EL-02 Yurizal Rachman 444-PH-1-T1,T12,T3,T4 Service dan repair
Replace thermocouple
2024-07-03
1 year ago
NR.EL-02 Yurizal Rachman 444-GT4,GT7,426-DV1 Service dan repair
Replace selang angin
Test open close 
Clean up filter regulator
2024-07-02
1 year ago
NR.EL-01 Peny Prasetyo 444-KL1 ganti label rtd tire 1
tarik kabel & terminasi
2024-07-03
1 year ago
NR.EL-01 Peny Prasetyo 444-AN1 pasang Analyzer redundant An1 2
pasang solenoid , wiring
2024-07-03
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Calibration pressure transmitter area pre heater Nr2
Calibration pressure transmitter zero and span area pre heater narogong 2 gets around 21 pressure transmitter for Over Haul  ( YOGA & ADI )
2024-06-11
1 year ago
NR.EL-03 Bayu Kiln Saputro M34-WPD Indikasi motor vibrasi
Cek motor posisi discouple
motor normal
vibrasi kemungkinan dari pompa lanjut tim mekanik
2024-06-10
1 year ago
NR.EL-03 Bayu Kiln Saputro 66B-CX4 Indikasi run dan fault ke CCR belum ada
Install Indikasi run dan fault ke CCR
Test OK
2024-06-10
1 year ago
NR.EL-03 Bayu Kiln Saputro SCISSOR-LIFT WBI
WBI scissor lift
2024-06-10
1 year ago
NR.EL-03 Bayu Kiln Saputro TRAFO-NAR1_2 WBI
WBI trafo OTR 2, 3, 301, 302, A, B
2024-06-07
1 year ago
NR.EL-03 Bayu Kiln Saputro OHS-BUILDING Lampu Mati
Cek tegangan hilang, cek fasa ada, kemungkinan netral putus
harus bobok plafon untuk pengecekan lanjutan 
2024-06-07
1 year ago
NR.EL-03 Bayu Kiln Saputro SDC-BUILDING Lampu Mati
Ganti lampu area SDC building
2024-06-07
1 year ago
NR.EL-03 Bayu Kiln Saputro OFFICE-ENVIRONMENT Lampu dan stop kontak mati
cek breaker 6A trip beban termasuk AC
ganti MCB dari 6A ke 16A
test OK
2024-07-02
1 year ago
NR.EL-02 Yurizal Rachman 434-PG1&PG6 Service dan repair
Test open close,inject 4-20mA check indikasi
Clean up area damper
2024-07-02
1 year ago
NR.EL-02 Yurizal Rachman 434-GT1 Service and repaire
Replace broken solenoid valve 
Test function from Do
2024-07-01
1 year ago
NR.EL-02 Yurizal Rachman 444-PH1- Overhoule
Dismantle all pressure transmitter area Preheater and id fan
2024-07-02
1 year ago
NR.EL-01 Wahyu Adi Triono MAIN-GATE-ACCES-CONTROL-OH-NR2 Inspection electrical and welding tools of contractor for OH NR2
Inspection electrical and welding tool of AQPA, SSM,CAT, TRUBA JAGA CITA, INDOPORLEN, RPM. Make report at form electrical for inspection electrical and welding tools for SHINAGAWA-TRUBA JAGA CITA-PINCURAN MAS-INDOPORLEN before 1 July 2024 ( ADI & EKA & MARPAUNG )
2024-07-02
1 year ago
NR.N2-OH AGUS SUMIAJI SARBINI 304-3E2 MCC, Switchgear Maintenance
1. Clean Up MCC Room & Panel (100%)
2. Clean Up Switcgear Room & Panel (100%)
3. Clean Up Transformer (100%)
4. Clean up Capacitor & Panel (100%)
5. 364-MD1.M1 mesure capacitor (100%)
6. LV Protection Relay Tripping Test (100%)
7. LV Protection Relay Replacement (50%)
2024-07-01
1 year ago
NR.EL-01 Peny Prasetyo 464-KL1.T11 ganti kabel rtd
pabrikasi jalur kabel rtd 
2024-07-01
1 year ago
NR.EL-01 Wahyu Adi Triono MAIN-GATE-ACCES-CONTROL-OH-NR2 Inspection electrical and welding tools
Inspection electrical and welding tools of TOTAL PRIME ENGINEERING, TRUBA JAGA CITA, RPM ( EKA & ADI & MARPAUNG )
2024-06-29
1 year ago
NR.EL-01 Wahyu Adi Triono 464-KL1-AND-444-PH1 Make working permit for Over Haul
Making working permit area kiln and pre heater for Over Haul NR2 ( RIZAL )
2024-06-29
1 year ago
NR.EL-01 Wahyu Adi Triono 364-RM1-AND-334-WF Make working permit for Over Haul
Making working permit area raw mill and feed bin for Over Haul  NR2 ( YOGA )
2024-06-29
1 year ago
NR.EL-01 Wahyu Adi Triono MAIN-GATE-ACCES-CONTROL Inspection electrical and welding machine of contractor
Inspection electrical and welding machine from INDOPORLEN, TRUBA JAGA CITA and AQPA ( ADI & MARPAUNG TRUBA JAGA CITA & SUTRI TRUBA JAGA CITA )
2024-06-28
1 year ago
NR.EL-01 Wahyu Adi Triono CCTV-BURNER Install panel box
Installing panel box at local ( PENY & ANDRI )
2024-06-28
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Completing data Juara Inovation
Completing data Juara Inovation and save at computer ( RIZAL )
2024-06-28
1 year ago
NR.EL-01 Wahyu Adi Triono WARE-HOUSE Install panel lighting at area motor for heater power. Connect power input and insatall cable to heater motor
Install panel lighting at area motor for heater motor. Connected cable power input and install cable heater motor ( YOGA & FIRMAN & ANDRI )
2024-06-28
1 year ago
NR.EL-01 Wahyu Adi Triono 393-FA3-A Prepare project give to vendor and pulling cable, install LCS, pulling I/O MCC
Preparing data of project, pulling cable, install LCS and I/O MCC to vendor ( PENY )
2024-06-28
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Completing wiring Input and Output panel
Completing wiring for Input and Output panel ( AGUS )
2024-06-28
1 year ago
NR.EL-01 Wahyu Adi Triono L1C-BC4-AND-L1C-BC7 Clean up panel welding and lighting
Clean up panel lighting and welding from dust coal use hand blower and cloth 
2024-06-27
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Service Grinding Machine Mechanic I
Service grinding machine from mechanic I., test functional result ok. Give tagging blue color ( ADI & FIRMAN )
2024-06-27
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Prepare document for audit
Prepare document for audit ( YURIZAL )
2024-06-27
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Continue labeling I/O
Labelling Input Output Panel ( AGUS )
2024-06-27
1 year ago
NR.EL-01 Wahyu Adi Triono CCTV-BURNER-FLOOR Install box
Prepare box at work shop, Install support panel continue painting  ( PENY & ADI )
2024-06-27
1 year ago
NR.EL-01 Wahyu Adi Triono IDO-PUMP Continue install lamp
Installing lamp ( ANDRI & FIRMAN & EVE DAVID )
2024-06-26
1 year ago
NR.EL-01 Wahyu Adi Triono 453-AE1 Install strainer line of instrument air
Install strainer line for instrument air ( FIRMAN & ANDRI )
2024-06-26
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP-MECHANIC-NR1 Inspection electrical and welding machine
Inspection electrical and welding machine for Mechanic NR 1 ( ADI & EVE DAVID )
2024-06-26
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Continue wiring diagram Input & Output
Wiring diagram I/O panel ( AGUS )
2024-06-26
1 year ago
NR.EL-01 Wahyu Adi Triono IDO-PUMP Continue install receptacle
Install receptacle at IDO PUMP ( ANDRI & FIRMAN )
2024-06-26
1 year ago
NR.EL-01 Wahyu Adi Triono L63-RM1-&-L3C-RE1-&-L1C-TR1 WBI instrumentation and electrical
WBI instrumentation and electrical are Coal Mill-Reclaimer and Tripper Coal ( PENY )
2024-06-26
1 year ago
NR.EL-01 Wahyu Adi Triono 493-AC2 Continue replace contactor auxilary LCS
Replacing contactor auxilary LCS ( YOGA & EVE RIZKY )
2024-06-25
1 year ago
NR.EL-01 Wahyu Adi Triono IDO-PUMP Install receptacle and lighting panel
Installing lighting panel and receptacle ( ANDRI & FIRMAN )
2024-06-25
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP JUARA INOVASI complete presentation data
Completing data for presentation JUARA INOVASI ( RIZAL )
2024-06-25
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Complete data check sheet
Completing data check sheet for PMS 463 MD1 years 2024. Scan file and save at server ( EMIS & ADI )
2024-06-25
1 year ago
NR.EL-01 Wahyu Adi Triono 463-2K1-&-443-2K1 PMR service analyzer
PMR service analyzer such clean up probe, filter probe, diaphragm pump, dyer gas, filter balston. Check filter humidity sensor replace filter if found bad condition with spare filter ( AGUS )
2024-06-25
1 year ago
NR.EL-01 Wahyu Adi Triono L63-RM1 PMR service analyzer L63 2K1-2k2-2k3 & 483 2k1
PMR service analyzer such clean up probe, filter probe, sample line, diaphragm pump, filter balston, dryer gas Check filter humidity sensor replace filter if found bad condition with spare filter ( YOGA & EVE RIZKY )
2024-06-24
1 year ago
NR.EL-01 Wahyu Adi Triono IDO-PUMP Replace lighting panel and install receptacle
Replacing panel lighting and installing receptacle ( ANDRI & FIRMAN )
2024-06-24
1 year ago
NR.EL-01 Wahyu Adi Triono 423-2K1 PMR service CEMS
PMR service CEMS, clean up filter purge air unit dust hunter and flowsic also area motor, transducer A & B flowsic, swivel window t/r & reflector dust hunter also alignment, filter cabinet MCS 100 E, room of CEMS and span gas also H2 of room ( YOGA )
2024-06-24
1 year ago
NR.EL-01 Wahyu Adi Triono 463-KL1 PMR service medium voltage motor
PMR service medium voltage motor. Clean up area and filter motor, measure vibration, noise and temperature free and load side. Add grease 10 times to 15 times for free side and load side motor ( PENY )
2024-06-24
1 year ago
NR.EL-01 Wahyu Adi Triono 363-RM1 PMR service medium voltage motor
PMR service medium voltage motor, clean up area and filter motor. Measure vibration, noise and temperature free and load side. Add grease 10 times to 30 times for free side and load side motor ( AGUS )
2024-06-24
1 year ago
NR.EL-01 Wahyu Adi Triono TENT-OH Install timer for lamp
Installing timer for lamp every tent over haul, test functional time result ok  ( FIRMAN & ANDRI )
2024-06-24
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan COOLER Panel junction penyok
Repair/ganti panel junction transmitter (Rizky, Deden)
2024-06-24
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan WORKSHOP-TRUBA Inspeksi Tools TRUBA
Inspeksi Tools truba Dan tagging tools Truba (Eka)

2024-06-24
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan 364-FN2 Info Motor terbakar
Cek motor slide gate (info motor terbakar), cek motor aman, lepas couple ampere motor normal, (indikasi gate berat), ganti/r pair emergency dan push button (Rizky, Yana)


2024-06-24
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan RAWMILL Motor harus di relokasi
Pindahkan motor, (Hariyanto, Amun)


2024-06-22
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan 404-3E1 Kabel FO Abnormal
Lanjut Cek/replace kabel FO (Titok,Deden)


2024-06-22
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan WORKSHOP-CIVA Inspeksi Tools CIVA
Inspeksi Tools Civa, Area Workshop Civa
(Yana, Eka)
2024-06-22
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan RAWMILL-BLENDING-PREHEATER Inspeksi Tools CIVA
Inspeksi Tools dan Taging tools Civa 
Area Blending PH, Rawmill 
(Rizky, Hariyanto)


2024-06-21
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan 404-3E1 Kabel FO Abnormal
Lanjut pengecekkan kabel FO (Titok, Deden)
2024-06-21
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan L64-BF1 Cek Backfilter
Cek Backfilter (Yana)

2024-06-21
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan L34-BC2 Lampu mati
Ganti lampu TL, no 2,3,7,8,10,11,19 dari belakang (Rizky)


2024-06-21
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan 394-RF2,RF3,RF6,RF7 Motor dan LCS kotor
Clean up motor dan panel LCS (Rizky, Supriadi Eve)


2024-06-21
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Complete data check sheet WBI grounding and lightning 2024
Completing data check sheet WBI grounding and lightning 2024 and scan file save at server ( EMIS & ADI )
2024-06-21
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Complete data wiring input/output
Completing data wiring I/O panel ( AGUS & PENY )
2024-06-21
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP- TPM 463 KL1 Tyre 3 complete data AM, safety and focus improvement, house keeping at local
Completing data TPM for AM, safety and focus improvement also print out file put at dash board . Do house keeping at local ( YOGA & RIZAL & EVE RIZKY )
2024-06-21
1 year ago
NR.EL-01 Wahyu Adi Triono EX-393-SC6-AND-BLOWER-PORTABLE Recondition motor and install cover fan
Recondition motor Ex 393 SC6, installing cover fan for blower portable ( ANDRI & FIRMAN )
2024-06-21
1 year ago
NR.EL-01 Wahyu Adi Triono 483-BL5 Replace grease tank for Auto Lubrication
Replacing grease tank of AUTO Lubrication with maximum level grease. Refiiling low grease tank to maximum level grease at work shop ( PENY & ADI )
2024-06-20
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan 394-CV2_3_4,-394-RF2_3_4 LCS kotor
394CV2/3/4, 394 RF2/3/4
LCS kotor, clean up panel LCS (Rizky, Supriadi Eve)
2024-06-20
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan 364-MS1 Motion Abnormal
Motion sensor abnormal, cek  kontrol motion (Yana)


2024-06-20
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan ER-4 Kabel FO Abnormal
Kabel FO Abnormal, relokasi kabel FO (Titok, Deden)


2024-06-20
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan 394-FA5 Motor bearing kasar
Motor bearing kasar, bongkar motor, ganti bearing, instal motor (Hariyanto, Eka, Amun)


2024-06-20
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan 464-FX4 Motor short (terbakar)


2024-06-20
1 year ago
NR.EL-01 Wahyu Adi Triono L3C-RE1 PM reclaimer coal check or clean up all LCS, proximity Harrow and another thing
PM reclaimer coal check proximity Harrow, clean up LCS, clean up others instrumentation sensor ( RIZAL & EVE RIZKY )
2024-06-20
1 year ago
NR.EL-01 Wahyu Adi Triono LEC-RE1 PM reclaimer coal replace cable Harrrow and control also change roller postion
PM reclaimer coal replace harrow cable and control also change roller position ( AGUS & PENY & ANDRI & FIRMAN )
2024-06-20
1 year ago
NR.EL-01 Wahyu Adi Triono L3C-RE1 PM reclaimer coal Clean up panel room
PM reclaimer coal clean up panel room from coal dust process use hand blower ( YOGA & IMAN )
2024-06-20
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Completing data check sheet WBI Panel Welding and Lighting 2024
Completing data check sheet WBI panel grounding, welding and lighting year 2024 continue scan also save data at server( ADI & EMIS )
2024-06-19
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan 394-SC1 Panel tidak terpakai
Bongkar panel tidak terpakai (Rizky, Anton, Eka)


2024-06-19
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan COOLER Transmitter menggangu area mekanik
Relokasi transmiter (Titok, Deden)
2024-06-19
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan RAWMILL PMR Critical Motor dan Elinst Rawmill
PMR Service Critical Motor dan Elinst area Rawmill (Hariyanto)


2024-06-19
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan 394-CV5-RF5 Motor dan LCS kotor
Clean up motor dan panel LCS (Rizky)
2024-06-19
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Service motor
Clean up body motor from dirt of dust use instrument air supply and equipment cleaning tools ( FIRMAN & ANDRI )
2024-06-19
1 year ago
NR.EL-01 Wahyu Adi Triono 443-PH1 WBI top blending, CT, PH and KILN
WBI top blending, CT, PH and KILN. Clean up motor use cloth from dirt of dust ( PENY & EVE RIZKY )
2024-06-19
1 year ago
NR.EL-01 Wahyu Adi Triono L63-RM1 PMR service analyzer
PMR service analyzer, such as clean probe, filter probe, sample line, diaphragma pump, filter balston, dryer gas. Check filter humidity sensor replace if found bad condition ( RIZAL )
2024-06-19
1 year ago
NR.EL-01 Wahyu Adi Triono 443-2K1-&-463-2K1 PMR service analyzer
PMR service analyzer, such as clean up probe, filter probe, sample line, diaphragma pump, filter balston, dryer gas from dirt of dust. Check filter humidity sensor replace with spare if found bad condition ( AGUS )
2024-06-19
1 year ago
NR.EL-01 Wahyu Adi Triono 363-RM1 WBI feed bin RM, CT and 423 BF1
WBI area feed bin, RM, CT and 423 BF1. Clean up area motor from dirt of dust process use instrument air supply ( YOGA )
2024-06-19
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Completing data sheet WBI 363 RM1
Completing data check sheet WBI 363 RM1 of Feed bin-Raw Mill-CT-Bag Filter years 2023 ( EMIS & ADI)
2024-06-18
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan 394-RF11 Motor dan LCS kotor
Clean up motor dan panel LCS (Rizky)
2024-06-18
1 year ago
NR.EL-01 Wahyu Adi Triono COOLER-NORTH-SIDE-AND-333-HD1 Dismantle lamp that hit scafolding and repair or replace lamp that is off
Dismantle lamp of 473 north side and replace lamp test lamp result on ( FIRMAN & ANDRI )
2024-06-18
1 year ago
NR.EL-01 Wahyu Adi Triono 423-2K1 PMR service CEMS
PMR service CEMS. Clean up filter purge air unit  dust hunter and flowsic 100, transducer A & B flowsic 100, swivel window T/R & R dust hunter also alignment dust hunter. Clean up CEMS room and filter dust cabinet ( RIZAL & EVE RIZKY )
2024-06-18
1 year ago
NR.EL-01 Wahyu Adi Triono 363-RM1 PMR service medium voltage motor
PMR service medium voltage motor. Clean area and filter motor from dirt of dust use instrument air supply. Measure vibration-noise and temperature free and load side motor. Add grease 30 times and 15 times for FS & LS motor ( AGUS )
2024-06-18
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP completing data check sheet WBI and PMR
Completing data sheet WBI and PMR year 2023 and 2024, continue scan safe at server computer ( ADI & EMIS )
2024-06-18
1 year ago
NR.EL-01 Wahyu Adi Triono 443-EL1 PMR service elevator
PMR service elevator, clean up room of elevator and cage. Test functional elevator from 8th to 1st floor. Result good ( PENY & YOGA )
2024-06-18
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan GCT Lampu area GCT mati
Service lampu area GCT (Titok, Deden)
2024-06-18
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan WELDING-PREHEATER Socket 1 Phasa rusak
Ganti socket 1 Phasa panel welding area Preheater (Anton)


2024-06-18
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan BLENDING-SILO Level Material eror
Check, dan clean up coating sensor Level Material Blending Silo Timur dan Barat (Rizky, Yana)


2024-06-14
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan 4D4 Lampu mati
Ganti lampu selancar area 4D4 (Hariyanto, Anton)
2024-06-14
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan IKGA-AN3 Filter tembus (Probe rembes)
Ganti Probe IKGA (Yana)
2024-06-14
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan COALMILL PMR Service Critical Motor
PMR Service Critical Motor Coalmill (Hariyanto)

2024-06-14
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Completing data check sheet PMR IR TAD-CCTV-Tscanner-Pyrometer and PM 363 MD1
Completing data check sheet PMR  IR TAD-CCTV-T Scanner, Pyrometer and PM 363 MD1. Continue scan also save at computer ( ADI & EMIS )
2024-06-14
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Replace burned motor
Replace burned motor with spare motor ( FIRMAN )
2024-06-14
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Test run motor and put at ware house after finish
Test run motor and put at ware house for motor ( RIZAL & YOGA )
2024-06-14
1 year ago
NR.EL-01 Wahyu Adi Triono 363-WS1 Continue connection
Connection cable panel I/O ( PENY & EVE RIZKY )
2024-06-14
1 year ago
NR.EL-01 Wahyu Adi Triono 363-MD1 Replace carbon brush and clean up carbon brush
Clean up and replace carbon brush ( AGUS & ANDRI )
2024-06-14
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan 474-EP1 PMR Steck
PMR Service Steck Cooler (Titok)
2024-06-14
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan 394-SC4 Motor dan LCS kotor
Clean up Motor dan panel LCS (Rizky)
2024-06-14
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan 394-RF8 Motor dan LCS kotor
Clean up Motor dan panel LCS (Rizky)

2024-06-14
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan L64-RM1 Lampu mati
Ganti lampu atas Panel Liquid (Anton, Eka)
2024-06-14
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan RECLAMER-COALMILL WBI Electric dan Instrument
WBI Electric dan Instrument Reclamer dan Coalmill atas (Rizky)
2024-06-13
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Make and completing data check sheet calibration damper and speed
Make data sheet and completing check sheet calibration damper and speed ( YURIZAL )
2024-06-13
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Replace burned motor blower for yellow blower motor
Replace motor blower with spare motor for yellow motor blower ( MUL )
2024-06-13
1 year ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Completing data check sheet PMR service medium voltage motor
Completing data sheet PMR service medium voltage motor ( ADI )
2024-06-13
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan RAWMILL PMR Critical Motor dan Elinst Rawmill
PMR Critical Motor dan Elinst RawMill (Hariyanto)
2024-06-13
1 year ago
NR.EL-01 Wahyu Adi Triono L63-RM1- PMR service analyzer
PMR service analyzer such as clean up probe, filter probe, diaphragm pump, filter balston, dryer gas from dust of coal. Check filter humidity sensor replace if found bad condition with spare filter ( YOGA & EVE RIZKY )
2024-06-13
1 year ago
NR.EL-01 Wahyu Adi Triono 363-WS1 Continue connection I/O and install solenoid valve
Connect cable at I/O panel and install solenoid valve ( PENY & MUL & AGUS & ANDRI )
2024-06-13
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan WELDING-LIGHTING-PREHEATER WBI panel Welding dan Lighting
WBI Welding Panel dan Lighting Area Preheater (Yana)

2024-06-13
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan CLINKER-COALMILL WBI Electric dan Instrument
WBI Elinst Clinker Silo dan Coalmill Bawah (Rizky)


2024-06-13
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan 4D4-RF3 Motor dan panel LCS kotor
Clean up Motor dan panel LCS (Rizky)

2024-06-13
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan 424-EP1 PMR Service Cems
Service CEMS (Rizky, Deden)

2024-06-12
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan WORKSHOP Fabrikasi Panel dan Service Vacum
Lanjut Fabrikasi Panel dan Service Vacum dari ER4 (Hariyanto, Amun)
2024-06-12
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan COALMILL Service lampu
Service Lampu area Pister Feeder (Anton, Eka)
2024-06-12
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan 444-2K2-DAN-2K1 PMR Service Analyzer
Service Analyzer AN1 dan AN2 (Yana, Deden)
2024-06-12
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan 4D4-PP1 Motor dan LCS kotor
Clean up Motor dan panel LCS (Rizky)


2024-06-12
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan 4D4-BL2 Motor dan LCS kotor
Clean up Motor dan panel LCS (Rizky)
2024-06-12
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan 394-RF9 Motor dan LCS kotor
Clean up Motor dan Panel LCS (Rizky)


2024-06-12
1 year ago
NR.EL-02 Rizky Fauzy Ramadhan 394-CV7 Motor dan LCS kotor
Clean up Motor dan panel LCS (Rizky)
2024-06-12
2 years ago
NR.EL-01 Wahyu Adi Triono 363-WS1 Termination I/O and solenoid valve
Termination cable at I/O panel and solenoid valve ( PENY & ANDRI )
2024-06-12
2 years ago
NR.EL-01 Wahyu Adi Triono 443-EL1 Repair door elevator 1st floor
Repair door of elevator at 1st floor service limit switch for door. Test run elevator functional from 8th to 1st floor result ok ( AGUS & EVE RIZKY )
2024-06-12
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1 PMR service IR TAD, CCTV, T Scanner, Pyrometer
PMR service IR TAD, CCTV, T scanner, Pyrometer such as clean area equipment, lens, probe from dirty dust process ( YOGA )
2024-06-12
2 years ago
NR.EL-01 Wahyu Adi Triono 463-2K1-AND-443-2K1 PMR service analyzer
PMR service analyzer. Clean up probe, filter probe, sample line, diaphragm pump, filter balston, dryer gas from dirty dust. Check filter humidity sensor replace filter if found bad with spare filter ( RIZAL )
2024-06-12
2 years ago
NR.EL-01 Wahyu Adi Triono 363-RM1-463-KL1-L63-RM1--WS-ELCTRIC-NR1 Check rubbish bin for B3-scrap and domestic must right at its placement
Check rubbish bin at local, bring bad rubbish bin to scrap room of environment department. Bring god bin to local and make name of rubbish bin for RED-GREEN and YELLOW ( ADI & EMIS & CIVACON MUL )
2024-06-12
2 years ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Completing data check PM 363 MD1 and PMR service motor and pyrometer
Completing data check sheet PM 363 MD1 and PMR service mv motor and pyrometer 
2024-06-11
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan IKGA-AN3 Cek Analyzer
Cek Analyzer (Yana)
2024-06-11
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan LIFT-PH Oli rel lift
Fabrikasi oli rel Lift (Yana)

2024-06-11
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan WORKSHOP Fabrikasi Panel LBS
Lanjut Fabrikasi Panel LBS
(Amun, Hariyanto)
2024-06-11
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan KILN PMR Critical Motor dan Elinst Kiln
PMR Critical Motor dan Elinst Kiln
(Hariyanto)
2024-06-11
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan BURNER-COOLER Camera Baru Burner kurang jelas, lampu area Burner dan Cooler ada mati
Cek Camera baru Burner,
Ganti lampu area Burner,
Ganti lampu area Cooler
(Titok, Deden)


2024-06-11
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan 394-SC5 Motor dan LCS kotor
Clean up Motor dan panel LCS (Rizky, Anton, Eka)
2024-06-11
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan 394-RF12 Motor dan LCS kotor
Clean up Motor dan panel LCS (Rizky, Anton, Eka)

2024-06-11
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan RAWMILL Lampu selancar atas pintu Rawmill mati
Ganti lampu selancar atas pintu Rawmill (Rizky, Anton, Eka)
2024-06-11
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan 364-BC6 Lampu Selancar mati
Ganti lampu selancar, (Rizky, Anton, Eka)


2024-06-11
2 years ago
NR.EL-01 Wahyu Adi Triono 363-WS1 Connect cable motor and LCS, pulling cable solenoid and LCS
Pulling cable solenoid valve and LCS, connect cable motor and LCS ( PENY & ANDRI & FIRMAN )
2024-06-11
2 years ago
NR.EL-01 Wahyu Adi Triono 423-2K1 PMR service CEMS
PMR service CEMS. Clean up filter purge air unit for dust hunter and flowsic. Clean up transducer A and B flowsic, swivel window T/R and R dust hunter also alignment dust hunter, clean up CEMS room, and filter cabinet MCS 100 E ( YOGA )
2024-06-11
2 years ago
NR.EL-01 Wahyu Adi Triono 363-RM1 PMR service motor
PMR service medium voltage, clean up area and filter motor. Measure vibration-noise and temperature free side and load side, add grease from 10 times to 30 times for free and load side motor if found vibration > 4 mm/s and noise > 2 gE ( AGUS )
2024-06-11
2 years ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Completing data check sheet PM 363 MD1 and PM Weigh Feeder
Completing data check sheet PM 363 MD1 and PM Weigh Feeder ( ADI & EVE RIZKY )
2024-06-10
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan WORKSHOP Panel LBS
Prepare plate, dan fabrikasi panel LBS (Hariyanto,Amun, Anton)
2024-06-10
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan 464-FXK Motor bearing kasar
Bongkar motor, Ganti bearing motor, instal motor (Hariyanto, Amun, Anton)
2024-06-10
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan IKGA-AN3 PMR Service
PMR Service (Yana)
2024-06-10
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan L74-RF1 Lampu area tangga mati
Ganti lampu (Rizky, Deden)
2024-06-10
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan L94-RF1 Lampu mati
Ganti lampu (Rizky, Deden)
2024-06-10
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan L64-BF1 Lampu mati
Ganti lampu (Rizky, Deden)
2024-06-05
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan RAWMILL-N2 PMR Critical Motor dan Elinst Rawmill
PMR Critical Motor dan Elinst Rawmill (Hariyanto)
2024-06-05
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan FEEDBIN-RAWMILL-N2 PMR Safety Device area Feedbin dan Rawmill (BC,WF)
Cek all Safety Device area Feedbin dan Rawmill (BC,WF),  croscek WF (Anton,Eka)
2024-06-05
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan 364-BC3 Indikasi Ready BD bermasalah
Cek indikasi Ready BD (Yana, Davin EVE)
2024-06-04
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan LIFT-PH-N2 Lampu area lift bawah mati, dan PMR sump pump
Ganti lampu dan tes sump pump (Yana, Deden)
2024-06-03
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan CO2-SYSTEM CO2 cepat habis
Cek CO2 system (Titok,Eka)
2024-06-03
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan CEMS-ER4 CEMs room dan ER 4 area genset kotor
Clean up CEMs room dan ER 4 area genset kotor (Anton,Amun,Deden)
2024-06-07
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan 334-WF3,4-334-SX3,4 Panel LCS kotor
Clean up panel (Rizky)
2024-06-07
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan 464-FXAM2 Lampu selancar tidak terpakai
Bongkar lampu (Rizky)
2024-06-07
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan ER4 PMR MCC Load
PMR MCC Load (Rizky)
2024-06-06
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan KILN-EPCOOLER-COOLER WBI inspection
WBI inspection (Rizky)
2024-06-06
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan 474-CC1 Panel 1 Phasa tidak safety hanya digantung
Bongkar panel (Rizky)
2024-06-06
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan 474-CC1 Panel 1 Phasa area atas kotor
Clean up panel (Rizky)
2024-06-05
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan VIBRO-SILO-BINFEED Panel vibro kotor
Clean up panel dan instal kanopi (Rizky,Amun, Ahmad EVE)
2024-06-05
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan 334-AC2-SX2 Panel motion mitronic kotor dan tertimpa material
Clean up panel dan instal kanopi (Rizky,Amun,Ahmad EVE)
2024-06-05
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan 334-SX1 Tutup fan motor, lepas
Pasang kembali tutup fan motor (Rizky,Ahmad EVE)
2024-06-05
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan 334-AC1 Panel load cel kotor dan tidak tertutup
Clean up dan tutup panel (Rizky,Ahmad EVE)
2024-06-05
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan 334-BC2 Lampu TL no 3 dari belakang mati
Ganti lampu (Rizky, Ahmad EVE)
2024-06-05
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan 334-BC1 Lampu TL no,5/6/9 dari belakang mati
Ganti lampu (Rizky,Ahmad EVE)
2024-06-04
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan 414-BL1 Lampu area BL mati (gelap)
Clean up panel dan kasih kanopi (Rizky,Amun)
2024-06-03
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan 394-RF4 Panel LCS miring, support rusak
Repair support tiang LCS (Rizky,Amun)
2024-06-03
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan 394-RF2 Panel LCS miring, support rusak
Repair support tiang LCS (Rizky,Amun)
2024-06-03
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan IKGA-AN3-N2 Oksigen tinggi, kebocoran pada salah satu SV Purging
SV Purging 1 dilepas, tunggu order, sementara pakai Purging 2 (Yana, Rizky)
2024-05-31
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan LIFT-PH Pintu lift, roller lepas dan rusak, list pintu rusak
Ganti roller dan list pintu (Yana, Rizky, Deden)
2024-06-10
2 years ago
NR.EL-01 Wahyu Adi Triono 443-CT1 Replace solenoid that is not work and pressure switch
Replace solenoid valve and pressure switch. Prepare canopy for pressure switch continue install at local ( RIZAL & ANDRI )
2024-06-10
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1 PMR service medium voltage motor
PMR service medium voltage motor, clean up area and filter motor from dirty use instrument air supply. Measure vibration-noise and temperature free and load side motor. Add grease 10 to 15 times for free side and load side if found vibration > 4 mm/s and noise > 2 gE ( PENY )
2024-06-10
2 years ago
NR.EL-01 Wahyu Adi Triono 363-WS1 Install LCS and connect cable to motor
Prepare canopy of LCS. Install LCS at local  ( YOGA & FIRMAN )
2024-06-10
2 years ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP completing data check sheet WBI
Completing data check sheet WBI 
2024-06-07
2 years ago
NR.EL-01 Wahyu Adi Triono 363-WS1 Pulling cable to ER3
pulling cable from bottom CT to ER3 ( ALL crew )
2024-06-06
2 years ago
NR.EL-03 Bayu Kiln Saputro MAINGATE-BUILDING AC mati di ruangan induksi akses kontrol
Disconnect sambungan untuk AC
Pulling kabel baru khusus untuk AC 
Connect ke MCB dan stop kontak AC
Test OK
2024-06-06
2 years ago
NR.EL-03 Bayu Kiln Saputro M3A-WP3 MC lengket
Perbaikan cubicle MCC
Ganti MC dari ABB 80A ke LS 100A
Ganti MCCB dari ABB ke Schneider, buat lubang dudukan baru
Ganti kabel out MCCB ke MC
2024-06-06
2 years ago
NR.EL-01 Wahyu Adi Triono L1C-BC7-SHUTTLE Clean up panel control and PLC tripper
Clean up panel control and PLC tripper from dirty coal dust ( RIZAL & EVE RIZKY )
2024-06-06
2 years ago
NR.EL-01 Wahyu Adi Triono L1C-BC7-SHUTTLE Clean up motor brake, area motor and panel
Clean up motor brake, area motor and panel from coal dust process. Install lamp 1 each test on result ok ( PENY & FIRMAN )
2024-06-06
2 years ago
NR.EL-01 Wahyu Adi Triono L1C-BC7 Clean up rail cable and tray
Clean up rail cable and tray also all panel at south side from coal dust process with instrument air and hand blower ( AGUS & ANDRI )
2024-06-06
2 years ago
NR.EL-01 Wahyu Adi Triono L1C-BC5-AND-BC7 Check water spray
Test functional water spray, at L1C BC7 found contact solenoid valve is not function well, replace limit switch with spare test functional result ok. L1C BC5 test functional found stick flapper is not long enough, replace stick flapper with spare test functional result ok ( YOGA & ADI )
2024-06-05
2 years ago
NR.EL-03 Bayu Kiln Saputro MAINGATE-BUILDING AC mati di ruangan induksi akses kontrol
Ruangan induksi di akses kontrol AC tidak bisa dinyalakan bareng (2Ea AC)
Cek MCB untuk 1 ruangan (2 AC, lighting ruangan dan TV)
Preparing jalur kabel untuk tarikan baru
2024-06-05
2 years ago
NR.EL-03 Bayu Kiln Saputro D3A-CP3 Tidak bisa loading, indikasi display sudah loading
Cek piston load unload belum buka
cek tegangan di socket solenoid 0 Vac
cek dipanel kontrol kabel untuk solenoid lepas diterminal
perbaikan kabel dan kencangkan terminasi
test run ok
2024-06-05
2 years ago
NR.EL-01 Wahyu Adi Triono 393-SC1-AND-363-LQ2 Test run and service motor
Test run motor and service motor ( PENY & AGUS )
2024-06-05
2 years ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Prepare canopy motor
Fabrication canopy motor ( FIRMAN & ANDRI )
2024-06-05
2 years ago
NR.EL-01 Wahyu Adi Triono 443-CT1 Check pressure switch
Check pressure switch at local compare with CCR ( RIZAL & YOGA & Production & MUKLAS )
2024-06-05
2 years ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Complete data check sheet PMR analyzer
Completing data PMR analyzer check sheet ( ADI & EVE RIZKY )
2024-06-05
2 years ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Repaire and replace bearing motor. Clean up motor 30 KW
Repaire and replace bearing motor also clean up motor 30 KW ( FIRMAN & EVE RIZKY )
2024-06-04
2 years ago
NR.EL-01 Wahyu Adi Triono 443-2K1-&-463-2K1 PMR service analyzer
PMR service analyzer, such as clean up probe and flange, filter probe, sample line, membran pump, balston filter, dryer gas. Check filter humidity, replace filter if found bad condition ( RIZAL )
2024-06-04
2 years ago
NR.EL-01 Wahyu Adi Triono 473-HC1 Install AUTO lubrication
Install AUTO lubrication ( PENY & ANDRI )
2024-06-04
2 years ago
NR.EL-01 Wahyu Adi Triono 423-2K1 PMR service CEMS
PMR service CEMS, such as clean up filter purge air unit dust hunter and flowsic 100. Clean up transducer A & B Flowsic 100 and swivel window transducer and reflector also reflector Dust Hunter. Clean up CEMS room and gas botle gas room also filter cabinet MCS 100 E ( YOGA )
2024-06-04
2 years ago
NR.SHIFT Wahyu Adi Triono 363-RM1 PMR service medium voltage motor
PMR service medium voltage. Clean up area and filter motor. Measure vibration, noise and temperature free and load side motor. Add grease 10 times to 30 times for free and load side motor ( AGUS )
2024-06-04
2 years ago
NR.EL-03 Bayu Kiln Saputro TRAFO-NAR2 Drum Oli Trafo berantakan
Rapihkan drum oli (pindahkan dari OTR A ke Trafo OTR B)
Clean up Area Trafo dan MSS

2024-06-04
2 years ago
NR.EL-03 Bayu Kiln Saputro 66B-CX4 Pemasangan kompresor baru
Commisioning dan Test Run
Pressure 5,7 Bar
Cek tegangan input kompresor 373 Vac
Cek Arus Input kompresor 300 A
  • nameplate main motor 323A
  • nameplate cooling fan 5.5A (2Ea)
2024-06-03
2 years ago
NR.EL-03 Bayu Kiln Saputro GENSET-NAR2 Banyak Ceceran Oli
Clean up ceceran oli di lantai dan body genset
Perbaikan kebocoran oli pada baud dengan threebond dan bold tightenning
2024-06-03
2 years ago
NR.EL-03 Bayu Kiln Saputro 66B-CX4 Pemasangan kompresor baru
Tie in Kabel Input breaker cubicle MCC ke Bar
Pasang scun kabel tarikan LCS ke Kompresor
Connect kabel di LCS dan di terminal input kompresor
2024-06-03
2 years ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP complete data wiring panel I/O area raw mill and preheater
Completing data wiring I/O of raw mill and preheater ( AGUS )
2024-06-03
2 years ago
NR.EL-01 Wahyu Adi Triono 463-2K1 Problem probe often retract but there is alarm when inside probe
Service analyzer, found valve safety relief late work when energize ( RIZAL )
2024-06-03
2 years ago
NR.EL-01 Wahyu Adi Triono 363-HS1 Replace lamp at room of HS
Replace lamp that are off with new spare lamp. Test on result ok ( ANDRI & ENDEN )
2024-06-03
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1 PMR service critical motor and LSR
PMR service critical motor and LSR. Clean up area and filter motor, measure vibration-noise and temperature free and load side motor. Add grease from 5 times to 10 time for free and load side if found vibration > 4 mm/s also noise > 2 gE ( PENY & ADI & EVE RIZKY )
2024-06-01
2 years ago
NR.EL-03 Bayu Kiln Saputro D3A-CP3 Display Mati
Cek panel MCB kontrol trip
ada bau coil MC overheat
ganti main MC, test simulasi saat pindah ke delta MC delta tidak energize
preparing lubang dudukan semua MC
ganti semua MC dari Schneider ke LS
kabel motor cooling fan dan kabel input untuk kontrol ada indikasi overheat di tapping input MC delta
ganti kabel input motor cooling fan dan rewiring kabel input kontrol
test run OK
2024-05-31
2 years ago
NR.EL-03 Bayu Kiln Saputro 66B-CX4 Pemasangan kompresor baru
Preparing kabel 240 mm
preparing kabel 95 mm
pabrikasi kabel tray LCS ke Kompresor
Install kabel tray
pulling kabel 240 mm lcs ke kompresor
ganti breaker cubicle MCC dari 400 A ke 680 A
2024-05-30
2 years ago
NR.EL-03 Bayu Kiln Saputro LIGHTING-JALAN Lampu Mati
Lampu jalan area trucklift sampai arah reclaimer batubara mati
ganti lampu 4 tiang
test OK
2024-05-31
2 years ago
NR.EL-01 Wahyu Adi Triono 363-RM1-&-443-PH1 Completing data wiring panel Input and output
COmpleting data wiring panel for I/O ( AGUS & PENY )
2024-05-31
2 years ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP-PLANT-BUILDING Inspection electrical and welding tools
Inspection electrical and welding tools. Repaire cable extention cable, portable lamp, grinding machine, drilling machine, and cutting machine full fill standard company ( ADI & YOGA & EVE RIZKY )
2024-05-31
2 years ago
NR.EL-01 Wahyu Adi Triono 393-FA5A Replace bearing motor
Replace bearing motor ( RIZAL & ANDRI & FIRMAN )
2024-05-29
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan WS-N2-AREA-FABRIKASI-MEKANIK Butuh lampu penerangan
Tambah lampu penerangan 
2024-05-29
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan 334-BC1 Lampu Mati dan Tidak Terpakai
Bongkar Lampu (Untuk di Repair)
2024-05-29
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan 334-BC2 Lampu Mati dan Tidak Terpakai
Bongkar Lampu (Untuk Di Repair)
2024-05-30
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan 364-BC1 Motor Selalu Tertimbun Material (Sirkulasi fan abnormal)
Clean Up Motor dan kasih Kanopy (Penghalang)
2024-05-30
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan 364-SR1 Socket Legrand panel 1 Phasa rusak (3 buah)
Ganti Socket Legrand Panel
2024-05-30
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan 364-SR1 Lampu TL atas pompa Grease mati
Ganti Lampu
2024-05-30
2 years ago
NR.EL-01 Wahyu Adi Triono INPUT-AND-OUTPUT-COOLER Pulling cable profibus
pulling cable profibus ( ANDRI )
2024-05-30
2 years ago
NR.EL-01 Wahyu Adi Triono L63-RM1- PMR service analyzer
PMR service analyser such as clean up probe, sample line, filter probe, membran pump. balston filter, dryer gas from dust coal ( RIZAL & YOGA )
2024-05-30
2 years ago
NR.EL-01 Wahyu Adi Triono 443-WB1 Dismantle motor
Dismantle motor and bring to work shop ( PENY & ADI & FRIMAN & ANDRI )
2024-05-30
2 years ago
NR.EL-01 Wahyu Adi Triono 393-FA5-&-433-RF1 Prepare spare motor
Preparing spare motor ( PENY & ADI & FIRMAN & ANDRI )
2024-05-30
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1 Replace gun grease
Check at local, do refilling grease and change battery for auto gun grease ( AGUS & EVE RIZKY )
2024-05-29
2 years ago
NR.EL-01 Wahyu Adi Triono 473-FA1-2 Move cable I/O
Move cable I/O ( RIZAL & YOGA )
2024-05-29
2 years ago
NR.EL-01 Wahyu Adi Triono TPM-463-KL1-TRYE-3 Assesment
Accompany judge for assesment TPM at work shop and local area ( YOGA & RIZAL )
2024-05-29
2 years ago
NR.EL-01 Wahyu Adi Triono L1C-BC4 Replace lamp that is off
Replace lamp that is off. Test on result ok ( AGUS & FIRMAN )
2024-05-29
2 years ago
NR.EL-01 Wahyu Adi Triono 443-FN1-P1 Draft value showing 0
Check draft at local compare at CCR ( RIZAL & YOGA & EVE RIZKY )
2024-05-29
2 years ago
NR.EL-01 Wahyu Adi Triono L63-RM1 WBI electrical and instrumentation
WBI electrical and instrumentation ( PENY & EVE RIZKY )
2024-05-29
2 years ago
NR.EL-01 Wahyu Adi Triono WORK-PLANT-BUILDING Inspection electrical and welding tools
Inspection electrical and welding tools. Repaire cable power electrical tools such as drilling machine, extention cable, portable lamp. cutting machine to company standard ( ADI & ANDRI )
2024-05-28
2 years ago
NR.EL-03 Bayu Kiln Saputro LIGHTING-JALAN Area Trucklift Lampu Mati
* Cek lampu jalan area trucklift
  • mcb tidak ada yg trip
  • lampu jalan menyala hanya 1 mata dari 3 mata dan juga ada yang mati total (total lampu ada 6 tiang)
* Cek lampu jalan area office afr sebelah trucklift
  • lampu sorot ada yang mati
  • cek panel ada yang trip, onkan mcb OK
2024-05-28
2 years ago
NR.EL-03 Bayu Kiln Saputro 444-CX2 Indikasi Sensor Abnormal
* Indikasi sensor air filter bintang-bintang
  • cek flexible kempot saat kompresor loading
  • saat diposisikan unload indikasi airfilter terbaca
* Indikasi DP separator bintang-bintang
  • flushing tubing
  • ganti sensor
  • test OK
  • coba bongkar sensor dp separator ex 444-cx2, sensor basah dan kabel ada yg putus
2024-05-28
2 years ago
NR.EL-01 Wahyu Adi Triono 333-MS1 Oil come inside motor. Replace bearing motor metal separator
Clean up area motor stator and rotor use special liquid, replace bearing 6206 2 each and 6303 1 each. Install back al local ( PENY & ANDRI & FIRMAN & ADI )
2024-05-28
2 years ago
NR.EL-01 Wahyu Adi Triono 463-2K1-&-443-2K1 PMR service analyzer
PMR service analyzer such as cleaning probe, filter probe, membran pump, filter balston, dryer gas, sample line from dirty ( YURIZAL )
2024-05-28
2 years ago
NR.EL-01 Wahyu Adi Triono TPM-463-KL1-TYRE-3 Complete data TPM and make basket cage for equipment cleaning tools
Completing data TPM and prepare basket cage for equipment cleaning tools also painting green color ( YOGA & EVE RIZKY )
2024-05-28
2 years ago
NR.EL-01 Wahyu Adi Triono 363-RM1 PMR service medium voltage motor
PMR service medium voltage motor, clean up area and filter. Measure vibration-noise-temperature at free and load side. Add grease 20 to 30 times for free and load side if found vibration up to 4 mm/s and noise up to 2 gE ( AGUS )
2024-05-28
2 years ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP-MECHANIC-NR1 Inspection electrical and welding tools
Inspection electrical and welding tools. Repaire cable for extention cable, grinding machine, cutting machine, drilling machine ( ADI & FIRMAN & ANDRI )
2024-05-28
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1-TYRE-3- TPM complete data absention, AM, safety, FI 2nd theme
Complete data absention, AM, safety and Focus Improvement and theme ( PENY & YOGA & YURIZAL )
2024-05-28
2 years ago
NR.EL-01 Wahyu Adi Triono 423-2K1 PMR service CEMS
PMR service CEMS, such as clean up filter purge air unit, transducer A & B, swivel window T?R & R alignment dust hunter, room CEMS and bottle gas ( RIZAL )
2024-05-28
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1 PMR service medium voltage motor
PMR service medium motor, clean up area and filter motor.  Measure vibration-noise and temperature for free and load side, add grease 10 to 15 times at free and load side motor ( AGUS )
2024-05-27
2 years ago
NR.EL-03 Bayu Kiln Saputro TRAFO-NAR1_2 WBI
WBI Trafo MV OTR 2, 3, 301, 302, A, B
2024-05-27
2 years ago
NR.EL-03 Bayu Kiln Saputro M3A-WP3 trip breaker di MCC
Cek kontaktor lengket
cek motor ground
discouple dan disconnect kabel power motor
bawa ke workshop untuk perbaikan (rewinding)
drawout cubicle mcc bawa ke workshop untuk perbaikan
2024-05-27
2 years ago
NR.EL-03 Bayu Kiln Saputro M3A-WP1 Motor Ground
Install motor di lokal 
(setelah service rotor dan stator karena karat, ganti bearing 2 x 6214 zz, ganti cooling fan karena rusak, retapping lubang untuk baud kabel ground dan cover, perbaikan dudukan cover fan)
test putaran motor
cek arus noload  fasa R=34 A; S=36 A; T=37 A
2024-05-24
2 years ago
NR.EL-03 Bayu Kiln Saputro M3A-WP1 Motor Ground
Discouple dan disconnect kabel power motor
bawa ke workshop
bongkar motor, coil motor basah
panaskan motor dengan heater
2024-05-24
2 years ago
NR.EL-03 Bayu Kiln Saputro M34-WP5 Trip Breaker di MCC
Cek resistan coil motor OK
Cek resistan isolasi motor OK
Cek induktansi motor unbalance nilainya
buka cover motor bau coil motor overheat
discouple motor dan disconnect kabel power
bawa ke workshop untuk di rewinding
2024-05-22
2 years ago
NR.EL-03 Bayu Kiln Saputro 444-CX2 Arah Putaran Motor Terbalik
Test run setelah rewinding motor
Balik arah putaran main motor
test run
cek tegangan saat kompresor unloading 350 Vac balance
2024-05-24
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1-TYRE-3 TPM gemba area 5R, install sign safety
Clean up area 5R, install guarding shell cooling fan and  sign safety ( ALL Crew Electric )
2024-05-24
2 years ago
NR.EL-01 Wahyu Adi Triono ER5-&-ER6 Clean up ER and top panel MV, ACB and MCC
Clean up filter and electric room , top panel medium voltage and top panel trafo at ER5. Clean up include inside MCC and ACB ( IMAN & FIRMAN )
2024-05-24
2 years ago
NR.EL-01 Wahyu Adi Triono 473-GQ1 WBI KILN, Cooler, Burner Floor, Clinker Silo
WBI area KILN, COOLER, BURNER FLOOR, and CLINKER SILO ( YOGA & EVE RIZKY )
2024-05-24
2 years ago
NR.EL-01 Wahyu Adi Triono 443-PH1 WBI top blending, CT, Pre heater and KILN
WBI top blending, CT, Pre heater, and KILN ( PENY )
2024-05-24
2 years ago
NR.EL-01 Wahyu Adi Triono PPUP-INSPECTION-ELECTRICAL-AND-WELDING-TOOLS Inspection electrical and welding tools
Inspection electrical and welding tool of PPUP work shop ( ADI & ANDRI )
2024-05-22
2 years ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP-PPUP Check electrical and welding tools
Check electrical and welding tools, do some repaire cable for welding machine, extention cable, grinding machine, portable lamp because grounding cable are not connected ( ADI & FIRMAN & ANDRI )
2024-05-22
2 years ago
NR.EL-01 Wahyu Adi Triono 363-RM1 WBI electric and instrumentation
WBI electric and instrumentation ( PENY )
2024-05-22
2 years ago
NR.EL-01 Wahyu Adi Triono 463-2K1-AND-443-2K1 PMR service analyzer
PMR service analyzer such as. clean filter probe, probe, membran pum, filter baltson , dryer gas, filter humidity sesnor from dirt ( YOGA & EVE RIZKY )
2024-05-22
2 years ago
NR.EL-01 Wahyu Adi Triono 423-2K1- PMR service CEMS
PMR service CEMS such as clean up filter purge air unit, transducer A & B, swivel windows dust hunter ( YOGA & EVE RIZKY )
2024-05-22
2 years ago
NR.EL-01 Wahyu Adi Triono 463-2K1 Test gas NO
Test gas NO ( YOGA & EVE RIZKY )
2024-05-22
2 years ago
NR.EL-01 Wahyu Adi Triono L63-RM1 Replace vibration sensor
Replace vibration sensor. measure vibration at local compare with CCR ( AGUS & ANDRI )
2024-05-22
2 years ago
NR.EL-01 Wahyu Adi Triono 443-WI1-M3 Replace cable power motor 4c x 50 mm, connect cable and test run
Replace cable power motor, connect cable at LCS and motor, test run measure ampere motor result ok ( PENY & ADI & FIRMAN )
2024-05-21
2 years ago
NR.EL-03 Bayu Kiln Saputro ALBANNA-BUILDING Lampu sorot area parkir mati
Ganti lampu sorot LED 2 Ea
Test OK
2024-05-21
2 years ago
NR.EL-03 Bayu Kiln Saputro M04-LM1 Sensor belum di sambung ke I/O
Wiring kabel di panel PLC dan cubicle MCC
Pulling kabel dari LCS M04-WP8 ke M04-WP7
Pulling kabel dari LCS M04-WP7 ke Sensor
(kabel spare hanya ada 1 core di tiap LCS)
2024-05-21
2 years ago
NR.EL-03 Bayu Kiln Saputro RIVERPUMP-BUILDING Lampu Mati
Ganti lampu dari HPIT ke Lampu LED 200W 1 Ea
Test OK
2024-05-21
2 years ago
NR.EL-03 Bayu Kiln Saputro RIVERPUMP-BUILDING cctv mati
CCTV area pompa M04-WP1 s.d. 4 mati
Cek socket basah karena air hujan, ganti socket RJ45
install juction box
masukkan kabel ke juction box
test OK
2024-05-20
2 years ago
NR.EL-03 Bayu Kiln Saputro MAINGATE-BUILDING CCVT gambar tidak jelas
Coba clean up masih sama
coba ganti converter balun masih sama
coba lepas camera pasang lansung di DVR OK
kemungkinan kabel sudah rusak
preparing ip cam dan ukur kebutuhan kabel ethernet
2024-05-20
2 years ago
NR.EL-03 Bayu Kiln Saputro TRAFO-NAR1_2 WBI
WBI Trafo MV OTR 2, 3, 301, 302, A, B
2024-05-20
2 years ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP Install way of instrument air auto grease pump
Prepare pipe also make drut pipe( ADI & ANDRI )
2024-05-20
2 years ago
NR.EL-01 Wahyu Adi Triono 443-EL1 Replace V-belt and service limit switch door all from 1st to 8th
Replace v-belt, service l/s from 1st to 8th door ( PENY & FIRMAN )
2024-05-20
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1 PMR service IR TAD, camera burner, T scanner and CCTV
PMR service IR TAD temperature, CCTV, T scanner and camera burner. Clean up lens and probe ( RIZAL )
2024-05-20
2 years ago
NR.EL-01 Wahyu Adi Triono 363-RM1 PMR service medium voltage motor
PMR service medium voltage motor. Clean up area and filter motor, measure vibration-noise-temperature load and free side. Add grease 10 time to 20 times if found vibration > 4 mm/s also noise > 2 gE ( AGUS & EVE RIZKY )
2024-05-20
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1 PMR service medium voltage motor
PMR service medium voltage motor. Clean up area and filter motor, measure vibration-noise and temperature fix and load side motor. Add grease 5 time until 15 times if found vibration up to 4 mm/s and noise up 2 gE ( YOGA )
2024-05-17
2 years ago
NR.EL-03 Bayu Kiln Saputro EAST-HOUSING Panel Listrik Mess No1 Belum ada Grounding
Install Grounding Rod, cek resistan 1 ohm
pulling kabel panel distribusi ke grounding rod
connect kabel di panel dan grounding rod
Perapihan kabel
2024-05-17
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1 TPM Tyre 3
Clean up area SGA Tyre 3 from dust use equipment cleaning tools and instrument air supply. Also tidy up cable shell cooling motor cable at cable tray (ALL CREW ELECTRIC NR1 )
2024-05-16
2 years ago
NR.EL-03 Bayu Kiln Saputro EAST-HOUSING Panel Listrik Mess No1 Belum ada Grounding
Pasang Grounding rod baru (1 batang 4m)
Cek dengan earth tester masih tinggi 5.9 Ohm
2024-05-16
2 years ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP-MECHANIC Install LCS roll machine
Install LCS for roll machine ( FIRMAN & ANDRI )
2024-05-16
2 years ago
NR.EL-01 Wahyu Adi Triono 393-BE1-BOTTOM Check tilt sensor
Adjust tilt sensor position ( RIZAL & EVE RIZKY )
2024-05-16
2 years ago
NR.EL-01 Wahyu Adi Triono 463-2K1-&-443-2K1 Monitor functional analyzer
Monitor functional analyzer ( RIZAL & EVE RIZKY )
2024-05-16
2 years ago
NR.EL-01 Wahyu Adi Triono 473-GQ1-AND-CLINKER-SILO WBI Hoist Crane
WBI Hoist Crane ( PENY )
2024-05-16
2 years ago
NR.EL-01 Wahyu Adi Triono L1C-BC6-&-BC7 Water spray can not stop
Replace s/v test functional result ok ( YOGA )
2024-05-16
2 years ago
NR.EL-01 Wahyu Adi Triono 393-SCA-AND-MV-MOTOR Monitor bearing motor
Clean up area motor and filter.add grease if found vibrationg and noise abnormal ( AGUS )
2024-05-16
2 years ago
NR.EL-01 Wahyu Adi Triono ER3-AND-ER6 Clean up to panel MV and trafo
Clean up filter fan an front of ER6, also clean up room of electric rooms and top panel MV and trafo ( ADI & IMAN )
2024-05-15
2 years ago
NR.EL-03 Bayu Kiln Saputro MAINGATE-BUILDING Lampu Mati
Ganti Lampu TL 14 Ea
Ganti Lampu Ulir 3 Ea
Ganti lampu tembak 100W 2Ea
Ganti lampu selancar 1Ea
2024-05-15
2 years ago
NR.EL-03 Bayu Kiln Saputro 581-CX1 trip breaker di MCC
Breaker trip saat pindah ke kontaktor delta
Cek resistan coil dan isolasi main motor dan motor fan OK
Cek finger contactor OK 
Cek tegangan output contactor (posisi kabel ke motor disconnect) balance 390 Vac OK
Cek setting MCCB di MCC, rubah Io dari 630 A ke 400 A dan Isd dari 1.5 ke 5
Test Run OK
2024-05-15
2 years ago
NR.EL-01 Wahyu Adi Triono 393-BE1 fabrication box grease
 fabrication box grease for bucket elevator ( AGUS & EVE RIZKY & MADIN )
2024-05-15
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1 WBI camera burner and clinker silo
WBI camera burner and clinker silo ( PENY )
2024-05-15
2 years ago
NR.EL-01 Wahyu Adi Triono 443-CT1 Solenoid valve for water and air are not function
Clean up s/v for water and air, found many dirty inside membran s/v water. result test ok ( RIZAL & ANDRI )
2024-05-15
2 years ago
NR.EL-01 Wahyu Adi Triono 473-FA1-AND-FA2 Install sensor RTD and vibration
Install sensor RTD and vibration ( RIZAL & ANDRI )
2024-05-15
2 years ago
NR.EL-01 Wahyu Adi Triono 423-2K1 PMR service CEMS
PMR service CEMS, such as clean up transducer A & B flowsic 100, clean up swivel window dust hunter, clean up filter purge air unit, calibration zero and span FIDOR ( YOGA & ADI )
2024-05-14
2 years ago
NR.EL-03 Bayu Kiln Saputro 66A-CX3 Kabel Output Contactor Delta Overheat
Coba kencangkan baud contactor dudukan kontak finger patah karena sudah getas
Buat lubang dudukan untuk kontaktor
Ganti contactor delta dari schneider ke LS
Ganti kabel jumper untuk Output MC Delta dan Star, karena kabel existing sudah overheat
Test OK

2024-05-14
2 years ago
NR.EL-03 Bayu Kiln Saputro D33-CX4 Main Motor Kompresor Panas
Install External Fan untuk pendinginan main motor
Wiring kontrol untuk start stop motor fan
Test OK
2024-05-14
2 years ago
NR.EL-01 Wahyu Adi Triono HRG Clean up area room HRG and filter
Clean up area HRG and filter use hand blower  ( JAJAT & ADI )
2024-05-14
2 years ago
NR.EL-01 Wahyu Adi Triono 363-MD1 Clean up motor
Clean up area motor and filter motor, Check carbon brush condition result condition carbon brush are ok ( AGUS & EVE RIZKY )
2024-05-14
2 years ago
NR.EL-01 Wahyu Adi Triono 463-MD1-&-473-FN7 Clean up motor
Clean up area motor and filter motor from dust, check carbon brush condition. Result carbon brush condition are ok ( PENY & FIRMAN )
2024-05-14
2 years ago
NR.EL-01 Wahyu Adi Triono 453-PF1-AND-483-PF1 Check load cell and calibration pfister feeder
Replace load cell for 453 PF1 continue calibration zero and span pfister feeder. Check calibration zero and span 483 PF1 ( RIZAL & YOGA & ANDRI )
2024-05-14
2 years ago
NR.EL-01 Wahyu Adi Triono PANEL-INPUT-&-OUTPUT-WEST-ALSO-EAST-BLENDING Panel I/O west and east blending dirty from dust blending
Clean up panel I/O west and east blending from dirt of dust blending with hand blower, also clean up panel FM and PF inside east blending ( ADI )
2024-05-14
2 years ago
NR.EL-01 Wahyu Adi Triono L1C-2RC-11 Panel input-output dirty
Clean up panel I/O from dirty dust with hand blower ( ADI )
2024-05-13
2 years ago
NR.EL-03 Bayu Kiln Saputro D33-CX4 Ketika distart ada indikasi Fault FC
Cek LCS handle patah
Cek Posisi LCS masih OFF
ganti handle LCS
On kan LCS
Test Run OK
2024-05-13
2 years ago
NR.EL-03 Bayu Kiln Saputro 443-CX5 Pressure outlet kompresor tidak naik
Cek arah putaran motor terbalik
Balik putaran motor dengan menukar kabel fasa S dan T\
Test Run
OK
2024-05-13
2 years ago
NR.EL-03 Bayu Kiln Saputro M33-LM1 Pembacaan sensor kadang kadang error
Cek sensor, clamp sling menyentuh dinding lubang sensor
perbaikan clamp sling sensor high dan low
Clean up sensor high dan low
buat lubang baru untuk baud dudukan sensor
adjust sensor di posisi tengah tengah lubang
Test OK
2024-05-10
2 years ago
NR.EL-03 Bayu Kiln Saputro M33-LM1 Pembacaan sensor kadang kadang error
Install dudukan sensor
Relokasi sensor
Test
OK
2024-05-08
2 years ago
NR.EL-03 Bayu Kiln Saputro D34-CP4 Counter running hour greasing motor aktif
Regreasing main motor
2024-05-08
2 years ago
NR.EL-03 Bayu Kiln Saputro D3A-CP8 Counter running hour greasing motor aktif
Regreasing main motor
2024-05-08
2 years ago
NR.EL-03 Bayu Kiln Saputro 561-CX1 Counter running hour greasing motor aktif
Regreasing main motor
2024-05-08
2 years ago
NR.EL-03 Bayu Kiln Saputro D3A-PQ2 Counter running hour greasing motor aktif
Regreasing main motor
2024-05-08
2 years ago
NR.EL-03 Bayu Kiln Saputro 581-CX1 Counter running hour greasing motor aktif
Regreasing main motor
2024-05-13
2 years ago
NR.EL-01 Wahyu Adi Triono 483-RF2 Connect motor
Connect motor RF and load cell at 483 PF1 ( PENY & YOGA )
2024-05-13
2 years ago
NR.EL-01 Wahyu Adi Triono 473-FA1-AND-FA2 Connect sensor RTD and vibration
Connect new TU at panel I/O, install RTD and vibration sensor ( RIZAL & ANDRI )
2024-05-13
2 years ago
NR.EL-01 Wahyu Adi Triono 493-AC1,-AC2,-AC3 Check and repaire TLS
Repaire TLS for 493 AC1,AC2,AC3 ( PENY & YOGA )
2024-05-13
2 years ago
NR.EL-01 Wahyu Adi Triono 473-EH3 Connect power hoist
Prepare cable power of hoist, connect power of hoist ( AGUS & FIRMAN )

2024-05-13
2 years ago
NR.EL-01 Wahyu Adi Triono RECONDITION-MOTOR Recondition motor 5.5 KW 4P and 2.2 KW 2P
Take motor from ware house electric behind ER5 and from ware houses 1.1 KW 2P, bring to work shop electric ( EMSI & ADI )
2024-05-13
2 years ago
NR.EL-01 Wahyu Adi Triono 393-FV2 Continue connection cable
Connect cable for limit switch and solenoid valve at I/O panel also box termination ( RIZAL & EVE RIZKY )
2024-05-13
2 years ago
NR.EL-01 Wahyu Adi Triono BURNER-FLOOR Connect camera
Prepare cable for camera, connect cable at side. Test run camera result view ok ( PENY )
2024-05-13
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1 Continue install rell hoist 463 MD1
Install rell hoist at 463 MD1 ( FIRMAN & CIVACON )
2024-05-13
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1 Tidy up cable shell cooling and install blower motor
Install 2 each blower motor, prepare cable blower motor at  work shop continue connect cable blower motor. Test run blower blower, replace contactor for run and emergency stop ( AGUS & YOGA & ADI & IMAN )
2024-05-08
2 years ago
NR.EL-03 Bayu Kiln Saputro 444-CX6 Counter running hour greasing motor aktif
Regreasing main motor
2024-05-08
2 years ago
NR.EL-03 Bayu Kiln Saputro 444-CX5 Counter running hour greasing motor aktif
Regreasing main motor
2024-05-08
2 years ago
NR.EL-03 Bayu Kiln Saputro 444-CX4 Counter running hour greasing motor aktif
Regreasing main motor
2024-05-08
2 years ago
NR.EL-03 Bayu Kiln Saputro 444-CX3 Counter running hour greasing motor aktif
Regreasing main motor
2024-05-08
2 years ago
NR.EL-03 Bayu Kiln Saputro 444-CX1 Counter running hour greasing motor aktif
Regreasing main motor

2024-05-08
2 years ago
NR.EL-03 Bayu Kiln Saputro M33-LM1 Pembacaan sensor kadang kadang error
Preparing relokasi sensor
install conduit dan pulling kabel
2024-05-08
2 years ago
NR.EL-01 Wahyu Adi Triono L63-RM1- Connect cable incoming welding to ER4 at cable tray
Connected cable welding incoming to ER4 near 463 KL1 ( AGUS & FIRMAN )
2024-05-08
2 years ago
NR.EL-01 Wahyu Adi Triono 463-LQ2 Install motor liquid
Test run motor spare result ampere high around 15 A. Take house motor after rebushing at work shop mechanic. Install motor test run with no load result ampere 2.4 - 2.6 A ( YOGA & PENY & ADI )
2024-05-08
2 years ago
NR.EL-01 Wahyu Adi Triono 483-FA1-M1 Test run motor, measure vibration and noise motor for free side and load side
Do test run motor with CBM teams, 1st result vibration and noise are still high upnormal, retightening coupling motor measure vibration and noise result normal when speed 2000 RPM ( PENY )
2024-05-08
2 years ago
NR.EL-01 Wahyu Adi Triono SLIDE-GATE-CKD Install box terminal cable, Limit Switch and Solenoid Valve
Install box terminal cable for power and indication, also limit switch and solenoid valve and cable tray and pipe cable from limit switch  ( RIZAL & EVE RIZKY & ANDRI )
2024-05-07
2 years ago
NR.EL-03 Bayu Kiln Saputro 443-CX5 Kabel MCC to LCS Overheat
Lanjutan
Tightenning bold di LCS dan MCC
On kan Breaker
cek tegangan di LCS
OK
2024-05-07
2 years ago
NR.EL-03 Bayu Kiln Saputro 444-CX2 Motor Ground
Install motor setelah rekondisi dan rewinding
Install dan tightenning kabel power di motor dan MC 
2024-05-07
2 years ago
NR.EL-01 Wahyu Adi Triono 363-WS1 Install new LCS
Install for new LCS ( PENY & AGUS & YOGA )
2024-05-07
2 years ago
NR.EL-01 Wahyu Adi Triono SLIDE-GATE-CKD Install box termination and cable tray. Also install limit switch and solenoid valve
Prepare support for box termination and limit switch and solenoid valve. Install box termination at local and  limit switch and solenoid valve. Painting support with yellow color ( RIZAL & ANDRI )
2024-05-07
2 years ago
NR.EL-01 Wahyu Adi Triono 473-EH3 relocation cable hoist to avoid hot materials from grate cooler
Install pipe for cable power hoist. Install cable hoist from motor to LCS. Test run hoist result ok ( FIRMAN & EVE RIZKY )
2024-05-07
2 years ago
NR.EL-01 Wahyu Adi Triono L63-LQ1 Check rubber coupling
Do check rubber coupling. Tightening nut for coupling distance more close than before ( AGUS )
2024-05-07
2 years ago
NR.EL-01 Wahyu Adi Triono 463-LQ2 Motor vibration and noise are not normal
Take motor from ware house. Test run at work shop result is not good, MC power supply trip and litle smoke come out from motor. try install hose new spare motor to original motor but does not match with nut. Original motor do rebushing at work shop mechanic  ( PENY & ADI & YOGA )
2024-05-06
2 years ago
NR.EL-03 Bayu Kiln Saputro 443-CX5 Kabel MCC to LCS Overheat
Doubling kabel existing dengan kabel Ex 443-CX1
2024-05-06
2 years ago
NR.EL-03 Bayu Kiln Saputro TRAFO-NAR1_2 WBI
WBI trafo MV OTR 2, 3, 301, 302, A, B
2024-05-03
2 years ago
NR.EL-03 Bayu Kiln Saputro SWITCHYARD Drum Oli Trafo Ex Overhoul masih ada di switchyard
Housekeeping pindahkan drum oli ke gudang limbah B3 dan oli baru ke MSS
2024-05-06
2 years ago
NR.EL-01 Wahyu Adi Triono 483-FA1-M1 Continue replace bearing motor
Replace bearing 2 each. Install bask shaft motor and motor. test run motor, measure vibration and noise result vibration free and load side are ok. Noise for free side around 1.9 gE and load side 2.6 gE. Add grease for measure noise still high up 2 gE for free side and load side  ( PENY & EVE RIZKY & YOGA & FIRMAN )
2024-05-06
2 years ago
NR.EL-01 Wahyu Adi Triono SLIDE-GATE-CKD Pulling cable 4 limit switch dan 2 solenoid valve
Take cable indication and power for limit switch and solenoid valve at ware house electric around green cable 35 meter and black cable 100 meter. Pulling cable from site slide gate CKD to panel i/O at 363 FN2. Prepare box termination cable at work shop ( RIZAL & ADI & ANDRI )
2024-05-02
2 years ago
NR.EL-03 Bayu Kiln Saputro 443-CX2 Reaktifasi kompresor setelah kebakaran
Install panel kontrol kompresor
Install display controller
Install Emergency pushbutton
2024-05-02
2 years ago
NR.EL-03 Bayu Kiln Saputro GENSET-NAR2 Genset tidak bisa di start
Test run setelah recharging
OK
2024-04-30
2 years ago
NR.EL-03 Bayu Kiln Saputro 443-CX2 Reaktifasi kompresor setelah kebakaran
rewiring control kompresor
simulasi dengan display kontroller
2024-04-30
2 years ago
NR.EL-03 Bayu Kiln Saputro GENSET-NAR2 Genset tidak bisa di start
Cek baterai, skun baterai kendor disisi kabel jumper
ganti skun/clamp 
recharge baterai
2024-04-29
2 years ago
NR.EL-03 Bayu Kiln Saputro GENSET-NAR WBI
WBI dan tes run genset nar 1, nar 2 dan packhouse nar 2
genset nar 2 kiln tidak bisa di start
2024-04-29
2 years ago
NR.EL-03 Bayu Kiln Saputro TRAFO-NAR1_2 WBI
WBI Trafo MV OTR 2, 3, 301, 302, A, B
2024-05-03
2 years ago
NR.EL-01 Wahyu Adi Triono 483-FA1-M1 Check bearing condition
Dismantle motor 483 FA1 M1, dismantle bearing motor and clean up around body motor from dust shaft motor from grease  ( PENY & ADI & FIRMAN )
2024-05-03
2 years ago
NR.EL-01 Wahyu Adi Triono L63-BV1 Check indication compare from CCR and local
Replace card analog with new card. Test run from CCR, set 0 % actual already close but indication available, set 100 % actual open full but indication 70 % ( RIZAL & ANDRI )
2024-04-26
2 years ago
NR.EL-03 Bayu Kiln Saputro 443-CX2 Reaktifasi kompresor setelah kebakaran
Install support panel
Wiring kontrol panel kompresor
2024-04-26
2 years ago
NR.EL-03 Bayu Kiln Saputro 6G1-CX1 Kompresor tidak bisa di start
Lanjutan
Cek valve solenoid EX Kompresor valve jenis NO
sedangkan valve gantinya jenis NC
Modifikasi wiring dengan menambah relay dan coil solenoid lewat kontak NC relay
Test Run OK Normal
2024-04-25
2 years ago
NR.EL-03 Bayu Kiln Saputro 443-CX2 Reaktifasi kompresor setelah kebakaran
Pabrikasi support untuk panel kompresor
pulling kabel LCS to MC
2024-04-25
2 years ago
NR.EL-03 Bayu Kiln Saputro 6G1-CX1 Kompresor tidak bisa di start
- Install display kontroller di kompresor
- Install trafo kontrol 380V-220V-24V
- Cek wiring MC ada kesalahan wiring seharusnya kontak NC MC delta untuk terminal A2 
   MC Star dan kontak NC MC Star untuk terminal A2 MC Delta, Koreksi wiring
- Test simulasi tanpa beban motor OK
- Pasang kabel motor test run, kompresor run
- Saat loading fuse kontrol putus
- Cek kabel solenoid ada kabel yg lepas dari terminal soket dan short, perbaikan kabel dan
  ganti soket
- Ganti solenoid+valve karena posisi coil diganjel baud
- Cek indikasi pressure out kompresor tidak naik, Ganti sensor pressure Test run OK
- Kompresor kadang kadang high temperatur, cek kabel RTD ada sambungan yang kadang
  kadang short, perbaikan kabel 
- Saat starting putaran motor berat....... lanjut
2024-04-24
2 years ago
NR.EL-03 Bayu Kiln Saputro 443-CX2 Reaktifasi kompresor setelah kebakaran
Pull back kabel LCS to MC
Buat 2 lubang di panel untuk exhaust fan dan sirkulasi udara

2024-04-24
2 years ago
NR.EL-03 Bayu Kiln Saputro 6G1-CX1 Kompresor tidak bisa di start
Lanjutan
Coba ganti Trafo
Tes run
kondisi MC masih tidak bisa ON
Lepas display kontroller, simulasi di workshop
test simulasi OK 
2024-04-23
2 years ago
NR.EL-03 Bayu Kiln Saputro 6G1-CX1 Motor tidak bisa start
cek tahanan gulungan motor dan tahanan isolasi OK
cek fuse input dan output trafo putus, ganti fuse 
simulasi tanpa beban motor
MC star dan mc delta abnormal (kadang energize kadang tidak) saat distart
trafo kontrol berasap
2024-05-03
2 years ago
NR.EL-01 Wahyu Adi Triono CABLE-WELDING-INCOMING-TO-ER4 Connected cable incoming welding to ER4
Connected cable welding to ER4 ( AGUS & YOGA & FIRMAN)
2024-05-02
2 years ago
NR.EL-01 Wahyu Adi Triono 453-AGITATOR-M1 Replace bearing and install at local
Replace bearing 2 each for agitator, install motor at local ( PENY & ADI & ANDRI & GEMAN )
2024-05-23
2 years ago
NR.EL-03 Bayu Kiln Saputro CBM-BUILDING Lampu Mati
Ganti Lampu TL LED 8 Ea
2024-05-23
2 years ago
NR.EL-03 Bayu Kiln Saputro EAST-HOUSING Hub ethernet rusak dugaan petir
cek grounding panel hasil 10 ohm
kabel grounding hanya sampai panel lama, tidak ada grounding rod
2024-04-23
2 years ago
NR.EL-03 Bayu Kiln Saputro TRAFO-NAR2 Cek Oli Trafo Rutin
Pengambilan sample oil trafo OTR-A dan OTR-B by quadro
2024-04-23
2 years ago
NR.EL-03 Bayu Kiln Saputro GENSET-NAR WBI
WBI dan test run genset Nar 1 dan packhouse nar 2
2024-04-22
2 years ago
NR.EL-03 Bayu Kiln Saputro WORKSHOP-BUILDING Lampu Mati
Ganti lampu TL ulir 2 Ea ruangan SI Electric
2024-04-22
2 years ago
NR.EL-03 Bayu Kiln Saputro CBM-BUILDING Lampu Mati
Ganti lampu TL LED 2 Ea
2024-04-22
2 years ago
NR.EL-03 Bayu Kiln Saputro WORKSHOP-BUILDING Tempat pemasangan kamera kurang pas
Relokasi kamera CCTV 1 Ea
2024-04-22
2 years ago
NR.EL-03 Bayu Kiln Saputro 443-CX2 Reaktifasi kompresor setelah kebakaran
Install main motor kompresor
Wiring panel kontrol
2024-04-22
2 years ago
NR.EL-03 Bayu Kiln Saputro TRAFO-NAR1_2 WBI
WBI Trafo MV OTR A, B, 2, 3, 301, 302
2024-04-19
2 years ago
NR.EL-03 Bayu Kiln Saputro WORKSHOP-BUILDING Kamera CCTV belum terpasang
Install kamera CCTV 4 Ea dan MMC 2 Ea
2024-04-19
2 years ago
NR.EL-03 Bayu Kiln Saputro 443-CX2 Reaktifasi kompresor setelah kebakaran
preparing kabel LCS to MC dan MC to motor
2024-04-19
2 years ago
NR.EL-03 Bayu Kiln Saputro EAST-HOUSING Hub ethernet rusak dugaan petir
cek grounding komrel office 3 titik
nilai resistance dibawah 5 ohm
OK
2024-04-18
2 years ago
NR.EL-03 Bayu Kiln Saputro 66B-CX3 Display Blank
Cek display kontroller Ex kompresor 66B-CX3
display blank karena ada komponen overheat di PCB mainboard
2024-04-18
2 years ago
NR.EL-03 Bayu Kiln Saputro D34-CPA Sensor DP separator error
Service sensor DP separator Ex kompresor D34-CPA
2024-04-18
2 years ago
NR.EL-03 Bayu Kiln Saputro LIGHTING-JALAN Lighting Jalan Raya Narogong Mati
Ganti lampu jalan 8 Ea
resetting timer karena penunjukkan jam sudah bergeser
test OK
2024-04-17
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-2 Indikasi di panel receiving fan trip
cek lokal fan radiator trafo trip 5 Ea dan noise 1 Ea
disconnect kabel dan lepas motor 6 Ea bawa ke workshop

2024-04-17
2 years ago
NR.EL-03 Bayu Kiln Saputro MSS-BUILDING Lighting Jalan Area MSS mati
Perapihan kabel
tambal bekas bobokan beton
2024-04-30
2 years ago
NR.EL-01 Wahyu Adi Triono CABLE-INGOMING-WELDING-TO-ER4 Cable incoming welding to ER4 that is burned
Replace cable incoming welding that is burned to ER4 near 463 KL1 with spare cable ( AGUS & FIRMAN )
2024-04-30
2 years ago
NR.EL-01 Wahyu Adi Triono L93-RF1-AND-L93-SC5 Seal leakage at rotary feeder and motor abnormal at screw conveyor
Replace seal for L93 RF1 and replace bearing 6208 2Z 2 each for L93 SC5 ( PENY & HARYANTO & RAMA & ANDRI )
2024-04-30
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1-TYRE-3 TPM prepare dash board, report FA, AM, and Safety
Prepare dash board for TPM 463 KL1 Trye 3, make report for FA, AM and Safety. Print out report and laminating. Install report at dash board ( YOGA & RIZAL & ADI & EVE RIZKY )
2024-04-29
2 years ago
NR.EL-01 Wahyu Adi Triono 423-FN1 Report for precomissioing drive
Clean up panel drive at ER4 and make report for precomissioing drive ( PENY )
2024-04-17
2 years ago
NR.EL-03 Bayu Kiln Saputro D3A-PQ4 trip breaker di MCC
Info shift motor cooling fan 1.1 OL disconnect kabel power
cek ulang tahanan coil motor dan tahanan isolasi OK balance
cek nilai induktance OK balance
coba reconnect kabel test ampere 2,8A, setting eocr 2.75
naikkan setting eocr ke 3A 
test run OK
2024-04-17
2 years ago
NR.EL-03 Bayu Kiln Saputro 561-CX1 Saat starting muncul indikasi open phase fault
Open phase muncul saat pindah ke MC delta
cek timer star 15s rubah ke 10s
cek parameter open phase 10s rubah ke 3s
test OK
2024-04-16
2 years ago
NR.EL-03 Bayu Kiln Saputro MSS-BUILDING Lampu jalan area MSS mati
Cek kabel kemungkinan ada yang putus
pulling kabel baru dari Luar MSS building ke lampu jalan
test OK
2024-04-29
2 years ago
NR.EL-01 Wahyu Adi Triono 363-MD1 Prepare pulling cable for indication temperature motor
Pulling cable for indication temperature motor ( AGUS & EVE RIZKY )
2024-04-29
2 years ago
NR.EL-01 Wahyu Adi Triono FIELD-NEW-INPUT-OUTPUT Pulling profibus cable
Pulling profibus cable for new filed I/O ( RIZAL & ANDRI )
2024-04-29
2 years ago
NR.EL-01 Wahyu Adi Triono 473-FA1-AND-FA2 Continue install cable vibration and RTD
Install cable for vibration and RTD ( RIZAL & ANDRI )
2024-04-29
2 years ago
NR.EL-01 Wahyu Adi Triono L93-SC4- Continue service cable power
Move cable power from L93 RF3 to L93 SC4 also connected cable to L93 SC4. Test on result ok ( YOGA & AGUS & ADI & FIRMAN )
2024-04-29
2 years ago
NR.EL-01 Wahyu Adi Triono WARE-HOUSE Check motor 463 MD1
Check motor 463 MD1 at ware house ( AGUS )
2024-04-29
2 years ago
NR.EL-01 Wahyu Adi Triono L93-SC4 pulling cable power
Pulling cable power, but we find spare cable at L93 RF3 ( YOGA & PENY & EVE RIZKY & FIRMAN )
2024-04-26
2 years ago
NR.EL-01 Wahyu Adi Triono 473-FA1-AND-FA2 continue install sensor RTD and vibration
Install sensor RTD and vibration ( RIZAL & ANDRI )
2024-04-16
2 years ago
NR.EL-03 Bayu Kiln Saputro 66B-CX3 Display Blank
Coba ganti LCD 
Test 4 jam (hanya ON display) masih buram
cek temperatur display overheat
ganti display spare 1 set
test OK
2024-04-16
2 years ago
NR.EL-03 Bayu Kiln Saputro D34-CPA Indikasi DP oil separator abnormal
Ganti sensor DP Separator
Test OK
2024-04-15
2 years ago
NR.EL-03 Bayu Kiln Saputro BATTERY-CHARGER-MSS Air aki low
Tambah Air aki
2024-04-15
2 years ago
NR.EL-03 Bayu Kiln Saputro HANDAK-BUILDING Lighting mati
Ganti lampu 200 W 2 Ea
2024-04-15
2 years ago
NR.EL-03 Bayu Kiln Saputro TRAFO-NAR1_2 WBI
wbi trafo mv OTR 2, 3, 301, 302, A, B
2024-04-25
2 years ago
NR.EL-01 Wahyu Adi Triono L93-SC4 Cable grounded
Measure with meger at ER4 at LCS result cable bad condition. Cable to motor disconnect, run motor from CCR result motor is not available. Advise pulling cable from ER4 to LCS L93 SC4 ( YOGA & ADI & FIRMAN &  EVE RIZKY )
2024-04-25
2 years ago
NR.EL-01 Wahyu Adi Triono ER5-UPS-AND-HYDROLIC-PLC Replace cable power PLC
Replace cable power PLC ( AGUS & PENY )
2024-04-25
2 years ago
NR.EL-01 Wahyu Adi Triono INPUT-OUTPUT-493-AC1 Connecting new I/O
Connecting new I/O for 493 AC1 ( PENY & YOGA )
2024-04-25
2 years ago
NR.EL-01 Wahyu Adi Triono 463-LQ1,-LQ2,-LQ3 Continue install motor at local
Install motor at local also replace coupling motor. Adjust position coupling for all motor. Test run motor measure vibration and noise LQ1 Vertical: 0.9 mm/s o.64 gE- Horizontal: 0.0 mm/s 0.7 gE, LQ2 Vertical: 5.0 mm/s 1.9 gE Horizontal: 1.5 mm/s 1.4 gE, LQ3 Horizontal: 1.2 mm/s 0.75 gE,, Vertical: 1.0 mm/s 0.68 gE ( ADI & FIRMAN & EVE RIZKY )
2024-04-25
2 years ago
NR.EL-01 Wahyu Adi Triono 473-FA1-AND-FA2 Continue install sensor RTD and vibration
Install sensor for RTD and vibration ( RIZAL & ANDRI )
2024-04-24
2 years ago
NR.EL-01 Wahyu Adi Triono 473-FA1-AND-FA2 Prepare cable for RTD and Vibration
Prepare box for connection cable RTD and vibration. Install box at local 9 RIZAL & ANDRI )
2024-04-24
2 years ago
NR.EL-01 Wahyu Adi Triono 363-RM continue install I/O
Install I/O for 363 RM1 ( PENY )
2024-04-24
2 years ago
NR.EL-01 Wahyu Adi Triono HRG Replace MC incoming
Replace MC incoming ( AGUS & EVE RIZKY )
2024-04-24
2 years ago
NR.EL-01 Wahyu Adi Triono 463-LQ1-LQ2-LQ3 LQ3 discouple coupling or replace bearing motor vibration 4.4 m/s noise 1.6 gE, LQ2 discouple motor& test noise 2.3 gE, LQ1 discouple & test noise 3.6 gE
Discouple motor 463 LQ1-LQ2-LQ3, clean up body motor from dust also replace bearing motor. Install motor at work shop for 463 LQ1-LQ2-LQ3( YOGA & ADI & FIRMAN )
2024-04-23
2 years ago
NR.EL-01 Wahyu Adi Triono 363-LQ2-M1-TO-M2-AND-463-LQ1-TO-LQ3 check condition bearing motor
Check condition bearing motor for 363 LQ1-LQ2 vibration normal but noise already 1 ge. 463 LQ1 - LQ3 check vibration are abnormal and noise motor are abnormal ( AGUS )
2024-04-23
2 years ago
NR.EL-01 Wahyu Adi Triono 473-HC1- Continue install sensor bearing
Reinstall sensor vibration, test run motor 473 EH1 from CCR, measure vibration from local and CCR. Differential 0.30 mm/s ( RIZAL & EVE RIZKY )
2024-04-23
2 years ago
NR.EL-01 Wahyu Adi Triono 473-EH3 Relocation power hoist
Relocation power for HOIST from hot material grate cooler ( FIRMAN & ANDRI )
2024-04-23
2 years ago
NR.EL-01 Wahyu Adi Triono 363-RM1 Relocation relay panel I/O
Relocation relay panel I/O 363 RM1. Install MCB and terminal distribution 3 each. Connecting cable ( PENY & ADI )
2024-04-22
2 years ago
NR.EL-01 Wahyu Adi Triono ER6 Replace battery charging 12 VDC
Replace charging battery 12 VDC 2 each for number 7 & 8. Test on result ok. measure voltage good ( EMIS & ADI )
2024-04-22
2 years ago
NR.EL-01 Wahyu Adi Triono 363-RM1-PANEL-INPUT-OUTPUT Move relay I/O
Move relay I/O 363 RM1 ( PENY & FIRMAN )
2024-04-22
2 years ago
NR.EL-01 Wahyu Adi Triono 473-HC1 pulling cable vibration sensor and make conduit way to vibration sensor
Clean up conduit from I/O panel to 473 Hc1, pulling cable vibration sensor from panel I/O to sensor vibration ( YOGA & ADI & EVE RIZKY & ANDRI & FIRMAN )
2024-04-19
2 years ago
NR.EL-01 Wahyu Adi Triono 453-PF1 continue install load cell
Install load cell 453 PF1 ( RIZAL & ANDRI )
2024-04-19
2 years ago
NR.EL-01 Wahyu Adi Triono 363-RM continue check I/O
Check I/O for 363 RM ( PENY )
2024-04-19
2 years ago
NR.EL-01 Wahyu Adi Triono 443-EL1 Continue replace bearing motor door at north side
Replace bearing motor door for north side ( OENY & FIRMAN )
2024-04-19
2 years ago
NR.EL-01 Wahyu Adi Triono FM-NR2 Continue calibration protection relay
Calibration protection relay ( AGUS & YOGA )
2024-04-19
2 years ago
NR.EL-01 Wahyu Adi Triono KALENESIA Check inspection electrical and welding tools
Inspection electrical and welding tools of PT KALENESIA at main gate ( ADI & IMAN )
2024-04-18
2 years ago
NR.EL-01 Wahyu Adi Triono 453-PF1 continue install convensator
Replace bearing for convensator 2 each. Install convensator at 453 PF1 ( RIZAL & ANDRI )
2024-04-18
2 years ago
NR.EL-01 Wahyu Adi Triono FM-NR2 Calibration protection relay
Do calibration protection relay ( AGUS & IMAN )
2024-04-18
2 years ago
NR.EL-01 Wahyu Adi Triono 443-EL1 Repaire elevator
Check elevator found nut for inside door 1 nut is loos, install nut of inside door. Test functional from 8th to 1st floor. Result ok ( PENY & ADI & FIRMAN )
2024-04-05
2 years ago
NR.EL-03 Bayu Kiln Saputro PUMP-NAR2 WBI
WBI Pompa line Nar 2
Regreasing motor pompa
2024-04-05
2 years ago
NR.EL-03 Bayu Kiln Saputro KOMPRESOR-NAR2 WBI
WBI kompresor Line Nar 2
Regreasing main motor 
2024-04-04
2 years ago
NR.EL-03 Bayu Kiln Saputro 474-CX2 NFB Trip di MCC
Cek MC 170A rusak
ganti MC 170A
perbaikan kabel output MC main (kabel Motor getas)
test OK
2024-04-03
2 years ago
NR.EL-03 Bayu Kiln Saputro GUDANG-HANDAK Power di office gudang handak mati
Perbaikan kabel power (sambungan)
test OK
2024-04-03
2 years ago
NR.EL-03 Bayu Kiln Saputro GUDANG-HANDAK Lighting mati
Cek kabel ada yang kegaruk excavator di tiang no 4
perbaikan kabel tiang no 4

2024-04-02
2 years ago
NR.EL-03 Bayu Kiln Saputro WORKSHOP-BUILDING Area electric workshop berantakan
Housekeeping area elektrik workshop
2024-04-02
2 years ago
NR.EL-03 Bayu Kiln Saputro GUDANG-APAR Ruangan Gelap
Cek lampu banyak yang mati
ganti lampu TL 2 Ea
perlu tarik kabel baru, kabel netral ada yang putus
2024-04-01
2 years ago
NR.EL-03 Bayu Kiln Saputro WORKSHOP-BUILDING Cross Check motor spare cooling fan trafo OTR-B
Clean up dan Cross Check motor spare cooling fan trafo OTR-B 5 Ea
2024-04-01
2 years ago
NR.EL-03 Bayu Kiln Saputro TRAFO-NAR1_2 WBI
WBI trafo MV OTR A, B, 2, 3, 301, 302
thermograf DS dan bushing trafo
2024-03-28
2 years ago
NR.EL-03 Bayu Kiln Saputro ER-7B Ketersediaan Stop Kontak Kurang
Install Stop kontak 1 Ea
pulling kabel
connect to kabel power ke stop kontak
test OK
2024-03-28
2 years ago
NR.EL-03 Bayu Kiln Saputro ER-7A Selector On-OFF Fire supression belum ada
Install Selector Switch on-off
Pulling kabel selector switch to panel FM200
Test OK
2024-03-28
2 years ago
NR.EL-03 Bayu Kiln Saputro ER-7B Selector On-OFF Fire supression belum ada
Install selector On-Off
pulling kabel selector switch to panel FM200
test OK
2024-03-28
2 years ago
NR.EL-03 Bayu Kiln Saputro ER-7B Verifikasi kWHmeter
Verifikasi kWHmeter ER-7B
2024-03-27
2 years ago
NR.EL-03 Bayu Kiln Saputro 444-CX4 Kompresor Trip Indikasi DP Air Filter
Cek indikasi sensor DP air filter OK
Cek flexible rubber kempot
Ganti flexible rubber (Ambil dari 444-CX2)
(Info mekanik flexible rubber barang baru dan meterialny lebih tipis)
2024-03-26
2 years ago
NR.EL-03 Bayu Kiln Saputro LIGHTING-JALAN Lighting Jalan Area MSS mati
Ganti Lampu jalan 4 Ea
test OK
2024-03-26
2 years ago
NR.EL-03 Bayu Kiln Saputro 444-CX4 Kompresor Trip Indikasi DP Air Filter
Ganti kabel + socket sensor pressure
Ganti Sensor DP Air Filter
Test OK
2024-03-25
2 years ago
NR.EL-03 Bayu Kiln Saputro ER-7B Verifikasi kWHmeter
Verifikasi kWHmeter ER-7B
2024-03-25
2 years ago
NR.EL-03 Bayu Kiln Saputro TRAFO-NAR1_2 WBI
WBI Trafo OTR 2, 3, 301, 302, A, B
2024-03-25
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-2 Manuver Power
Manuver power OTR-2
Open all Outgoing
Open Bustie OTR-2
Open Bustie MSS - ER-7B
Close Incoming OTR-2
Close all outgoing
2024-03-22
2 years ago
NR.EL-03 Bayu Kiln Saputro ER-7B Verifikasi kWHmeter
Verifikasi kWHmeter ER-7B
2024-03-22
2 years ago
NR.EL-03 Bayu Kiln Saputro LIGHTING-JALAN Lampu Logo SBI mati
pasang sangkar untuk lampu tembak
pasang lampu tembak 200W
pulling kabel untuk lampu tembak 
connect kabel power
test OK
2024-03-22
2 years ago
NR.EL-03 Bayu Kiln Saputro WAREHOUSE-BUILDING Handpallet rusak
Perbaikan handpallet ganti all oil seal
test OK
2024-04-09
2 years ago
NR.EL-01 Wahyu Adi Triono 363-BE1 Replace bright lamp that are of
Replace bright lamp that are off with new bright lamp 2 each at 363 BE1, test functional result ok ( ADI & ANDRI ) 
2024-04-09
2 years ago
NR.EL-01 Wahyu Adi Triono ER-3 Continue install door siren and lamp emergency
Install siren and lamp emergency at ER 3, test functional result ok ( AGUS & FIRMAN )
2024-04-09
2 years ago
NR.EL-01 Wahyu Adi Triono 363-BC1 Replace bright lamp are off
Replace bright lamp 4 each with new bright lamp at 363 BC1, test functional ok lamp are on ( ADI & ANDRI )
2024-04-08
2 years ago
NR.EL-01 Wahyu Adi Triono 363-BC1 Replace bright lamp are off
Replace bright lamp off with new spare ( ADI & ANDRI )
2024-04-08
2 years ago
NR.EL-01 Wahyu Adi Triono 473-EH3 Relocation power
Relocation power for hoist at 473 Eh3 from hot material from under grate cooler ( AGUS & FIRMAN )
2024-04-08
2 years ago
NR.EL-01 Wahyu Adi Triono L1C-BC7 Continue install bright lamp
Install bright lamp at L1C BC7 3 each. Do test functional of lamp result ok all bright are on ( ADI & ANDRI )
2024-04-05
2 years ago
NR.EL-01 Wahyu Adi Triono L33-BC1 Interlock BD is not connecting, cross check
Cross check interlock BD at L33 BC1, continue connected cable BD to interlock at systems ( RIZAL & GEMAN TRUBA )
2024-04-05
2 years ago
NR.EL-01 Wahyu Adi Triono 393-BF2-TOP-DUST-BIN Replace regulator filter
Do replace for regulator filter ( RIZAL & GEMAN TRUBA )
2024-04-05
2 years ago
NR.EL-01 Wahyu Adi Triono 363-HS1 Continue install panel I/O
Install panel I/O for 363 HS1 ( PENY & FIRMAL-MUL  CIVACON)
2024-04-05
2 years ago
NR.EL-01 Wahyu Adi Triono 433-BF2 test run equipment
Test functional for 433 BF2 ( PENY )
2024-04-05
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1&-473-EH3 tidy up all cable shell cooling fan put inside cable tray and cable power is burn also install scafolding
Supervision contractor install scafolding at 473 EH3 cut cable power that is burning from hot materials advise make another way of cable tray avoid hot material from great cooler ( AGUS & ADI )
2024-04-04
2 years ago
NR.EL-01 Wahyu Adi Triono ER4-AND-ER5-CLEAN-UP-ER-AND-FILTER-DRIVE Electric room and filter drive are not clean up yet
Clean up electric room and filter drive ( IMAN )
2024-04-04
2 years ago
NR.EL-01 Wahyu Adi Triono 363-WS1-CONTINUE-INSTALL-PANEL-AND-WIRING- Panel is not install yet
Fabrication support panel hagger, do wiring. Install panel at local ( AGUS & CIVA )
2024-04-04
2 years ago
NR.EL-01 Wahyu Adi Triono 453-PF1-BRING-DOWN-COMPENSATOR Compensator is not bring down yet
Bring down compensator 453 PF1 to work shop ( RIZAL & YOGA & ANDRI )
2024-04-04
2 years ago
NR.EL-01 Wahyu Adi Triono 433-DG1-CHECK-AND-TEST-RUN-SIGNAL-KTDR-TO-CCR Signal KTDR from I/O panel to CCR is not check yet
Check and test run signal KTDR from panel I/o to CCR. Result ok ( PENY & ADI )
2024-04-04
2 years ago
NR.SHIFT Wahyu Adi Triono 433-BF2-&-433-FN2-PREPARE-INPUT-OUTPUT-AND-TEST-RUN I/O are not ready yet
Connect cable power and control 433 BF2 and  433 FN2, do test run from panel I/O to CCR result ok ( PENY & ADI )
2024-04-03
2 years ago
NR.EL-01 Wahyu Adi Triono 363-WS1-PREPARE-INSTALL-HAGGER-BOX Box hagger is not prepare yet
Prepare box hagger at work shop ( AGUS & FIRMAN )
2024-04-03
2 years ago
NR.EL-01 Wahyu Adi Triono 363-WS1-CONTINUE-SOLENOID-VALVE-ALSO-PREPARE-CABLE-POWER-AND--CABLE-CONTROL S/V, cable power and control are not install and prepare yet
take cable at ware house bring to ER3 bottom, prepare LCS 2 each for 363 WS1 ( PENY & ADI )
2024-04-03
2 years ago
NR.EL-01 Wahyu Adi Triono L1C-BC7-CONTINUE-INSTALL-LAMP Lamp off are not install yet
Install bright lamp at L1C BC7 ( YOGA & ANDRI )
2024-04-02
2 years ago
NR.EL-01 emis supadma 493-AC2 breaker tdk bisa di reset
breaker 225A Hyundai , ganti dengan breaker 225A LS
2024-04-01
2 years ago
NR.SHIFT emis supadma L33-BC2-BELT-DRIVE-SOUTH-SIDE-MOTOR-IS-NOT-ACTIVE BD south motor is not check yet
Activated BD south motor L33 BC2 ( RIZAL & ANDRI )
2024-04-02
2 years ago
NR.EL-01 Wahyu Adi Triono L1C-TR1-INSTALL-LAMP-ALL-BC- Lamp off are not replace yet
Install lamp for all belt conveyor at L1C TR1 ( ANDRI )
2024-04-02
2 years ago
NR.EL-01 Wahyu Adi Triono ER4-MCC-LOAD-FOR-ACB-AND-MCC Area MCC of ACB & MCC are not check yet
Check MCC load for ACB and MCC at ER4 ( PENY )
2024-04-02
2 years ago
NR.EL-01 Wahyu Adi Triono 463-2K1-AND-443-2K1-PMR-SERVICE-ANALYZER Flange probe, probe, filter probe, sample line, membran pump, filter balston, dryer gas dirt by dust process
Clean flange probe, probe, filter probe, sample line, membran pump. disposable filter, dryer gas from dust process ( RIZAL )
2024-04-02
2 years ago
NR.EL-01 Wahyu Adi Triono L63-RM1-PMR-SERVICE-ANALYZER Sample line, filter, flange probe full material of coal, also filter balston
Clean up flange probe, sample line, filter probe, membran pump also disposable filter from dust coal process. Clean dryer gas and check filter humidity sensor replace filter with spare filter ( AGUS )
2024-04-02
2 years ago
NR.EL-01 Wahyu Adi Triono L63-RM1-&-L1C-TR1-&-L3C-RE1-WBI-ELECTRIC-AND-INSTRUMENTATION Area motor, reclaimer and tripper dirty by dust coal process
Measure vibration-noise and temperature for free side and load side ( YOGA & ADI )
2024-04-01
2 years ago
NR.EL-01 Wahyu Adi Triono 363-WS1 install new s/v
Install solenoid valve 363  WS1 (  RIZAL & ANDRI )
2024-04-01
2 years ago
NR.EL-01 Wahyu Adi Triono L33-BC1-ACTIVATED-BD-IS-NOT-STANDARD-FOR-TRIP-IS-NOT-ACTIVE--AND-PULLING-CABLE BD is activated yet
Activated BD and trip do setting normal also pulling cable ( PENY & YOGA )
2024-04-01
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1-REPLACE-AND-INSTALL-BRIGHT-LAMP Lamp is off not replace yet and mew instalation lamp is not resy yet
Replace bright lamp at east stair with spare bright lamp and install bright lamp at 463 KL1 ( AGUS & ADI & FIRMAN )
2024-04-01
2 years ago
NR.EL-01 Wahyu Adi Triono 493-EH1-&-EH4-MOVE-POWER-TO-EMERGENCY-BOX Power hoist are not move yet at ER5
Move power hoist 493 EH1 to emergency box ( AGUS & ADI & FIRMAN )
2024-03-28
2 years ago
NR.EL-01 Wahyu Adi Triono ER3-MCC-LOAD-ACB-AND-THERMOGRAPHY-MCC Thermography MCC and Load MCC ACB are not do at Electric Room
Do MCC load ACB and thermography MCC ( PENY ) 
2024-03-28
2 years ago
NR.EL-01 Wahyu Adi Triono 463-MD1-AUDIT-TPM Audit TPM 463 MD1 is not do at site
Accompany judge for AUDIT TPM 463 MD1 ( PENY & RIZAL & YOGA )
2024-03-28
2 years ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP-COMPLETING-DATA-TPM.-AM-AND-SAFETY-ALSO-DASH-BORAD Data TPM for AM, Safety and Dash Board are complete yet
Complete data TPM 463 MD1 for AM-Safety also Dash Board ( YOGA & RIZAL )
2024-03-28
2 years ago
NR.EL-01 Wahyu Adi Triono 473-FA7,-FA8,-FA9-INSTALL-MEMO-LUBE-OR-AUTO-GREASE Auto grease or memo lube are not install yet at motor
Install memo lube or AUTO GREASE at 473 FA7-FA8-FA9 ( AGUS & FIRMAN & ANDRI )
2024-03-28
2 years ago
NR.EL-01 Wahyu Adi Triono L63-RM1-PMR-SERVICE-ANALYZER Filter probe, sample line, membran pump, balston filter, dryer gas dirt of coal
Clean up sample line, flange probe, filter probe, membran pump, disposable filter, dryer gas from dirt of coal process. Check filter humidity sensor, service sensor replace filter if found bad condition ( ADI & ANDRI )
2024-03-27
2 years ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP-COMPLETING-DATA-TPM Data TPM is not complete yet
Complete data TPM and save at computer ( RIZAL & YOGA )
2024-03-27
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1-WBI-KILN,-COOLER,-CLINKER-SILO Area kiln, cooler, clinker silo dirty from dust and coal process
Clean up area kiln, cooler, clinker silo from dust and coal process ( PENY )
2024-03-27
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1-WBI-TOP-BLENDING,-PREHEATER,-CT-AND-KILN Area top blending, PH, CT and kiln dirty from dust process
Clean up top blending, PH, CT and kiln from dirty dust process. Measure vibration-noise-temperature. Add grease 5 to 10 times ( AGUS & EVE RAGIL )
2024-03-27
2 years ago
NR.EL-01 Wahyu Adi Triono 463-MD1-TPM-HOUSE-KEEPING-AND-PAINTING Area TPM dirty and fence,pipe,also need be repainting green and grey color
Clean up pipe cable also base plate motor, repainting pipe green color and support motor grey color ( ADI & EVE RIZKY & ANDRI )
2024-03-25
2 years ago
NR.SHIFT emis supadma 463-2K1 Rell utk probe sdh rusak sehingga roller juga ikut cepat rusak
ganti rell dan roller ( Yurizal , firman , andri )
2024-03-23
2 years ago
NR.EL-01 emis supadma 393-CN1-CYCLONE-RM lampu mati semua
ganti lampu OSRAM  5 pcs   ( Firman & Andri )
2024-03-26
2 years ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP-UTILITY-TRAINING-PLC PLC is not training yet for employee
Do training PLC at work shop utility ( RIZAL & YOGA )
2024-03-26
2 years ago
NR.EL-01 Wahyu Adi Triono 463-2K1-AND-442-2K1-PMR-SERVICE-ANALYZER Flange probe, probe, filter probe, sample line, membran pump, filter balston, dryer gas dirt by dust process
Clean up flange probe, probe, filter probe, sample line, membran pump, filter balston, dryer gas from dust process. Check filter humidity sensor replace with spare if found bad condition ( AGUS )
2024-03-26
2 years ago
NR.EL-01 Wahyu Adi Triono 423-2K1-PMR-SERVICE-CEMS Filter purge air unit for dust hunter and flowsic, swivel window dust hunter, transducer flowsic, CEMS room dirty from dust procecc
Clean up purge air unit dust hunter and flowsic, clean swivel windows transceiver/receiver and reflector dust hunter do alignment dust hunter, clean up transducer flowsic, clean filter cabinet MCS 100 E ( PENY )
2024-03-26
2 years ago
NR.EL-01 Wahyu Adi Triono 463-MD1-TPM-CLEAN-AND-PAINTING Area TPM still dirty from dust process and fence also cover motor still need to be repainting
Clean up area TPM and repainting yellow and grey color for fence also cover motor also install sign motor and safety ( ADI & EVE RIZKY & FIRMAN & ANDRI )
2024-03-25
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1-PMR-SERVICE-MOTOR Area and filter motor are dirty from dust process
Clean up area and filter motor use instrument air suplly. Measure vibration-noise and temperature for free and load side, add grease for 15 to 30 times for free and load side ( PENY )
2024-03-25
2 years ago
NR.EL-01 Wahyu Adi Triono 363-RM1-PMR-SERVICE-MOTOR Area and filter motor dirt from dust process
Clean up area and filter motor use instrument air supply, measure vibration-noise and temperature free and load side. Add grease from 15 times to 100 times for free side and load side ( AGUS )
2024-03-25
2 years ago
NR.EL-01 Wahyu Adi Triono 463-2K1-REPLACE-ROOLER-PROBE Roller bad condition and rell probe are not replace yet
Replace roller with spare unit, also replace rell probe use spare one ( RIZAL & EVE RIZKY & FIRMAN & ANDRI )
2024-03-25
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1-PMR-SERVICE-TEMPERATURE-TAD,-T-SCANNER,-CCTV,-CAMERA-BURNER Area lens temperature TAD, T scanner, CCTV and camera burner ( pyrometer ) dirty from dust process
Clean up flange and lens temperature TAD, T scanner, CCTV, area room camera burner also control from dust process use instrument air supply and use equipment cleaning tools ( ADI & EVE RAGIL )
2024-03-18
2 years ago
NR.SHIFT Wahyu Adi Triono ER3-INSTALL-LIMIT-SWITCH-AND-PULLING-CABLE Limit switch and cable are not ready at ER3
Install limit switch and pulling cable ( RIZAL & ANDRI )
2024-03-18
2 years ago
NR.EL-01 Wahyu Adi Triono 473-FA1-REPLACE-BEARING-MOTOR Bearing bad condition is not replace yet
Replace bearing motor, install back motor at local. Test run result ok ( YOGA & EVE RIZKY & EVE RAGIL & FIRMAN )
2024-03-22
2 years ago
NR.EL-01 Wahyu Adi Triono 363-RM1-PMR-SERVICE-MEDIUM-VOLTAGE-MOTOR Area motor dirty, filter motor, measure vibration, noise, temperature motor for free side and load side
Clean up area and filter motor. Replace auto grease for 363 MD1 at load side. Measure vibration-noise and temperature load and free side. add grease LS and FS 15 times to 100 times ( AGUS & ADI )
2024-03-22
2 years ago
NR.EL-01 Wahyu Adi Triono ER3-INSTALL-HORN-OF-DOOR HORN of door at ER3 is not install yet
Install HORN for door,test functional resulr ok ( AGUS & ANDRI )
2024-03-22
2 years ago
NR.EL-01 Wahyu Adi Triono 363-CYCLONE-ALL-LAMP-OFF Lamp is off still not replace yet
Replace lamp off at cyclone 363 RM1  ( PENY & FIRMAN )
2024-03-22
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1-PMR-SERVICE-IR-TAD-TSCANNER-PYROMETER-CCTV Flange probe, probe, sample line, filter probe,membran pump, dryer gas filter balston dirty
Clean up lens  of TAD temperature sensor, lens CCT- Tscanner also  pyrometer or camera burner ( YOGA )
2024-03-22
2 years ago
NR.EL-01 Wahyu Adi Triono L63-RM1-PMR-SERVICE-ANALYZER- Flange probe, sample line, filter probe,membran pump dirt of dust coal
Clean up flange probe, filter probe, sample line, diaphragma pump, disposable filter, dryer gas from dust coal process. Check and clean up filter humidity sensor replace with spare filter if found bad condition ( ADI & EVE RIZKY )
2024-03-22
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1-&-463-MD1-GEMBA-TPM Area TPM need to be clean and repainting for yellow color for fence and cover motor
Dismantle unuse ducting, put items at garbage tank. Clean up area conduit near inching motor kiln, repainting yellow color for fence near dash board TPM , also cover motor 463 MD1 and inching motor kiln ( PENY & AGUS & ADI & YOGA & EVE RIZKY & FIRMAN & ANDRI )
2024-03-21
2 years ago
NR.EL-03 Bayu Kiln Saputro 474-CX1 Finger Contactor Rusak
Preparing penggantian MC
Preparing kabel Power ke MC star dan delta
Preparing kabel Jumper output MC delta ke star
2024-03-21
2 years ago
NR.EL-03 Bayu Kiln Saputro MSS-BUILDING Verifikasi kWHmeter
Verifikasi kWHmeter MV-21, MV-23B, MV-24B, MV-25B, MV-26B, MV-27
Verifikasi ulang kWHmeter MV-16A, MV-24B dan MV-21
2024-03-20
2 years ago
NR.EL-03 Bayu Kiln Saputro 474-CX1 Finger Contactor Rusak
Preparing penggantian MC
Preparing kabel Power ke MC star dan delta
Preparing kabel Jumper output MC delta ke star
2024-03-20
2 years ago
NR.EL-03 Bayu Kiln Saputro MSS-BUILDING Verifikasi kWHmeter
Verifikasi kWHmeter MV-11, MV-13A, MV-14A, MV-15A, MV-16A, MV-17A, MV-22 
2024-03-19
2 years ago
NR.EL-03 Bayu Kiln Saputro 444-CX2 Indikasi overload motor
Bongkar mainmotor
bawa ke workshop untuk di rewinding 

2024-03-19
2 years ago
NR.EL-03 Bayu Kiln Saputro 474-CX1 Indikasi di display Host Overload
Coba test run noload tanpa screw OK
cek MC delta dan star fingerny sudah rusak
preparing penggantian MC
Buat lubang dudukan MC (diganti dengan LS, sebelumnya Schneider)
2024-03-21
2 years ago
NR.EL-01 Wahyu Adi Triono ER3-INSTALL-DOOR-HORN Horn at ER3 is not install yet
Install HORN Door at ER3, test functional result ok ( AGUS & FIRMAN )
2024-03-21
2 years ago
NR.EL-01 Wahyu Adi Triono 363-CYCLONE--LAMP-ALL-OFF-AND-363-RM1-P3-DP-RM-INDICATION-HIGH Lamp off are not replace yet and Indication DP RM are not check
Replace lamp off at Cyclone Raw Mill, and check DP service sample line and flange result DP local at CCR same ( PENY & EVE RIZKY-EVE RAGIL )
2024-03-21
2 years ago
NR.EL-01 Wahyu Adi Triono 463-2K1-CONTINUE-REPLACE-ROLLER- Roller for probe is not replace yet
Replace roller probe at 463 2K1 because probe need to more center to get more gas for indication at analyzer ( RIZAL & YOGA & ANDRI )
2024-03-21
2 years ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP-COMPLETE-DATA-CALIBRATION-OF-ANALYZER Data for analyzer are not complete yet
Complete data PMR service analyzer, scan data PMR year 2023 and 2024 and save at computer ( EMIS & ADI )
2024-03-20
2 years ago
NR.EL-01 Wahyu Adi Triono 443-CYCLONE-4-REPAIRE-TUBING Tubing bad condition is not repaire yet
Repaire tubing at 443 PH1 Cyclone 4 ( RIZAL & EVE RIZKY & ANDRI )
2024-03-20
2 years ago
NR.EL-01 Wahyu Adi Triono ER3-INSTALL-DOOR-HORN Door horn is not install yet at ER3
Install Door Horn at ER3, test functional result ok ( RIZAL & EVE RIZKY & ANDRI )
2024-03-20
2 years ago
NR.EL-01 Wahyu Adi Triono 463-BL7-AND-BL9--REPLACE-AUTO-GREASE Auto grease is not replace yet
Replace for AUTO GREASE with new spare, setting time test functional AUTO GREASE result ok ( AGUS & ANDRI )
2024-03-20
2 years ago
NR.EL-01 Wahyu Adi Triono 473-HC1-INSTALL-VIBRATION-SENSOR Vibration sensor is not ready at site
Installing vibrations sensor for 473 HC1 ( PENY & FIRMAN )
2024-03-20
2 years ago
NR.EL-01 Wahyu Adi Triono 463-2K1-AND-43-2K1-PMR-SERVICE-ANALYZER Flange probe, probe, filter probe, sample line, membran pump, filter balston, dryer gas dirt by dust process
Clean up flange probe, probe, filter probe, sample line, membran pump, filter disposable, dryer gas from dust process. Check filter humidity sensor replace with spare if found bad condition ( PENY & EVE RAGIL )
2024-03-20
2 years ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP-SCAN-DATA-CALIBRATION-AND-SCHEDULE-CALIBRATION Data calibration and schedule calibration are not ready for scanning
Scanning data calibration and schedule calibration year 2024 and save at file ( EMIS & ADI )
2024-03-18
2 years ago
NR.EL-03 Bayu Kiln Saputro 474-CX1 Indikasi overload motor
cek kabel motor di ouput MC overheat semuanya
perbaikan kabel yang overheat dan ganti scun
cek screw (diputar dengan tangan) berat
kemungkinan kabel overheat karena ampere motor tinggi dari screw yang berat
2024-03-18
2 years ago
NR.EL-03 Bayu Kiln Saputro 444-CX2 Indikasi overload motor
Cek resistan isolasi (dari output MC) OK
cek resistan coil motor putus 1 gulungan (dari output MC)
cek terminal motor kabel arah coil terbakar
2024-03-18
2 years ago
NR.EL-03 Bayu Kiln Saputro 444-CX1 Indikasi sensor temperatur elemen outlet fault
Cek kabel sensor putus
cek sensor rusak
ganti kabel dan sensor RTD PT1000
test run OK
2024-03-15
2 years ago
NR.EL-03 Bayu Kiln Saputro 444-CX2 Indikasi sensor DP Separator Oil Fault
cek sensor basah oli
clean up tubing sensor
ganti sensor dengan spare rekondisi
test run OK
2024-03-15
2 years ago
NR.EL-03 Bayu Kiln Saputro 444-CX1 Trip Overload
Coba start
cek ampere motor OK
run normal
2024-03-15
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-302 Motor Fan Radiator Trafo Noise
Ganti motor 1 set dengan spare
bongkar motor dan ganti bearing 2x 6203 2RS
2024-03-14
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-301 Motor Fan Radiator Trafo Noise
Ganti Fan 1 set dengan spare
bongkar motor existing
ganti bearing 2x 6203 2RS
cek winding sudah rusak (getas)
rewinding motor ke vendor
2024-03-14
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-2 Yearly Maintenance (OH)
Cek level oil main tank dan OLTC pakai selang
function test PRD setelah penggantian dari ex OTR-A
Masukkan DS
Onkan OCB

2024-03-19
2 years ago
NR.EL-01 Wahyu Adi Triono L63-RM1-P2-DRUFT-PRESSURE-OFTEN-HIGH-AROUND-25-MMH2O Actual pressure at local are not check yet use portable sensor pressure
Do cross check actual pressure, clean up probe pressure found pressure increase from 19.1 to 25.6 so same at CCR reading ( YOGA & ADI )
2024-03-19
2 years ago
NR.EL-01 Wahyu Adi Triono L63-2K1-SERVICE-ANALYZER-COMPLAIN-CO-READING-FLUCTAUIC-OFTEN-HIGH Flowmeter at low position, fllange-sample line, and filter probe are not service yet
Clean up sample line, flange probe, filter probe, filter disposable from dirt of coal process. Result after cleaning indication ball flowmeter increase result trusted at CCR ( YOGA & ADI )
2024-03-15
2 years ago
NR.SHIFT Wahyu Adi Triono 443-WI1-M3-REPLACE-BEARING-MOTOR Bearing motor bad are not replace yet
Replace bearing motor with spare bearing. Install motor test functional motor result ok ( FIRMAN & ANDRI )
2024-03-15
2 years ago
NR.EL-01 Wahyu Adi Triono 443-PH1,-GCT,-463-KL1,-423-EP1-WBI-ELECTRICAL-&-INSTRUMENTATION Area electrical and Instrumentation are not clean up yet
Do clean up area electrical and instrumentation for 443 PH1, 423 EP1, GCT, and 463 KL1 ( YOGA )
2024-03-15
2 years ago
NR.EL-01 Wahyu Adi Triono LA3-VA1-&-VA3-CALIBRATION-SENSOR-IDO Sensor IDO are not calibrated yet
Calibrated sensor IDO LA3 VA1 and VA3 ( RIZAL & EVE RIZKY )
2024-03-15
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1-GEMBA-TPM-5R Area TPM are dirty are not clean up yet, unuse ducting still at location
Clean up area TPM use equipment tools, dismantle unuse ducting ( ALL CREW & FIRMAN & ANDRI & IMAN )
2024-03-19
2 years ago
NR.EL-01 Wahyu Adi Triono 423-BF1-INSTALL-OIL-FILTER Filter oil is not install yet at location
Installing filter oil at 423 BF1 ( RIZAL & FIRMAN & ANDRI )
2024-03-19
2 years ago
NR.EL-01 Wahyu Adi Triono ER3-INSTALL-LIMIT-SWITCH-AND-PULLING-CABLE Limit switch is not insall yet
Install limit switch and pulling cable at ER3. Test functional limit switch result ok ( RIZAL & FIRMAN & ANDRI )
2024-03-19
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1-&-473-CC1-PMR-SERVICE-CRITICALMOTOR-AND-LSR Area and filter motor dirt by dust
Clean up area and filter motor use instrument air supply. Measure vibration-noise for free side and load side, add grease free and load side 15 times to 30 times ( AGUS & EVE RIZKY )
2024-03-19
2 years ago
NR.EL-01 Wahyu Adi Triono 423-2K1-PMR-SERVICE-CEMS Filter purge air unit for dust hunter and flowsic, swivel window dust hunter, transducer flowsic, CEMS room dirty from dust procecc
Clean up motor and filter purge air unit of dust hunter also flowsic, swivel windows dust hunter, transducer flowsic from dust process. Do alignment dust hunter, clean up CEMS room use equipment cleaning tools. Clean up filter cabinet MCS 100E use instrument air supply ( YOGA & ADI )
2024-03-18
2 years ago
NR.EL-01 Wahyu Adi Triono ER3-INSTALL-LIMIT-SWITCH-AND-PULLING-CABLE Limit switch and cable are not ready at ER3
Install limit switch and pulling cable and ER3. Test functional result ok ( RIZAL & ANDRI )
2024-03-18
2 years ago
NR.EL-01 Wahyu Adi Triono 473-FAC-REPALCE-BEARING-MOTOR Bearing motor bad are not replace yet
Replace bearing motor. Install back at location test run result ok ( YOGA & FIRMAN & EVE RIZKY-RAGIL )
2024-03-18
2 years ago
NR.EL-01 Wahyu Adi Triono 363-RM1-AND-L63-RM1-PMR-SERVICE-CRITICAL-MOTOR--AND-LSR Area and filter motor dirty from dust process
Clean up area and filter motor. Measure vibration-noise and temperature free also load side. Add grease from 20 times and 100 times. Replace AUTO GREASE for load side at 363 MD1 with EASY LUBE setting auto grease every 2 hour ( AGUS & ADI )
2024-03-18
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1-DISMANTLE-UNUSE-DUCTING unuse ducting still at location
Dismantle unuse ducting ( FIRMAN & ANDRI )
2024-03-18
2 years ago
NR.EL-01 Wahyu Adi Triono LA3-VA1-&-VA3-CALIBRATION-SENSOR-IDO Sensor IDO are not calibrated yet
Calibration sensor IDO ( RIZAL & RIZKY )
2024-03-18
2 years ago
NR.EL-01 Wahyu Adi Triono TPM-GEMBA-5R Area GEMBA 5R are not clean up yet
Do clean up area GEMBA 5R ( ALL CREW )
2024-03-18
2 years ago
NR.EL-01 Wahyu Adi Triono 443-PH1,-GCT,-EP,-463-KL1-WBI-ELECTRICAL-AND-INSTRUMENTASI- Electrical / Instrumentation are not check yet
WBI area PH-GCT-EP-KILN for electrical and instrumentation ( YOGA )
2024-03-14
2 years ago
NR.EL-01 Wahyu Adi Triono FLOWMETER-IDO-CALIBRATION IDO flowmeter is not calibration yet
Calibration flowmeter IDO at preheater and burner floor. drop test IDO. Result ok ( RIZAL & YOGA )
2024-03-14
2 years ago
NR.EL-01 Wahyu Adi Triono L63-RM1-R4-REPLACE-THERMOCOUPLE Thermocouple is not replace yet
Replace thermocouple at L63 RM1 T4. Check indication at CCR for temperature result ok ( YOGA & ANDRI )
2024-03-14
2 years ago
NR.EL-01 Wahyu Adi Triono 443-EL1-PMR-SERVICE-ELEVATOR Elevator is not service yet
PMR service at 433 EL1, clean up control VSD at 8th floor, also clean up every floor for safety sensor, Do test operation elevator every floor. Result ok ( PENY & EVE RIZKY )
2024-03-14
2 years ago
NR.EL-01 Wahyu Adi Triono 433-BE1-REPLACE-AUTO-GREASE Auto grease is not replace yet
Replace AUTO GREASE for 433 BE1 ( AGUS )
2024-03-14
2 years ago
NR.EL-01 Wahyu Adi Triono 393-EB1-REPLACE-LAMP-AT-BOTTOM-BLENDIG Lamp off is not replace
Replace lamp at bottom blending. Do test on result ok ( FIRMAN & ANDRI )
2024-03-14
2 years ago
NR.EL-01 Wahyu Adi Triono L63-RM1-PMR-SERVICE-ANALYZER Sample line, filter, flange probe full material of coal, also filter balston
Clean up filter probe, flange, sample line, membran pump, filter balston from dust coal use instrument air. Check filter humidity sensor result still ok ( ADI & EVE RAGIL )
2024-03-13
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-2 Sensor pressure relief maintank rusak
Cek sensor tidak bisa simulasi kontak
Ganti box terminal dan limit switch dengan spare (ex OTR-A)
Test OK
2024-03-13
2 years ago
NR.EL-03 Bayu Kiln Saputro 444-CX1 Indikasi fault
Cek d display indikasi sensor dp separator error
Cek dan flushing tubing ok
Service sensor dp separator
Test OK
2024-03-13
2 years ago
NR.EL-01 Wahyu Adi Triono 393-3B1-REPLACE-LAMP-OF-BOTTOM-BLENDING Lamp off are not replace yet
Replace lamp at bottom blending, test on result ok ( ANDRI & FIRMAN )
2024-03-13
2 years ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP-REPORT-EFFICIENCY-ENERGY Report efficiency energy are not ready yet
Make report efficiency energy at work shop ( PENY )
2024-03-13
2 years ago
NR.EL-01 Wahyu Adi Triono L63-WF1-CHECK-LAMP-INSIDE-WEIGHT-FEEDER-IS-OFF Lamp off is not replace yet
Replace lamp off at L63 WF1. Test on result ok ( PENY )
2024-03-13
2 years ago
NR.EL-01 Wahyu Adi Triono BURNER-FLOOR-&-493-3B1-WBI-CRANE Crane are not check yet for move up and down also move south-north or west-east
Do WBI for crane at burner floor and clinker silo. Test crane move up and down also move north-south or west-east ( EVE RIZKY )
2024-03-13
2 years ago
NR.EL-01 Wahyu Adi Triono WORK-SHOP-COMPLETE-DATA-CALIBRATION Data calibration are not complete yet
Complete data calibration at work shop ( YOGA & RIZAL )
2024-03-13
2 years ago
NR.EL-01 Wahyu Adi Triono 433-BE1-CHECK-SPEED-SENSOR Speed sensor is not check yet
Check speed sensor at 433 BE1. Result ok ( RIZAL & YOGA )
2024-03-13
2 years ago
NR.EL-01 Wahyu Adi Triono 483-2K1-&-443-2K1-PMR-SERVICE-ANALYZER Probe, flange, filter probe, filter humidity sensor are not clean up yet from dirty dust process
Clean up probe, flange, filter probe, filter humidity sensor from dirty dust process. for 463 2K1 do adjust probe to be center at flange, cover end probe make to close and do zero calibration for CO zero before -.0.065 vol % zero after -0.012 vol % ( AGUS & ADI & EVE RAGIL )
2024-03-12
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-2 Yearly maintenance (OH)
Test function trafo
Indikasi high level oil maintank bareng dengan suddent pressure maintank
Cek wiring, sensor level dengan pressure di paralel untuk indikasi sedangkan untuk sensor pressure kabel untuk indikasi tidak di wiring
Normalkan wiring untuk indikasi level di terminal X2.1 11 dan 12 no kabel 207, sedangkan untuk indikasi sudden press di terminal X2.2 11 dan 12 no kabel 218
2024-03-12
2 years ago
NR.EL-03 Bayu Kiln Saputro 464-MD1 Pengukuran harmonik
Pengukuran harmonic trafo vsd maindrive kiln nar2 hasilny harmonic current 7%
2024-03-12
2 years ago
NR.EL-03 Bayu Kiln Saputro ALBANNA-BUILDING Lampu mati
Ganti lampu 18 Ea
2024-03-08
2 years ago
NR.EL-03 Bayu Kiln Saputro ALBANNA-BUILDING Lampu mati
Ganti lampu TL 5 Ea
2024-03-08
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-2 Yearly Maintenance (OH)
Function Test Protection Trafo
2024-03-12
2 years ago
NR.EL-01 Wahyu Adi Triono 463-MD1-CLEAN-AREA-MOTOR-AND-FILTER-MOTOR Area and filter motor are not clean up yet
Do clean up area and filter motor. Check spark at carbon brush before and after clean up ( PENY & ADI )
2024-03-12
2 years ago
NR.EL-01 Wahyu Adi Triono L63-RM1-7-443-PH1-WBI-CRANE Crane are not test yet for move up and down also south-north or west-east
Do test carne move up and down also move north and south or west and east ( YOGA & ADI )
2024-03-12
2 years ago
NR.EL-01 Wahyu Adi Triono 463-KL1-AND-473-CC1-PMR-CRITICAL-MOTOR-&-LSR Area motor and filter motor are not clean up yet
Do clean up area motor and filter motor. Measure vibration-noise-temperature for free side and load side. Add grease from 10 times to 15 times for free side and load side ( AGUS & FIRMAN )
2024-03-12
2 years ago
NR.EL-01 Wahyu Adi Triono 423-2K1-PMR-SERVICE-CEMS Filter PAU, swivel windows Dust Hunter, transducer Flowsic 100, filter cabinet MCS are dirt from dust process
Do clean up filter purge air unit dust hunter and flowsic 100, clean up swivel wndows transducer/reflector and reflector unit Dust Hunter, clean up transducer A & B of Flowsic 100, clean up filter cabinet MCS 100 E, clean up CEMS room ( YOGA & EVE RIZKY & ANDRI )
2024-03-12
2 years ago
NR.EL-01 Wahyu Adi Triono FEED-BIN-WBI-ELECTRICAL-AND-INSTRUMENTATION-CHECK-INPUT-OUTPUT-PANEL i/O panel area feed are dirty from dust process
Do clean up panel I/O area feed bin use hand blower ( PENY & ADI )
2024-03-12
2 years ago
NR.EL-01 Wahyu Adi Triono 443-PH1-PMR-SERVICE-TEMPERARUE-TAD-&-T-SCANNER-&-CCCTV-AND-CAMERA-BURNER Lens of temperature TAD-Tscanner-CCTV and camera burner are not clean up yet
Do clean up lens of temperature TAD, CCTV, T scanner, camera burner from dirt dust proses ( PENY & ADI )
2024-03-08
2 years ago
NR.EL-01 Wahyu Adi Triono 363-CV2 Often speed failure
Do modification support flange of probe speed sensor. Test run 363 CV2 result ok ( PENY & ADI & FIRMAN-WIKAN CIVACON )
2024-03-08
2 years ago
NR.EL-01 Wahyu Adi Triono 363-LD2 Can not close 0 %
Do check at local at CCR wheter direct close 0% is available. Result ok  ( RIZAL & EVE RAGIL )
2024-03-08
2 years ago
NR.EL-01 Wahyu Adi Triono 473-EH5-CONNECT-TO-LCS-NEAR-483-BL7 Cable for power 473 EH5 is not connect yet
Do connect power cable 473 EH5 to LCS near 483 BL7 ( FIRMAN & WIKAN CIVACON )
2024-03-08
2 years ago
NR.EL-01 Wahyu Adi Triono 453-PF1-MONITOR Problem 453 PF1 still exist
Do monitor 453 PF1, use load at local and change CF ( RIZAL & EVE RAGIL )
2024-03-08
2 years ago
NR.EL-01 Wahyu Adi Triono 363-CV1-&-363-CV2 Often speed failure
Do check at pre amplifier for 363 CV1 and 363 CV2 found cable are not tighten. Use lug cable for cable, tighten result ok ( PENY - ADI - EVE RIZKY )
2024-03-07
2 years ago
NR.EL-03 Bayu Kiln Saputro RIVERPUMP-BUILDING Kabel Lan tarikan baru (utk PC dan telepon) masih berantakan
Rapihkan kabel (masukkan ke pit dan kabel tray)
Test OK
2024-03-07
2 years ago
NR.EL-03 Bayu Kiln Saputro RIVERPUMP-BUILDING Motor pompa domestik belum ada panel start stop
Install panel start stop motor pompa air domestik
Pulling kabel dari panel welding ke panel start stop
Rapihkan kabel arah motor (masukkan ke pit) dalam MCC
Test OK
2024-03-07
2 years ago
NR.EL-03 Bayu Kiln Saputro RIVERPUMP-BUILDING Area water intake pencahayaan kurang
Install lampu tembak 2 Ea
test OK
2024-03-07
2 years ago
NR.EL-01 Wahyu Adi Triono TENT-OH-LAMP-LIGHT-INSIDE Lamp light inside tent OH are not dismantle yet
Do dismantle lamp light and  power dispenser inside tent ( YOGA & ADI & ANDRI )
2024-03-07
2 years ago
NR.EL-01 Wahyu Adi Triono 363-MD1,-363-SR1,-463-MD1,473-FA2,-483-BL9,-433-W1-M3,-473-FN1-FN3-FN6 Monitoring motor are not action yet
Do measure vibration-noise and temperature free and load side add grease from 10 times to 20 times ( YOGA & EVE RAGIL - EVE RIZKY )
2024-03-07
2 years ago
NR.EL-01 Wahyu Adi Triono 473-EH5-AND-493-EH1 Move power to new panel are not ready yet
Do move power to new panel for 473 EH5 and 493 EH1 ( AGUS & FIRMAN & RAGIL-RIZKY EVE )
2024-03-07
2 years ago
NR.EL-01 Wahyu Adi Triono 433-FA1,-5,5-KW-MOTOR-AND-45-KW-MOTOR- Motor 433 FA1 is not move to ware house, motor 5,5 KW is not move to Mr. Dwiyan wh, motor 45 KW is not move from WS Electric Nr2 to WS Electric Nr1
Do move motor 433 FA1 to WH, also motor 5.5 KW move to Mr. Dwiyan work shop, and move motor 45 KW from WS Electric Nr2 to WS Electric Nr1 ( ADI & ANDRI )
2024-03-06
2 years ago
NR.EL-03 Bayu Kiln Saputro M3A-WP1 Kabel LCS ke Motor banyak yang lecet
Preparing kabel, scun, gland kabel dan fabrilkasi holder gland kabel
cek motor ground (hasil megger 0,5 ohm)
2024-03-06
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-301 Cooling fan trafo Noise
Ganti Cooling fan dengan cooling fan spare 1 set
test OK
2024-03-06
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-2 Yearly Maintenance (OH)
Supervisi PT Quadro
2024-03-04
2 years ago
NR.SHIFT Ade Mulyadi 363-MD1 N1OH 2024
Install, wiring, test new vibration sensor pinion axial & vertical
2024-03-04
2 years ago
NR.SHIFT Ade Mulyadi 473-FAA N1OH 2024
Replace bearing temperature free side
2024-03-04
2 years ago
NR.SHIFT Ade Mulyadi 473-SC1 N1OH 2024
Setting ppm & delay motion detector
2024-03-04
2 years ago
NR.SHIFT Ade Mulyadi 473-HC1 N1OH 2024
Commisioning & test signal motion detector
2024-03-03
2 years ago
NR.SHIFT Ade Mulyadi 473-HC1 N1OH 2024
Modif & activation motion detector
2024-03-03
2 years ago
NR.SHIFT Ade Mulyadi 453-PF1 N1OH 2024
Recallibration PF & PreHopper
Dynamic zerro also with blower 
2024-03-03
2 years ago
NR.SHIFT Ade Mulyadi 483-PF1 N1OH 2024
Recallibration PF & PreHopper
Dynamic zerro also with blower
2024-03-03
2 years ago
NR.SHIFT Ade Mulyadi 473-FA3-4-5-6-7-8-9-A N1OH 2024
Cek & service all temperature sensor & vibrasion sensor
2024-03-03
2 years ago
NR.SHIFT Ade Mulyadi BURNER-FLOOR-NAR1 N1OH 2024
Disconnect power cable PT Sinagawa from welding panel
2024-03-03
2 years ago
NR.SHIFT Ade Mulyadi 473-SC1-2-3-4-5 N1OH 2024
Commisioning all screw and test safety device
2024-03-03
2 years ago
NR.SHIFT Ade Mulyadi 483-BV2 N1OH 2024
Replave & modif SV from 24vdc to 110VAC, Change power in IO panel
2024-03-06
2 years ago
NR.EL-01 Wahyu Adi Triono 453-PF1-MONITOR Monitor functional 453 PF1
Do monitoring functional of 453 PF1 ( RIZAL  & EVE RIZKY )
2024-03-06
2 years ago
NR.EL-01 Wahyu Adi Triono 463-FX2-M2 Replace motor
Do replace motor for 463 FX2 M2 ( YOGA & FIRMAN & ANDRI )
2024-03-06
2 years ago
NR.EL-01 Wahyu Adi Triono 363-MD1-AND-363-SR1 Temperature bearing over heat
Do measure vibration-noise-temperature for free and load side, add grease 10 times to 20 times ( AGUS & EVE RAGIL )
2024-03-06
2 years ago
NR.EL-01 Wahyu Adi Triono 463-MD1,-473-FA8,-483-BL9,-473-FN1-FN3-FN6 Do monitoring bearing motor
Do measure vibration-noise and temperature free side also load side, Add grease 5 times-7 times-10 times for free side and load side ( PENY & ADI )
2024-03-05
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-2 Yearly Maintenance (OH)
Supervisi PT Quadro
2024-03-05
2 years ago
NR.EL-03 Bayu Kiln Saputro M03-WT3 Yearly Maintenance (OH)
Install Motor di lokal after replacement bearing
2024-03-05
2 years ago
NR.EL-03 Bayu Kiln Saputro D3A-CP3 Indikasi Loading, aktual tidak Loading
Cek relay loading energize
cek socket OK
cek solenoid OK
coba tukar tubing valve OK Piston bisa posisi nonjok
2024-03-05
2 years ago
NR.EL-01 Wahyu Adi Triono ER3-ER4--ER5-SETTING-MOTOR-DT Motor much can not start because setting DT are abnormal
Setting DT motor at ER3-ER4 and ER5, test run result ok ( AGUS & ADI )
2024-03-05
2 years ago
NR.EL-01 Wahyu Adi Triono 463-2K1-INLET-KILN-GAS-ANALYZER Reading O2 is abnormal
Do service analyzer such as clean up flange, filter probe. Also calibration O2 for zero and span ( RIZAL & ANDRI & RAFLI EVE )
2024-03-05
2 years ago
NR.EL-01 Wahyu Adi Triono 443-PH1-CYCLONE-4-TEMPERATURE-SHOW-AND-453-PF1-AMPERE-HIGH-MOTOR Temperature cyclone 4 material and gas are show abnormal, Ampere motor 453 PF1 is abnormal
Do cross check temperature at cyclone for material and gas make same reading at CCR. Also do recalibration 453 PF1 for zero and span ( RIZAL & YOGA & RAFLI EVE & ANDRI CIVACON )
2024-03-05
2 years ago
NR.EL-01 Wahyu Adi Triono 393-FN5-&-HGA-SYSTEM 393 FN5 is indication ampere also vibration high. HGA system is not start yet
Do check vibration and ampere at 393 FN5 and do tighten base plate result ampere and vibration are normal. Do start HGA system al location ( PENY & FIRMAN & RAGIL-FARHAN EVE )
2024-03-05
2 years ago
NR.EL-01 Wahyu Adi Triono ER3-363-SR1 Indication ready at CCR Operator is not appear
Do connect cable for indication ready, KW at ER3 bottom ( AGUS & ADI &  FARHAN-RIZKY-RAGIL EVE )
2024-02-21
2 years ago
NR.N1-OH Wahyu Adi Triono MCC-ER3-ACB Peremajaan ACB
Ganti ACB ER 3 atas 3 unit
2024-02-26
2 years ago
NR.N1-OH Wahyu Adi Triono ER3-SWITCH-GEAR Peremajaan VCS to VCB
ganti VCS to VCB 3TR 301 , 2TR 301 , 363 SR1
2024-03-04
2 years ago
NR.N1-OH Wahyu Adi Triono L33-FN1 motor grouded
ganti mtr dgn 7,5KW / 4P ( WIG )
Check no load , 6A  , 6,4A , 6,2A
2024-03-04
2 years ago
NR.N1-OH Yoga Permana 433-PF1 OH-N1 2024
-kalibrasi 433-PF1
-393-FA7 repair fan nosie
-393-3E1 West sensor level error, done
-393-BF1 tubing leaking, done
-393-PG9 done
-463-KL1 install camera
-463-2K1 ready dan kalibeasi
-443-ZA3 error, done
2024-03-04
2 years ago
NR.EL-03 Bayu Kiln Saputro 423-CX2 Indikasi Air Press Rendah (tidak sesuai aktual)
Saat di run sempet ada indikasi overload main motor
Indikasi Air Press Rendah (tidak sesuai aktual)
Coba ganti sensor transducer 4-20 mA 0-16 Bar, masih abnormal
cek kabel OK
coba ganti controller
Test OK (indikasi air press sesuai aktual)
2024-03-04
2 years ago
NR.EL-03 Bayu Kiln Saputro 474-CX2 indikasi temperature discharge high 130 derajat
cek sensor rtd OK, indikasi tidak jumping
cek vsd run di 30 Hz terus
coba inject vsd dengan kalibrator 4-20 mA OK
cek 4-20 mA output controller pin 13 dan 21 tidak ada
ganti controller
Test OK
2024-03-04
2 years ago
NR.EL-03 Bayu Kiln Saputro D33-CX1 Indikasi overload motor
Coba turunkan setting press load (dari 7.0 bar ke 6.3 bar) unload (dari 7.5 bar ke 6.8 bar)
test OK
2024-03-04
2 years ago
NR.EL-01 Wahyu Adi Triono ER-5-TO-PLC-COOLER-PULLING-CABLE Cable for PLC Cooler are not ready at site
Do pulling cable 2 rools from ER5 to PLC Cooler ( ADI & RAGIL-FARHAN EVE & ANDRI-OHA-DEDI-EKO-JOKO-RIDWAN-RIAN-SADDAM-MAHPUDIN-SYAHRI-ALDIAN-RAHMAT-RAMANDA-IQBAL CIVACON )
2024-03-02
2 years ago
NR.EL-03 Bayu Kiln Saputro 443-CX4 Yearly Maintenance (OH)
Reconnect kabel main motor 160 kW
test OK
2024-03-02
2 years ago
NR.EL-03 Bayu Kiln Saputro D33-CX5 Yearly Maintenance (OH)
- Buat Lubang dudukan MC (Main, Star dan delta)
- Buat kabel jumper Output MC Delta dan Star
- Ganti MC ke LS 3 Ea
- Ganti Kabel motor cooling fan 5,5kW (kabel 4 mm) dan 1,1kW (kabel 1,5 mm)
- Test Run OK
2024-03-02
2 years ago
NR.EL-03 Bayu Kiln Saputro ER-7A Manuver Power
Normal Power OTR-301
- OFF Outgoing OTR-301 All
- OFF Bustie 16, Rack Out ACB
- OFF Bustie 17, Rack Out ACB
- Rack In ACB Incoming OTR-301, ON ACB
- ON Outgoing OTR-301 All

* Saat ON ACB Incoming OTR-301, OCB OTR-301 OFF
* Relay 86 di panel incoming trip, Reset relay 86
* Hanya ada indikasi Alarm di Vamp, Reset
* Turunkan OLTC ke posisi tap 3
* ON OCB OTR-301, tunggu tegangan sampai 6300V
* ON ACB Incoming OTR-301

2024-03-02
2 years ago
NR.EL-03 Bayu Kiln Saputro ER-7B Manuver Power
Manuver Power Outgoing OTR-2 ke MSS
- OFF outgoing OTR-2 All
- OFF Incoming OTR-2, Rack Out ACB
- Rack In ACB Bustie OTR-2 ON Bustie OTR-2
- ON Outgoing OTR-2 All
Manuver Power Outgoing OTR-3 dari MSS ke OTR-3
- OFF Outgoing OTR-3 All
- OFF Bustie OTR-3, Rack Out ACB
- Rack In ACB Incoming OTR-3, ON ACB
- ON Outgoing OTR-3 All
2024-03-03
2 years ago
NR.EL-01 Wahyu Adi Triono 493-BV2,-473-HS1,473-CV1,473-CV2,473-CV3,-473-CV4,473-CV5 Install S/V BV2, check miltronic sensor are not ready yet
Do install S/V of 483 BV2 110 VAC also modification power supply, check settingan sensor miltronic for 473 CV1-CV5 and modification support flange probe 473 HS1 ( ADE & ADi & ALDI CIVACON )
2024-03-03
2 years ago
NR.EL-02 Yana Yuhana L63-WF1 OH nar1
Kalibrasi 
2024-03-03
2 years ago
NR.EL-02 Yana Yuhana 4D3-FM1 OH nar1
Kalibrasi 
2024-03-03
2 years ago
NR.EL-02 Yana Yuhana 4D3-AE2 OH nar1
Cek dan tes 
2024-03-03
2 years ago
NR.EL-02 Yana Yuhana 4D3-AE1- OH nar1
Cek dan tes
2024-03-02
2 years ago
NR.SHIFT Ade Mulyadi 483-PF1 N1OH 2024
Cek & adjust loadcell,
Baru hard callibration
2024-03-02
2 years ago
NR.SHIFT Ade Mulyadi GUN-BURNER-NAR1 N1OH 2024
Install all pressure gauge, ada beberapa yg rusak, sudah di infokan
2024-03-02
2 years ago
NR.SHIFT Ade Mulyadi 483-BL9 N1OH 2024
Commisioning, cek signal temperature & vibration sensor
Vibrqtion signal error, sudah diperbaiki
2024-03-02
2 years ago
NR.SHIFT Ade Mulyadi 483-BL7 N1OH 2024
Commisioning, cek signal temperature & vibration sensor
2024-03-02
2 years ago
NR.SHIFT Ade Mulyadi 483-FN1 N1OH 2024
Commisioning, cek signal temperature & vibration sensor
2024-03-02
2 years ago
NR.SHIFT Ade Mulyadi 483-BV2 N1OH 2024
Test open close belum mau open, ada masalah di solenoid valve
2024-03-02
2 years ago
NR.SHIFT Ade Mulyadi 483-BV1 N1OH 2024
Test open close sudah bagus,
2024-03-02
2 years ago
NR.SHIFT Ade Mulyadi 473-SC5 N1OH 2024
Perbaikan panel pre-amp
Perbaikan connection & probe installation
2024-03-02
2 years ago
NR.SHIFT Ade Mulyadi L63-FN1 N1OH 2024
Cek signal all temperature & vibration bearing fan
2024-03-02
2 years ago
NR.SHIFT Ade Mulyadi 473-SC4 N1OH 2024
Modif safety device, replace probe motion detector, test signal
2024-03-01
2 years ago
NR.SHIFT Ade Mulyadi 473-SC5 N1OH 2024
Prepare perbaikan box pre-amp & connection
2024-03-01
2 years ago
NR.SHIFT Ade Mulyadi SCREW-MULTICYCLONE-COOLER-NAR1 N1OH 2024
Continue modif, adjust & test safety device
473-SC4 replace card miltronic
2024-03-01
2 years ago
NR.SHIFT Ade Mulyadi L64-RM1 N1OH 2024
Install temperature roller R1 & R2
2024-03-02
2 years ago
NR.N1-OH AGUS SUMIAJI SARBINI 363-MD1.M1 Motor Maintenance
# Blow out winding, rotor & termination box.
# Measure rotor insulation. ( K-11,9....L-10,8....M-10,9 MOhm)
# Measure carbon brush lenght.
# Replace carbon brush ( 2 eah, RC73).
2024-03-02
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 423-BV5 OH N1
Ganti Proximity Open dan Close
2024-03-02
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 423-BV3 OH N1
Ganti Proximity Open
2024-03-02
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 423-SG6 OH N1
Ganti Proximity, clean up area SlideGate 
2024-03-02
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 423-SG5 OH N1
Cek Proximity dan cleanup area SlideGate 
2024-03-02
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 423-SG4 OH N1
Cek Proximity dan cleanup area SlideGate 
2024-03-02
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 423-SG3 OH N1
Cek Proximity dan cleanup area SlideGate 
2024-03-02
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 423-SG2 OH N1
Cek Proximity dan cleanup area SlideGate 
2024-03-02
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 423-SG1 OH N1
Ganti Proximity, clean up area SlideGate 
2024-03-02
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 423-BF1-PT07 OH N1
Ganti Presure Transduser 
2024-03-02
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 423-BF1-PT06 OH N1
Ganti Presure Transduser 
2024-03-02
2 years ago
NR.N1-OH Yoga Permana 443-PH1 OH-N1 2024
-Perbaikan termocouple tertarik 443-ZA1 T2
-Ganti transmiter 443-ZA2 T2
-Pasang filter udara 433-PG1
-Calibrasi 443-FM1
2024-03-01
2 years ago
NR.EL-01 Yurizal Rachman 413-AE2-V1-16 Check dan service
Check dan service solenoid
Check dan service actuator
Check indikasi pada I/O

2024-03-01
2 years ago
NR.EL-01 Yurizal Rachman 413-PG-A-F Check dan service
Check open close
Adjust mekanikal stik
Adjust indikasi
2024-03-01
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 423-BF1-T4 OH N1
Cek dan Tes
2024-03-01
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 423-BF1-T3 OH N1
Cek dan Tes
2024-03-01
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 423-BF1-T2 OH N1
Cek dan Tes
2024-03-01
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 423-BF1-T1 OH N1
Cek dan Tes
2024-02-29
2 years ago
NR.EL-01 Yurizal Rachman 413-AE1-V1-16 Check dan service
Check dan service actuator
Check dan service solenoid
Check indikasi di I/O
2024-02-29
2 years ago
NR.EL-01 Yurizal Rachman 413-PG5-8 Service damper
Check open close
Adjust mekanikal stik
Adjust indikasi

2024-03-01
2 years ago
NR.N1-OH AGUS SUMIAJI SARBINI 403-3E1 4P3-1M3 MCC Maintenance
# Service Main Contactor (100%)
# Test OCR/EOCR (100%)
# 413-BL4.M1 Ganti MC & MCCB (100%)
# 393-FA5A.M1 Rewiring (100%)
2024-03-01
2 years ago
NR.N1-OH AGUS SUMIAJI SARBINI 403-3E1 4P3-1M4 MCC Maintenance
# Service Main Contactor (100%)
# Test OCR/EOCR (100%)
2024-03-01
2 years ago
NR.N1-OH AGUS SUMIAJI SARBINI 403-3E1 4P3-1M5 MCC Maintenance
# Service Main Contactor (100%)
# Test OCR/EOCR (100%)
2024-03-01
2 years ago
NR.N1-OH Yoga Permana BLENDINGSILO-N1 OH-N1 2024
-kalibrasi 413-PGE,PGF,PGG,PG9
-kalibrasi 433-PG1
-Service air filter 433-PG1
-Replace gear 413-PG9  
2024-03-01
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-301 Yearly Maintenance (OH)
Supervisi PT Megavolt
- Test DIRANA, Tan Delta, PI 
- Connect kabel HV dan LV
- Function Test
2024-03-01
2 years ago
NR.EL-03 Bayu Kiln Saputro 443-CX4 Yearly Maintenance (OH)
Install motor
2024-03-01
2 years ago
NR.EL-03 Bayu Kiln Saputro D33-CX5 Yearly Maintenance (OH)
Install mainmotor, cooling fan 1.1kW dan 5.5kW
2024-03-01
2 years ago
NR.EL-02 Yana Yuhana 423-BV-K OH nar1
Cek dan tes 
2024-03-01
2 years ago
NR.EL-02 Yana Yuhana 423-BV-J OH nar1
Cek dan tes 
2024-03-01
2 years ago
NR.EL-02 Yana Yuhana 423-BV-I OH nar1
Cek dan tes 
2024-03-01
2 years ago
NR.EL-02 Yana Yuhana 423-BV-H OH nar1
Cek dan tes 
2024-03-01
2 years ago
NR.EL-02 Yana Yuhana 423-BV-G OH nar1
Cek dan tes 
2024-03-01
2 years ago
NR.EL-02 Yana Yuhana 423-BV-F OH nar1
Cek dan tes 
2024-03-01
2 years ago
NR.EL-02 Yana Yuhana 423-BV-E OH nar1
Cek dan tes 
2024-03-01
2 years ago
NR.EL-02 Yana Yuhana 423-BV-D OH nar1
Cek dan tes 
2024-03-01
2 years ago
NR.EL-02 Yana Yuhana 423-BV-C OH nar1
Cek dan tes 
2024-03-01
2 years ago
NR.EL-02 Yana Yuhana 423-BV-B OH nar1
Cek dan tes 
2024-03-01
2 years ago
NR.EL-02 Yana Yuhana 423-BVA OH nar1
Cek dan tes 
2024-03-01
2 years ago
NR.EL-02 Yana Yuhana 423-BV9 OH nar1
Cek dan tes 
2024-03-01
2 years ago
NR.EL-02 Yana Yuhana 423-BV8 OH nar1
Cek dan tes
2024-03-01
2 years ago
NR.EL-02 Yana Yuhana 423-BV7 OH nar1
Cek dan tes 
2024-03-01
2 years ago
NR.EL-02 Yana Yuhana 423-BV6 OH nar1
Cek dan tes 
2024-03-01
2 years ago
NR.EL-02 Yana Yuhana 423-BV5 OH nar1
Cek dan tes 
2024-03-01
2 years ago
NR.EL-02 Yana Yuhana 423-BV4 OH nar1
Cek dan tes 
2024-03-01
2 years ago
NR.EL-02 Yana Yuhana 423-BV3 OH nar1
Cek dan tes 
2024-03-01
2 years ago
NR.EL-02 Yana Yuhana 423-BV2 OH nar1
Cek dan tes
2024-03-01
2 years ago
NR.EL-02 Yana Yuhana 423-BF1-PT7 OH nar1
Ganti presure tranduser 
2024-03-01
2 years ago
NR.EL-02 Yana Yuhana 423-BF1-PT6 OH nar1
Ganti presure tranduser
2024-03-01
2 years ago
NR.EL-01 Wahyu Adi Triono 393-3S3-AND-393-3S4-CLEAN-UP-LCS-AND-MOTOR LCS and motor are dirty by dust process and not clean up yet
Do clean up panel LCS for west blending and east blending 413 FN2-413 FX2-413 FA2-413 BF2 C1-413 FA4-413 BL6,BL7,BL8,BL9,BLC-433 FA5-4D3 FA1-433 PF1,PF2-483 SC4-413 FA1-413 BF1 C1-413 FX1-413 BE1 M1,M2-413 FN1,FN4-413 BF3 C1-433 SG4. Replace handle LCS also INS 40 A for 413 BL6 ( ADI & DIDIN )
2024-03-01
2 years ago
NR.N1-OH AGUS SUMIAJI SARBINI 403-3E1 4P3-1M4 MCC Maintenance
# Service Main Contactor (100%) (by FM Crews)
# Test OCR/EOCR (100%)

2024-03-01
2 years ago
NR.N1-OH AGUS SUMIAJI SARBINI 403-3E1 4P3-1M5 MCC Maintenance
# Service Main Contactor (100%) (by FM Crews)
# Test OCR/EOCR (100%)

2024-03-01
2 years ago
NR.N1-OH AGUS SUMIAJI SARBINI 403-3E1 LP3-1M1 MCC Maintenance
# Service Main Contactor (100%) (by FM Crews)
# Test OCR/EOCR (100%)

2024-02-29
2 years ago
NR.N1-OH AGUS SUMIAJI SARBINI 403-3E1 LP3-1M2 MCC Maintenance
# Service Main Contactor (100%) (by FM Crews)
# Test OCR/EOCR (100%)
# 453-BL2.M1 Rewiring (100%)
2024-02-29
2 years ago
NR.SHIFT Ade Mulyadi SCREW-MULTICYCLONE-COOLER-NAR1 N1OH 2024
Cek, repair, service & modification safety devices (motion detector & control) all screw conveyor multicyclone nar1
2024-02-29
2 years ago
NR.SHIFT Ade Mulyadi LEVEL-UNDERGRATE N1OH 2024
Cek level under grate diatas 473-FV4 (info sensor level masih trial dan belum di fungsikan)
2024-02-28
2 years ago
NR.SHIFT Ade Mulyadi GUN-BURNER-NAR1 N1OH 2024
Service all pressure gauge (manometer) gun burner Nar1
2024-02-28
2 years ago
NR.SHIFT Ade Mulyadi FAN-COOLER-NAR1 N1OH 2024
Install pressure transmitter & flushing line sampling 473-FA3,4,5,6,7,8,9,A
2024-02-28
2 years ago
NR.SHIFT Ade Mulyadi BURNER-FLOOR-NAR1 N1OH 2024
Install & flushing line sampling all pressure transmitter area burner floor nar1
2024-02-29
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-301 Yearly Maintenance (OH)
Supervisi PT Megavolt
- Ganti silica gel
- cek kebocoran oli di bushing LV dan HV
- Purifikasi Oli trafo
- BDV test
2024-02-29
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-3 Yearly Maintenance (OH)
Supervisi PT Quadro
- Function test

* ON GCB OTR-3
* Energize trafo OTR-3
2024-02-29
2 years ago
NR.EL-03 Bayu Kiln Saputro 483-CX1 Yearly Maintenance (OH)
Service MC
bold tighten all terminal
clean up panel
2024-02-29
2 years ago
NR.EL-03 Bayu Kiln Saputro 423-CX2 Yearly Maintenance (OH)
Service MC
clean up panel

2024-02-29
2 years ago
NR.EL-03 Bayu Kiln Saputro 423-CX1 bearing motor lifetime
Install main motor dan fan
service MC
mc delta KM2 rusak
buat lubang dudukan untuk MC baru 
ganti MC delta KM2 (dari siemens 115A ke LS 130A
clean up panel
2024-02-29
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 363-MW1 OH N1
Cek dan Service 363MW1
2024-02-29
2 years ago
NR.EL-02 Titok Pangesti Aji 2C1-2RC.11 KDT NR1
Replace CI
Replace MTU
2024-02-29
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 333-BC2 OH N1
Cek dan Service Safety Device 333BC1
2024-02-29
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 333-BC1 OH N1
Cek dan Service Safety Device 333BC1
2024-02-28
2 years ago
NR.EL-02 Titok Pangesti Aji CO2-SYSTEM KDT NR1
Install pressure transmitter
Test release CO
Replace solenoid valve
2024-02-29
2 years ago
NR.EL-02 Titok Pangesti Aji 483-PF1 KDT NR1
Service and calibration
Clean up and replace bearing counter weigh
2024-02-29
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 333-SX2 OH N1
Cek dan Service Safety Device 333SX2
2024-02-29
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 333-SX1 OH N1
Cek dan Service Safety Device 333SX1

2024-02-29
2 years ago
NR.EL-02 Yana Yuhana 313-3B1-BIN-LIMESTONE OH nar1
Kalibrasi 
2024-02-29
2 years ago
NR.EL-02 Yana Yuhana 323-3B2-BIN-SHALE OH nar1
Kalibrasi 
2024-02-29
2 years ago
NR.EL-02 Yana Yuhana 323-3B3--BIN-SILIKA OH nar1
Kalibrasi 
2024-02-29
2 years ago
NR.EL-02 Yana Yuhana 333-WF4 OH nar1
Kalibrasi 
2024-02-29
2 years ago
NR.EL-02 Yana Yuhana 333-WF3 OH nar1
Kalibrasi 
2024-02-29
2 years ago
NR.EL-02 Yana Yuhana 333-WF2 OH nar1
Kalibrasi 
2024-02-29
2 years ago
NR.EL-02 Yana Yuhana 333-WF1 OH nar1
Kalibrasi
2024-02-29
2 years ago
NR.EL-01 Wahyu Adi Triono CLEAN-UP-PANEL-INPUT-OUTPUT-AREA-443-PH1-AND-BLENDING Panel I/O are not clean up yet
Do clean up panel I/O area pre heater and west blending also east blending, replace CI 4C1-2RA-31 from CI 830 to CI 801 ( ADI & DIDIN & EKO CIVACON )
2024-02-28
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 333-WF4 OH N1
Cek dan Service Safety Device 333WF4
2024-02-28
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 333-WF3 OH N1
Cek dan Service Safety Device 333WF3
2024-02-28
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 333-WF2 OH N1
Cek dan Service Safety Device 333WF2
2024-02-28
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 333-WF1 OH N1
Cek dan Service Safety Device 333WF1
2024-02-28
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan PDT2002 OH N1
Pasang Kembali Transmiter PDT2002

2024-02-28
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan PDT2001B OH N1
Pasang Kembali Transmiter PDT2001B
2024-02-28
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan PDT2001A OH N1
Pasang Kembali Transmiter PDT2001A
2024-02-28
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 324-BF1P2 OH N1
Pasang Kembali Transmiter 324 BF1 P2

2024-02-28
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 324-BF1P1 OH N1
Pasang Kembali Transmiter 324 BF1 P1
2024-02-28
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 363-RM1P1,363-RM1P3,363-RM1P4 OH N1
Pasang Kembali Transmiter 363 RM1 P1, 363 RM1 P3, 363 RM1 P4

2024-02-28
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-301 Yearly Maintenance (OH)
Supervisi PT Megavolt
- repair baud bushing LV
- ganti butterfly valve
- filling oil
- purifikasi main tank
2024-02-28
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-3 Yearly Maintenance (OH)
Supervisi PT Quadro
- ganti valve radiator
- ganti silica gel OLTC
- ganti silika gel maintank
- filling oil
2024-02-28
2 years ago
NR.EL-03 Bayu Kiln Saputro M03-WT3 Yearly Maintenance (OH)
Lepas motor
bongkar motor
clean up dan cat ulang motor
ganti bearing 
2024-02-28
2 years ago
NR.EL-03 Bayu Kiln Saputro M03-WT2 Yearly Maintenance (OH)
Install motor di lokal setelah rekondisi bearing
2024-02-28
2 years ago
NR.EL-03 Bayu Kiln Saputro D33-CX2 Yearly Maintenance (OH)
Service panel kontrol
service MC
cek terminal box motor
2024-02-28
2 years ago
NR.EL-03 Bayu Kiln Saputro D33-CX1 Yearly Maintenance (OH)
Pasang motor fan (setelah rekondisi bearing)
Service panel kontrol
service MC
cek terminal box motor
2024-02-28
2 years ago
NR.EL-03 Bayu Kiln Saputro D33-CX4 Indikasi emergency stop
cek wiring
cek resistance kontak K10
kontak jelek, ganti dengan relay 8 pin
test
2024-02-28
2 years ago
NR.N1-OH Yoga Permana 413-PG6 OH-N1 2024
-Kalibrasi 413-PG6, PG5, PG4, PG3.
-Konek sensor reducer RAW MILL

2024-02-26
2 years ago
NR.EL-01 Yurizal Rachman 443-PH1 Relokasi Thermocouple
Instal new thermocouple
Buat jalur piping cable
Tarik kabel thermocouple
2024-02-27
2 years ago
NR.EL-01 Yurizal Rachman 443-Z4B-T2 Transmitter rusak
Instal new transmitter
Buat support transmitter
2024-02-27
2 years ago
NR.EL-01 Yurizal Rachman 363-RM1 Support blackout
Support blackout
Lepas jumperan acb

2024-02-28
2 years ago
NR.EL-01 Yurizal Rachman 443-PH1 Flexible dan tubing rusak
Repair flexible 443 Z3A T2
Replace selang tubing
2024-02-28
2 years ago
NR.EL-01 Yurizal Rachman 413-PG1-4 Check open close
Check open close
Inject setpoint
Check indikasi
Repair mekanikal stuck
2024-02-28
2 years ago
NR.EL-01 Yurizal Rachman 363-RM1 Connect cable
Connect cable temperature dan vibrasi
Instal new rtd thrust pad
2024-02-28
2 years ago
NR.EL-02 Yana Yuhana 4D3-SG2 OH nar1
Ganti kinetrol dan limit switch 
2024-02-28
2 years ago
NR.EL-01 Wahyu Adi Triono CLEAN-UP-LCS-AND-MOTOR-AREA-BURNER-FLOOR LCS and motor area burner floor are still dirty by dust process
Do clean up LCS for 473 FN1-FN2-FN3-FN4-FN5-FN6 also replace handle  door 2 each-handle LCS 3each and emergency bottom 4 each. Clean up LCS and motor for 473 EH1-473 EH5-483 LQ1-473 FAB-483 BL5-483 BL9-483 FA1-483 FA2-473 LD1 C1-483 LQ1 replace handle LCS 3 each for 483 BL7-483 BL9-483 LQ1. Install stick for handle LCS 473 EH5 ( ADI & DIDIN & FARHAN EVE & RAHMAT-EKO CIVACON )
2024-02-28
2 years ago
NR.N1-OH AGUS SUMIAJI SARBINI 403-3E2 4P3-1MA MCC Maintenance
# Service Main Conntactor (100%)
# Replace OCR with EOCR (100%)
# Test OCR/EOCR (100%)


2024-02-28
2 years ago
NR.N1-OH AGUS SUMIAJI SARBINI 403-3E2 4P3-1M9 MCC Maintenance
# Service Main Conntactor (100%)
# Replace OCR with EOCR (100%)
# Test OCR/EOCR (100%)


2024-02-28
2 years ago
NR.N1-OH AGUS SUMIAJI SARBINI 403-3E2 4P3-1M8 MCC Maintenance
# Service Main Conntactor (100%)
# Replace OCR with EOCR (100%)
# Test OCR/EOCR (100%)


2024-02-28
2 years ago
NR.N1-OH AGUS SUMIAJI SARBINI 403-3E2 4P3-1M7 MCC Maintenance
# Service Main Conntactor (100%)
# Replace OCR with EOCR (100%)
# Test OCR/EOCR (100%)


2024-02-28
2 years ago
NR.N1-OH AGUS SUMIAJI SARBINI 403-3E2 4P3-1M6 MCC Maintenance
# Main Contactor Service (100%)
# Replace OCR with EOCR (100%)
# Test EOCR (100%)
2024-02-27
2 years ago
NR.SHIFT Ade Mulyadi 473-FA2.P1 N1OH 2024
Install pressure transmitter & clean up line sampling
2024-02-27
2 years ago
NR.SHIFT Ade Mulyadi 473-FA1.P1 N1OH 2024
Install pressure transmitter, clean up line sampling
2024-02-27
2 years ago
NR.SHIFT Ade Mulyadi 473-GQ1.T2,T3 N1OH 2024
Replace temperature undergrate cooler
2024-02-27
2 years ago
NR.SHIFT Ade Mulyadi 473-GQ1.P1,2,3,3B,4,5,6,7,8,9,A N1OH 2024
Install & cek indication all pressure transmitter undergrate cooler
2024-02-27
2 years ago
NR.EL-03 Bayu Kiln Saputro M03-WT2 bearing motor lifetime
ganti bearing motor 
Rakit motor
2024-02-27
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-301 Yearly Maintenance (OH)
- Supervisi PT Megavolt
  * Ganti gasket bushing HV dan LV
2024-02-27
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-3 Yearly Maintenance (OH)
Supervisi PT Quadro
- Ganti valve radiator 4 set
2024-02-27
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-302 Yearly Maintenance (OH)
- ukur kapasitor bank OTR-302 all (36Ea)
- Kapasitor bank no 2 nilai kapasitansinya 1.5 nF (seharusnya 50.5uF)
- Geser kapasitor no 1 ke no 2
- Fabrikasi dudukan untuk pengganti kapasitor 
- Ganti kapasitor ambil dari kapasitor OTR 301
2024-02-27
2 years ago
NR.EL-02 Hariyanto 483-BL9--473-FN1--473-FN3--473-HS4--993-FN2 pasang motor
Pasang motorsetelah di rekondisi
2024-02-27
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 4D3-BF1 OH N1
Cek dan Service 4D3BF1
2024-02-27
2 years ago
NR.SHIFT Rizky Fauzy Ramadhan 393-BF1 OH N1
Cek dan Service 393BF1
2024-02-27
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 363-BC1 OH N1
Las Support LCS 363BC1
2024-02-27
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 363-BE1M2 OH N1
Las Support LCS 363BE1 M2 (LCS Inching)
2024-02-27
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 363-BF1 OH N1
Cek dan Service 363BF1
2024-02-27
2 years ago
NR.EL-02 Titok Pangesti Aji L63-SR1.T1 KDT NR1
Replace cable sensor
Replace temp transmitter
Replace sensor RTD
2024-02-27
2 years ago
NR.EL-02 Titok Pangesti Aji L93-BF1.C1 KDT NR1
Service solenoid purging
Ganti box panel
2024-02-27
2 years ago
NR.N1-OH Yoga Permana 443-PH1 OH-N1 2024
-Blackout Normalisasi replace VCB Er3 dan ACB Er3
-Install pressure transmiter
2024-02-27
2 years ago
NR.EL-01 Wahyu Adi Triono ER5-CLEAN-UP-MCC-ALSO-REPLACE-TOR-TO-EOCR TOR still applied at ER5
Do clean up MCC and replace TOR to EOCR for 493 FN4 and 493 AC2 ( ADI & DIDIN )
2024-02-27
2 years ago
NR.EL-01 Wahyu Adi Triono ER-3-NORMALISATION-CABLE-JUMPERE-ACB-AND-VCB Cable jumpered for ACB and VCB still connecting at ER 3
Do disconnected cable jumpered ACB and VCB at ER3 top and bottom ( EMIS-PENY-RIZAL-YOGA-ADI )
2024-02-27
2 years ago
NR.EL-02 Yana Yuhana 4D3-PG1 OH nar1
Cek dan tes
2024-02-27
2 years ago
NR.EL-02 Yana Yuhana 363-BE1 OH nar1
Ganti sensor level matrial ,las suport LCS inching
2024-02-27
2 years ago
NR.EL-02 Yana Yuhana 443-CT1-V3 OH nar1
Cek dan tes
2024-02-27
2 years ago
NR.EL-02 Yana Yuhana 443-CT1-VA2 OH nar1
Cek dan tes 
2024-02-26
2 years ago
NR.EL-02 Hariyanto 493-FN2-473-FN3--473-FN1--473-HS4--443-W1M3 bawa motor ke lokasi br datang rekondisi
Bawa motor ke lokasi baru datang rekondisi
2024-02-26
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-301 Yearly Maintenance (OH)
- Supervisi PT Megavolt
  * Service OLTC
  * Purifikasi Oli
  * Top up oli baru OLTC
  * Service oil level indicator OLTC
2024-02-26
2 years ago
NR.EL-03 Bayu Kiln Saputro D33-CX4 Test run
Test run kompresor setelah rewinding main motor
saat running normal kadang kadang muncul indikasi Emergency Stop, Ganti Push button emergency stop
test
2024-02-26
2 years ago
NR.EL-03 Bayu Kiln Saputro M03-WT2 bearing motor lifetime
Lepas motor
bongkar, clean up dan cat ulang motor
2024-02-26
2 years ago
NR.EL-03 Bayu Kiln Saputro D33-CX1 bearing motor lifetime
Lepas Motor Exh fan Kompresor
Bongkar, clean up dan cat ulang motor
Ganti bearing
rakit motor 
2024-02-25
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-3 Yearly Maintenance (OH)
- Supervisi PT Quadro
  * Bolt tightening OTR-3
  * Turn Ratio Test
  * Insulation Test
  * Reconnect kabel HV dan LV
2024-02-25
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-301 Yearly Maintenance (OH)
- Supervisi PT Megavolt
  * Clean Up Trafo dan bushing HV dan LV
  * Preparing Gasket 
- Supervisi PT Quadro
  * Clean up bushing OCB

2024-02-25
2 years ago
NR.EL-01 Yurizal Rachman 443-PH1 Replace thermocouple
Replace thermocouple cyclone 1-4 
2024-02-26
2 years ago
NR.EL-01 Yurizal Rachman 423-BF2 Sevice purging
Replace solenoid
Check timer cycle
Clean up box panel
2024-02-26
2 years ago
NR.EL-02 Titok Pangesti Aji 493-AC1.T1 KDT NR1
Service temperaturen clinker
2024-02-26
2 years ago
NR.EL-01 Yurizal Rachman 413-BF1 Service purging
Replace solenoid
Check timer cycle
Clean up box panel
2024-02-26
2 years ago
NR.EL-02 Titok Pangesti Aji 493-BF3 KDT NR1
Replace solenoid Valve
Test cycle purging
2024-02-26
2 years ago
NR.EL-02 Titok Pangesti Aji 493-BF4 KDT NR1
Replace solenoid Valve
Test cycle purging
2024-02-26
2 years ago
NR.EL-01 Yurizal Rachman 443-PH1 Instal new TE
Instal new relocation TE,
Instal pipa conduit
Instal pipa housing
2024-02-26
2 years ago
NR.EL-02 Titok Pangesti Aji 493-AC4.M1 KDT NR1
Check and simulation safety device
Ganti sling pull cord
2024-02-26
2 years ago
NR.EL-02 Yana Yuhana 443-CT1-VA1 OH nar1
Pasang dan set proporsional valve
2024-02-26
2 years ago
NR.EL-02 Titok Pangesti Aji 493-AC3.M1 KDT NR1
Check and simulation safety device
2024-02-26
2 years ago
NR.EL-02 Titok Pangesti Aji 494-AC2.M1 KDT NR1
Check and simulation safety device
2024-02-26
2 years ago
NR.EL-01 Wahyu Adi Triono ACCES-CONTROL-INSPECTION-ELECTRICAL-AND-WELDING-TOOLS-OF-CONTRACTOR Tools for electrical and welding are already expired tagging
Do inspection check for electrical and welding tools of MENARA BUKIT LUBUKELI-JANTAN SETIA SAKTI-TRUBA JAGA CITA-MEGAVOLT PERKASA ( ADI & MARPAUNG - SUTRI TRUBA JAGA CITA )
2024-02-26
2 years ago
NR.N1-OH Yoga Permana 443-PH1 OH-N1 2024
-install pressure transmiter PH
2024-02-24
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-301 Yearly Maintenance (OH)
- Ukur kapasitor bank (24Ea)
- Supervisi PT Megavolt 
  * Lepas kabel HV dan LV
  * Pengukuran karakteristik trafo before service
2024-02-24
2 years ago
NR.EL-03 Bayu Kiln Saputro ER-7B Yearly Maintenance (OH)
- Load Outgoing OTR-2 All Open 
- Bustie OTR-2 Open, Rack Out ACB
- OCB OTR-2 Close
- Incoming OTR-2 Rack In ACB, Close ACB
- Load Outgoing OTR-2 All Close

2024-02-24
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-2 Yearly Maintenance (OH)
Energize Trafo
2024-02-24
2 years ago
NR.EL-03 Bayu Kiln Saputro ER-7A Yearly Maintenance (OH)
Manuver power from MSS to OTR-302
- Load Outgoing all Open
- Bustie OTR 301/302 ER-7B Open
- Bustie 16 dan 17 open
- OCB OTR-302 Close
- Incoming 302 Rack In ACB, Close ACB
- Bustie 16 dan 17 Close
- Load Outgoing All Close
2024-02-24
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-3 Yearly Maintenance (OH)
- Supervisi PT Quadro (Characteric Test Trafo After Service)
  * Dirana Test
  * Tan Delta
  * Winding Resistance
  * Dynamic Resistance
  * Leakage Test
2024-02-23
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-302 Yearly Maintenance (OH)
- Bolt tightening dan tambal cover trafo yang rembes
- Bolt tightening kabel arrester 70 kV
- Function Test protection trafo
  * Indikasi Bukholz 1 stage Alarm tidak ada di panel RCP, cek relay kerja, lampu indikasi mati
  * Indikasi OLTC Oil Low Level aktif terus, cek kabel OK, cek kontak level switch rusak, 
     sementara di lepas kabelnya
-Energize Trafo
- Supervisi PT Megavolt
  * Insulation Test After service
  * Pasang kabel sisi HV dan LV
  * Function Test
2024-02-25
2 years ago
NR.EL-02 Hariyanto 393RF6--363FA2--363MD1--393RF4 rekondisi dan pasang motor
Bongkar dan pasang motor 
2024-02-25
2 years ago
NR.SHIFT Ade Mulyadi 493-AC3 N1OH 2024
Reposisi box amplifier motion
Clean up panel miltronic AC1, 2, 3 & 4
2024-02-25
2 years ago
NR.SHIFT Ade Mulyadi 493-AC2 N1OH 2024
Modif, wiring & test safety device (R5)
Service motion sensor
2024-02-25
2 years ago
NR.SHIFT Ade Mulyadi 493-AC1 N1OH 2024
Service motion sensor
2024-02-25
2 years ago
NR.SHIFT Ade Mulyadi 483-AE1 N1OH 2024
Replace T-joint yang pecah
2024-02-25
2 years ago
NR.SHIFT Ade Mulyadi COAL-MILL-AREA N1OH 2024
Install all pressure transmitter after callibration
2024-02-25
2 years ago
NR.SHIFT Ade Mulyadi 493-BF4 N1OH 2024
Service solenoid purging
2024-02-25
2 years ago
NR.SHIFT Ade Mulyadi 493-BF2 N1OH 2024
Service solenoid purging
2024-02-25
2 years ago
NR.SHIFT Ade Mulyadi SILO-BESI-NAR-1 N1OH 2024
Service level sensor
2024-02-25
2 years ago
NR.SHIFT Ade Mulyadi 493-AC1 N1OH 2024
Service sensor temperature clinker (cont)
Replace air regulator (done)
2024-02-25
2 years ago
NR.EL-02 Yana Yuhana 323-3B1 OH nar1
Cek dan tes matrial level
2024-02-25
2 years ago
NR.EL-02 Yana Yuhana 323-3B4 OH nar1
Cek dan tes matrial level 
2024-02-25
2 years ago
NR.EL-02 Yana Yuhana 323-3B3 OH nar1
Cek dan tes matrial level
2024-02-25
2 years ago
NR.EL-02 Yana Yuhana 323-3B2- OH nar1
Ganti sensor matrial level
2024-02-24
2 years ago
NR.SHIFT Ade Mulyadi 493-AC2 N1OH 2024
Modif, wiring & test safety device (TLS R6)
2024-02-24
2 years ago
NR.SHIFT Ade Mulyadi 493-AC3 N1OH 2024
Modif, wiring & test safety device (TLS R5 dan R6)
2024-02-24
2 years ago
NR.SHIFT Ade Mulyadi 493-AC1 N1OH 2024
Modif, wiring & test safety device (TLS R4)
2024-02-24
2 years ago
NR.SHIFT Ade Mulyadi ER3-N1 N1OH 2024
Clean up Trafo ER3 Nar1
Insulation test kabel input
Insulation test trafo (sisi primer)
2024-02-24
2 years ago
NR.EL-02 Titok Pangesti Aji 473-LD7.M1 KDT NR1
Service and check open/close
2024-02-24
2 years ago
NR.EL-02 Titok Pangesti Aji 473-LD6.M1 KDT NR1
Service and check open/close
2024-02-24
2 years ago
NR.EL-02 Titok Pangesti Aji 473-LD5.M1 KDT NR1
Service and check open/close
2024-02-24
2 years ago
NR.EL-02 Titok Pangesti Aji 473L-LD4.M1 KDT NR1
Service and check open/close
2024-02-24
2 years ago
NR.EL-02 Titok Pangesti Aji 473-LD3.M1 KDT NR1
Service and check open/close
2024-02-24
2 years ago
NR.EL-02 Titok Pangesti Aji 473-LD2.M1 KDT NR1
Service and check open/close
2024-02-24
2 years ago
NR.EL-02 Titok Pangesti Aji 473-LD1.M1 KDT NR1
Service and check open/close
2024-02-23
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-3 Yearly maintenace (OH)
- Service DS-F 70 kV OTR-3
- Supervisi PT Quadro
 * Ganti Gasket Bushing Netral 
 * Ganti baud OLTC dan tutup cover OLTC
 * Purifikasi
 * Cleaning isolator OCB 302
 * Vacum Maintank
 * Pasang bukhols relay
 * Oil Filling
2024-02-24
2 years ago
NR.EL-02 Titok Pangesti Aji 473-CC1.T1 KDT NR1
Service and clean up temperature sensor clinker
2024-02-24
2 years ago
NR.EL-02 Titok Pangesti Aji L63-BV3.M1 KDT NR1
Service and recondisi motor
Test damper hanya mampu 50% - 80%
Mekanikalnya berat
2024-02-24
2 years ago
NR.EL-02 Hariyanto 413FN2--L63LQ1--L63HS1--463FA2-393RF4 rekondisi motor
Bongkar motor untuk di rekondisi ke luar
2024-02-24
2 years ago
NR.N1-OH Yoga Permana PREHEATER-N1 OH-N1 2024
-replace termocouple area preheater n1
-service draft line preheater n1
2024-02-24
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 423-BF1L6-BF1SG6-BF1HE6 OH N1
Cek dan Service 423 BF1 L6, atas bawah, 423 BF1 SG6 atas bawah, BF1 HE6
2024-02-24
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 423-BF1L5-BF1SG5-BF1HE5 OH N1
Cek dan Service 423 BF1 L5, atas bawah, 423 BF1 SG5 atas bawah, BF1 HE5
2024-02-24
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 423-BF1L4-BF1SG4-BF1HE4 OH N1
Cek dan Service 423 BF1 L4, atas bawah, 423 BF1 SG4 atas bawah, BF1 HE4
2024-02-24
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 423-BF1L3-BF1SG3-BF1HE3 OH N1
Cek dan Service 423 BF1 L3, atas bawah, 423 BF1 SG3 atas bawah, BF1 HE3
2024-02-24
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 423-BF1L2-BF1SG2-BF1HE2 OH N1
Cek dan Service 423 BF1 L2, atas bawah, 423 BF1 SG2 atas bawah, BF1 HE2
2024-02-24
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 423-BF1L1-BF1SG1-BF1HE1 OH N1
Cek dan Service 423 BF1 L1, atas bawah, 423 BF1 SG1 atas bawah, BF1 HE1
2024-02-23
2 years ago
NR.EL-02 Yana Yuhana 443-CT1 OH nar1
Ganti selenoid valve untuk tangki air
2024-02-23
2 years ago
NR.SHIFT Yana Yuhana 423-BV1V1 OH nar1
Cek dan tes buka tutup ok
2024-02-23
2 years ago
NR.EL-02 Yana Yuhana 363-LD2 OH nar1
Pasang motor dan tes buka tutup
2024-02-23
2 years ago
NR.EL-02 Yana Yuhana 363-LD1 OH nar1
Pasang motor dan tes buka tutup
2024-02-23
2 years ago
NR.EL-02 Titok Pangesti Aji L63-BV2.M1 KDT NR1
Replace motor beck actuator
Signal test open close from CCR
2024-02-23
2 years ago
NR.EL-02 Titok Pangesti Aji L63-BV1.M1 KDT NR1
Service and replace motor actuator
Test open close from CCR
2024-02-23
2 years ago
NR.SHIFT Ade Mulyadi 493-AC1 N1OH 2024
Replace TLS (R1, R2, R3)
2024-02-23
2 years ago
NR.SHIFT Ade Mulyadi 473-GQ1.L1 N1OH 2024
Pulling cable dan konek (level sensor & io)
2024-02-23
2 years ago
NR.EL-02 Hariyanto 463FA2,-473FA1,-413BLC,-363FA2393FA6,7,-433FAA rekondisi mltor
 bongkar motor untuk di rekpndisi keluar
2024-02-23
2 years ago
NR.N1-OH Yoga Permana 443-KL1 OH-N1 2024
-replace socket sesor bearing tire kilen dan isntall conduit cable
-cek sensor tacho kiln
2024-02-23
2 years ago
NR.EL-01 Wahyu Adi Triono ER3-SERVICE-MCC-AND-REPLACE-TOR-TO-EOCR TOR are not replace yet to EOCR at MCC ER3
Do service MCC at ER3 top floor, and replace TOR to EOCR for 363 BE1 M1-363 HS1 M1 7 M2- 363 HS2 M1, 363 FA1 ( ADI & AGUS & DIDIN )
2024-02-23
2 years ago
NR.EL-01 Yurizal Rachman 463-KL1 Check dan repair
Check dan repair sensor vibrasi pinion gear
Repair pipa conduit
2024-02-22
2 years ago
NR.EL-01 Yurizal Rachman 463-KL1 Check and repair
Check dan repair sensor temperature tire kiln
2024-02-23
2 years ago
NR.N1-OH AGUS SUMIAJI SARBINI 303-3E2 3P3-1M2 MCC Maintenance
# Service Main Conntactor (100%)
# Replace OCR with EOCR (100%)
# Test OCR/EOCR (100%)
2024-02-23
2 years ago
NR.N1-OH AGUS SUMIAJI SARBINI 303-3E2 MCC MAINTENANCE
3P3-1M4 MCC Maintenance 
# Service Main Contactor (100%)
# Test OCR/EOCR (100%)
2024-02-22
2 years ago
NR.SHIFT Ade Mulyadi TRAFO-ER4-N1 Manuver power
Clean up trafo
Test insulation kabel input
Test insulation input trafo
Normalkan power area ER4 N1
2024-02-21
2 years ago
NR.SHIFT Ade Mulyadi COOLER-&-BURNER-FLOOR N1OH 2024
Service pressure transmitter under grate 
Service pressure transmitter area burner floor
2024-02-22
2 years ago
NR.SHIFT Ade Mulyadi 494-AC1 N1OH 2024
Check function rope switch
Prepare ganti switch 4pcs
2024-02-22
2 years ago
NR.SHIFT Ade Mulyadi 473-GQ1.L1 N1OH 2024
Check & service level sensor, prepare tarik kabel baru, kabel lama kena kebakaran
2024-02-22
2 years ago
NR.SHIFT Ade Mulyadi 483-BV2 N1OH 2024
Test functuon BV, kondisi mekanikal berat
2024-02-22
2 years ago
NR.SHIFT Ade Mulyadi 483-BV1 N1OH 2024
Test function BV, kondisi mekanikal berat
2024-02-22
2 years ago
NR.SHIFT Ade Mulyadi 474-CN1.T1 N1OH 2024
Replace Thermocouple
Replace Flexible Conduit
2024-02-22
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-301 OCB tidak bisa ON
Cek indikasi di RCP masih ada fault
coba reset di panel RCP
coba posisi lokal tidak bisa
coba posisi remote OK
2024-02-22
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-302 OCB tidak bisa ON
Cek indikasi di RCP masih ada fault
reset di relay bukholz
coba reset di panel RCP masih blm hilang faultnya
coba reset power MCB kontrol 110 Vdc
indikasi fault hilang
coba posisi lokal tidak bisa
coba posisi remote OK
2024-02-22
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-3 GCB tidak bisa ON
- Cek tegangan kontrol dan motor spring charger 0 V
- Posisi trafo CPT OTR-2 dan OTR-3 OFF
- Inject tegangan 220 V dari receptacle ER-7B ke panel ATS CPT OTR-2 / OTR-3 ke output MCCB untuk kontrol GCB
- Test OK
2024-02-22
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-3 Yearly Maintenance (OH)
Supervisi PT Quadro
- Pengukuran keserempakan dan resistance contact GCB
- Ganti O ring dan gasket Bushing HV
2024-02-22
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-302 Yearly Maintenance (OH)
Supervisi PT Megavolt
- Pengukuran karakteristik Trafo

Supervisi PT Quadro
- Pengukuran keserempakan dan resistance contact OCB
2024-02-22
2 years ago
NR.EL-03 Bayu Kiln Saputro MCC-COOLING-TOWER-NAR1 Yearly Maintenance (OH)
Clean up trafo MV (6,3 kV) to LV (400 V)
- Ukur tahanan isolasi sisi HV to ground 
   RST to ground = 12,8 Gohm ; 14,6 Gohm ; 15,1 Gohm (inject 5000 V)
- Ukur tahanan isolasi sisi LV to ground = 520 Mohm (inject 500 V)
- Ukur tahanan isolasi sisi HV terhadap sisi LV = 63,3 Gohm (inject 2500 V)
2024-02-22
2 years ago
NR.EL-03 Bayu Kiln Saputro ER-7B Yearly Maintenance (OH)
Power PLN 70 kV ke Nar1 OFF
Manuver Power dari trafo OTR-2 ke MSS
Aux Mill 1, 2, dan main office open
Incoming OTR-2 Open
Bustie OTR-2 Close
Aux Mill 1, 2, dan main office close
2024-02-22
2 years ago
NR.EL-03 Bayu Kiln Saputro ER-7A Yearly Maintenance (OH)
Power PLN 70 kV ke Nar1 OFF
Manuver Power dari trafo OTR-301 ke MSS
ER-3, ER-4, ER-5, ER-6, ER-8, Cooling Tower Open
Incoming OTR-301 Open
Bustie 16 dan 17 ER-7A Open
Bustie 301-302 ER-7B Close
Bustie 16 dan 17 ER-7A Close
ER-3, ER-4, ER-5, ER-6, ER-8, Cooling Tower Close
2024-02-22
2 years ago
NR.EL-02 Hariyanto 393FA1,FA2,FA3,-433FA1,FA2,FA3,RF1-413FA1,FA22 bongkar motor untuk di rekondisi
Bongkar motor untuk di rekondisi ke luar
2024-02-22
2 years ago
NR.N1-OH Yoga Permana 433-BE1,-ER4 OH-N1 2024
-Replace speed sensor 433-BE1 dan repair clamping beltdrift 
-Insulation testing all trafo TR ER4
2024-02-22
2 years ago
NR.EL-01 Wahyu Adi Triono ACCES-CONTROL-INSPECTION-ELECTRICAL-AND-WELDING-TOOLS-OF-CONTRACTOR Tools for electrical and welding are already expired tagging
Do inspection electrical and welding tools of contractor INDOPORLEN-KALOPER-MAGNA INDONESIA-MENARA BUKIT LUBUKELI ( ADI & MARPAUNG TRUBA JAGA CITA )
2024-02-22
2 years ago
NR.EL-02 Titok Pangesti Aji ER4-NR1 KDT NR1
Service and clean up trafo
Meger kabel incoming
2024-02-23
2 years ago
NR.EL-02 Titok Pangesti Aji L3A.BC1.ML1 KDT NR1
Replace baling2 sensor
2024-02-23
2 years ago
NR.SHIFT Titok Pangesti Aji L3A-BC1.M1 KDT NR1
Simulation and test safety device 
2024-02-23
2 years ago
NR.EL-02 Titok Pangesti Aji L3A-BC2.M1 KDT NR1
Simulation and test safety device replace ropeswitch
2024-02-22
2 years ago
NR.EL-02 Titok Pangesti Aji L33-BC1.M1 KDT NR1
Simulation and test safety device 
2024-02-22
2 years ago
NR.EL-02 Titok Pangesti Aji L33-BC2.M1 KDT NR1
Simulation and test safety device 
2024-02-22
2 years ago
NR.EL-02 Titok Pangesti Aji L33-3B1.W1 KDT NR1
Clean up sensor
2024-02-22
2 years ago
NR.EL-02 Titok Pangesti Aji L33-3B1.L1 KDT NR1
Service and test simulation
2024-02-22
2 years ago
NR.EL-02 Titok Pangesti Aji L33-BF1 KDT NR1
Service and test purging
2024-02-22
2 years ago
NR.EL-02 Titok Pangesti Aji L63-RM1.P1 KDT
Replace tubing sample
2024-02-21
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-302 Yearly Maintenance (OH)
+ Clean up Capasitor bank

Supervisi PT Megavolt
- Overhoul OLTC
- Ganti O ring valve radiator
2024-02-21
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-3 Yearly Maintenance (OH)
Supervisi PT Quadro
- Ganti drain dan filling valve maintank
- Ganti drain dan filling valve OLTC
- Ganti drain valve conservator OLTC dan Maintank
- Ganti gasket manhole consevator
- Ganti gasket oil level maintank
- Cleaning HV bushing
- Overhoul OLTC
2024-02-21
2 years ago
NR.EL-03 Bayu Kiln Saputro D3A-CP3 Display Mati
Cek Fuse 2A untuk kontrol putus
Coba ganti fuse
Lepas output main motor dan cooling fan
Test saat setelah MC delta energize mau ke posisi loading Fuse putus
Ganti fuse dengan MCB 2A
Lepas solenoid untuk loading unloading
Test Simulasi OK
Pasang kabel main motor dan cooling fan
Ganti Solenoid  Load Unload
Test OK
2024-02-21
2 years ago
NR.EL-03 Bayu Kiln Saputro D33-CX3 bearing motor lifetime
Lepas motor Exh fan
Ganti Bearing
Pasang Motor
Test Putaran OK
2024-02-21
2 years ago
NR.EL-03 Bayu Kiln Saputro D33-CX2 bearing motor lifetime
Pasang motor exh fan (after replacement bearing)

2024-02-20
2 years ago
NR.N1-OH Radifan Almas Sudaryadi 4C2-2RC.11 Overhaul(Yearly Maintenance)
Clean up dan rapihkan kabel
2024-02-20
2 years ago
NR.SHIFT Radifan Almas Sudaryadi 4C2-2RC.23 Overhaul(Yearly Maintenance)
Clean up dan rapihkan kabel
2024-02-20
2 years ago
NR.N1-OH Radifan Almas Sudaryadi 4C2-2RC.22 Overhaul(Yearly Maintenance)
Clean Up panel dan rapihkan kabel
2024-02-22
2 years ago
NR.N1-OH AGUS SUMIAJI SARBINI 303-3E2 MCC MAINTENANCE
3P3-1M3 MCC Maintenance
# Service Main Contactor (100%)
# Replace OCR with EOCR (100%)
# Test OCR/EOCR (100%)
2024-02-22
2 years ago
NR.N1-OH AGUS SUMIAJI SARBINI 303-3E2 MCC MAINTENANCE
4P3-1M1 MCC Maintenance
# Service Main Contactor (100%)
# Test OCR/EOCR (100%)
# Replace OCR with EOCR (100%)
2024-02-21
2 years ago
NR.N1-OH Yoga Permana 433-BE1,-443-RF1,-443-RF2,-433-BF1 Service, test
-Test proteksi 433-BE1
-Test sensor speed 443-RF1, 443-RF2
-Test 433-BF1
2024-02-21
2 years ago
NR.EL-02 Rizky Fauzy Ramadhan 474-EP1 F2B1, sering trip
Ganti modul card trafo (mA,kV)
2024-02-21
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 363-LD1,363-LD2 OH N1
Ganti bearing motor (LS,FS)
2024-02-20
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-3 Yearly Maintenance (OH)
Supervisi PT Quadro
- Bongkar panel radiator
- Bongkar dan repair ganti o ring NBR upper bottom valve radiator
- Ganti gasket radiator 20 pcs
- ganti gaslet blind flange pipa junction panel radiator
- ganti gasket manhole 4 set
- ganti gasket LV bushing 4 set
- ganti gasket bushing stabilizing/tertier 2 set

2024-02-20
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-302 Yearly Maintenance (OH)
Supervisi PT Megavolt
- Purifying 
- Clean up trafo
2024-02-20
2 years ago
NR.EL-03 Bayu Kiln Saputro D33-CX2 bearing motor lifetime
Bongkar motor exh fan
ganti bearing (6002zz dan 6002zz)
2024-02-20
2 years ago
NR.EL-03 Bayu Kiln Saputro 443-CX4 bearing motor lifetime
Bongkar main motor
bawa ke workshop
2024-02-20
2 years ago
NR.EL-03 Bayu Kiln Saputro 423-CX1 bearing motor lifetime
bongkar motor fan 4 kw
pasang motor fan ex 423-CX2 (sudah ganti bearing baru) 
cek putaran OK
2024-02-21
2 years ago
NR.N1-OH Yoga Permana BURNER-NAR1 N1OH 2024
Service pressure transmitter dan temperature sensor area burner floor
2024-02-21
2 years ago
NR.EL-02 Titok Pangesti Aji L63-2K3 KDT NR1
Service and calibration
2024-02-21
2 years ago
NR.N1-OH Yoga Permana COOLER-NAR1 N1OH 2024
Melanjutkan service pressure transmitter area fan cooler dan under grate
2024-02-21
2 years ago
NR.EL-02 Titok Pangesti Aji L63-2K2 KDT NR1
Service and calibration
2024-02-21
2 years ago
NR.EL-01 Titok Pangesti Aji L63-2K1 KDT NR1
Service and calibration
2024-02-21
2 years ago
NR.EL-02 Hariyanto 493-AC3,-493-FN2,-473-HS4,-443-WI1M3,-413-FN2,-413-FA2 rekondisi motor
Bongkar mptor untuk di rekondisi keluar
2024-02-21
2 years ago
NR.EL-01 Yurizal Rachman 433-BF1 Check dan service
Check dan service solenoid purging
2024-02-21
2 years ago
NR.EL-01 Yurizal Rachman 443-RF2 Check dan service
Check dan servoce motion detector
2024-02-21
2 years ago
NR.EL-01 Yurizal Rachman 443-RF1 Check dan service
Check dan service motion detector
2024-02-21
2 years ago
NR.EL-01 Yurizal Rachman 433-SG7,8-DAN-9 Check and service
Check and service solenoid dan damper
2024-02-21
2 years ago
NR.N1-OH Yoga Permana 433-BE1 Safety device
Check,repair and replace safety device
2024-02-20
2 years ago
NR.N1-OH Radifan Almas Sudaryadi 4C2-2RC.21 Overhaul(Yearly Maintenance)
Clean Up, rapihkan kabel, 
2024-02-20
2 years ago
NR.N1-OH Radifan Almas Sudaryadi 4W3-1NE Overhaul(Yearly Maintenance)
Clean Up dan cek panel power dan welding
2024-02-21
2 years ago
NR.SHIFT Radifan Almas Sudaryadi 473-FA9 Overhaul(Yearly Maintenance)
Clean up LCS, cek box motor dan winding 
2024-02-20
2 years ago
NR.SHIFT Radifan Almas Sudaryadi 473-FAA Overhaul(Yearly Maintenance)
Clean Up LCS, Box power motor dan box winding
2024-02-19
2 years ago
NR.N1-OH Radifan Almas Sudaryadi 493-BF3 Overhaul(Yearly Maintenance)
Clean up dan cek LCS serta kontrol BF
2024-02-21
2 years ago
NR.EL-01 Wahyu Adi Triono ACCES-CONTROL-INSPECTION-ELECTRICAL-AND-WELDING-TOOLS-OF-CONTRACTOR Tagging for electrical and welding tools of contractor already expire date and month
Do inspection electrical and welding tools of KAJIAN LOGAM PERSADA-MENARA BUKIT LUBUKELI-ARCA SEMESTA ( ADI & FAHRUL MARPAUNG TRUBA JAGA CITA )
2024-02-19
2 years ago
NR.N1-OH Radifan Almas Sudaryadi 493-BF2 Overhaul(Yearly Maintenance)
Clan Up dan cek LCS serta control BF
2024-02-19
2 years ago
NR.N1-OH Radifan Almas Sudaryadi 493-FN4 Overhaul(Yearly Maintenance)
Clean Up LCS dan Box Motor
2024-02-19
2 years ago
NR.N1-OH Radifan Almas Sudaryadi 493-FN3 Overhaul(Yearly Maintenance)
Clean Up LCS dan Box Motor
2024-02-19
2 years ago
NR.N1-OH Radifan Almas Sudaryadi 493-FN2 Overhaul(Yearly Maintenance)
Clean Up LCS dan Box Motor
2024-02-19
2 years ago
NR.N1-OH Radifan Almas Sudaryadi 493-FN1 Overhaul(Yearly Maintenance)
Clean Up LCS dan Box Motor
2024-02-19
2 years ago
NR.N1-OH Radifan Almas Sudaryadi 493-EH1 Overhaul(Yearly Maintenance)
Clean Up LCS dan ganti Switch INS 63
2024-02-19
2 years ago
NR.N1-OH Radifan Almas Sudaryadi 493-AC4 Overhaul(Yearly Maintenance)
Clean Up LCS dan Box Motor
Pengecekan dan clean Up PCS (kiri dan kanan) 
2024-02-19
2 years ago
NR.N1-OH Radifan Almas Sudaryadi 493-AC3 Overhaul(Yearly Maintenance)
Tidak bisa buka dan clean up LCS dan box motor karena sedang ada pekerjaan mekanik
Pengecekan dan clean up safety device PCS 1(atas) dan PCS2(bawah)
2024-02-21
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 393-BF3 OH N1
Cek dan Service 393-BF3
2024-02-21
2 years ago
NR.N1-OH Rizky Fauzy Ramadhan 393-BF2 OH N1
Cek dan Service 393-BF2
2024-02-20
2 years ago
NR.EL-01 Yurizal Rachman 443-PH1 Calibration pressure tx
Lepas dan kalibras pressure transmitter area preheater
2024-02-19
2 years ago
NR.SHIFT Ade Mulyadi ALL-PRESSURE-TRANSMITTER-COOLER-NAR1 KDT Nar1 2024
Dismantle pressure transmitter
2024-02-19
2 years ago
NR.EL-03 Bayu Kiln Saputro M03-WT1 bearing motor lifetime
Bongkar motor
clean up motor
ganti bearing 6312 ZZ dan 6212 ZZ
rakit motor dan repainting
2024-02-19
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-302 Kaca counter arrester buram
Clean up kaca counter arrester
modif frame kaca counter
2024-02-19
2 years ago
NR.EL-03 Bayu Kiln Saputro TRAFO-NAR1_2 WBI
WBI Trafo OTR A, B, 2, 3, 301, 302
2024-02-18
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-3 Yearly Maintenance (OH)
Supervisi PT Quadro
- Insulation Resistance Test (Before)
- Polarization Index (Before)
- Drain Oil maintank
- Inject Nitrogen Maintank
- Drain Oil OLTC
- Ganti Gasket OLTC
- Bolt Tightening OLTC
- Filling Oil Maintank
2024-02-18
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-302 Yearly Maintenance (OH)
Supervisi PT Megavolt
- Drain Oli
- Ganti gasket LV bushing, gasket oil level dan gasket butterfly valve atas bukholz

2024-02-17
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-302 Yearly Maintenance (OH)
Supervisi PT Megavolt
- Lepas Koneksi HV dan LV
- Test Tan Delta (Before)
- DIRANA (Before)
- Turn Ratio Test (Before)
- Winding Resistace Test (Before)
- Dynamic Resistance (Before)
2024-02-17
2 years ago
NR.EL-03 Bayu Kiln Saputro OTR-3 Yearly Maintenance (OH)
Supervisi PT Quadro
- Pembuatan Gasket OLTC
- Test Tan Delta (Before)
- DIRANA (Before)
- Turn Ratio Test (Before)
- Winding Resistace Test (Before)
- Dynamic Resistance (Before)
2024-02-17
2 years ago
NR.EL-03 Bayu Kiln Saputro 214-TR1 trip indikasi VSD GF (ground fault)
214-TR1 Motor Travel
coba discouple motor
test noload ampere 80A
ada noise di motor
beberapa saat GF lagi di VSD
turunkan motor, riwinding by Sigma
2024-02-20
2 years ago
NR.EL-02 Titok Pangesti Aji 483-2K1 KDT
Service and calibration analyzer
2024-02-21
2 years ago
NR.EL-02 Titok Pangesti Aji 483-AE1 KDT
Service purging solenoid
Test simulation purging
2024-02-20
2 years ago
NR.EL-02 Titok Pangesti Aji 453-AE1 KDT
Service membrane solenoid
2024-02-20
2 years ago
NR.EL-02 Titok Pangesti Aji L63-LD1 KDT
Test open / close dari CCR
2024-02-20
2 years ago
NR.EL-02 Yana Yuhana 393.-BE1 OH nar1
Service safety device 
2024-02-20
2 years ago
NR.EL-02 Yana Yuhana 393-3S3 OH nar1
Service level matrial 
2024-02-20
2 years ago
NR.EL-02 Yana Yuhana 393-3S2 OH nar1
Service level matrial 
2024-02-20
2 years ago
NR.EL-02 Yana Yuhana 393-3S1 OH nar1
Service level matrial
2024-02-20
2 years ago
NR.EL-02 Yana Yuhana 393-AE2 OH nar1
Cek dan service selenoid 
2024-02-20
2 years ago
NR.EL-02 Yana Yuhana 393-AE1 OH nar1
Cek dan service selenoid
2024-02-20
2 years ago
NR.EL-02 Hariyanto 363-SR1,473-FN1,473-FN3,473-FA8 rekondisi motor
Bongkar motor untuk di rekondisi ke pt mesindo dan cigma
2024-02-20
2 years ago
NR.N1-OH Yoga Permana 463-2K1,-443-PH1 Overhaul
-Replace proximity IKGA
-Remove Transmiter Preheater 

2024-02-20
2 years ago
NR.EL-01 Wahyu Adi Triono ACCES-CONTROL-INSPECTION-ELECTRICAL-AND-WELDING-TOOLS-OF-CONTRACTOR Tagging for electrical and welding tools of contractor already expired
Do inspection electrical and welding tools of MESINDO-MENARA BUKIT LUBUKELI-INDOPORLEN-MAGNA INDONESIA ( ADI & FAHRUL MARPAUNG TRUBA JAGA CITA )
2024-02-19
2 years ago
NR.EL-02 Hariyanto 483-BL9 Rekondisi motor
Bongkar motor
2024-02-19
2 years ago
NR.EL-01 Titok Pangesti Aji L63-RM1 KDT NR1
Turunkan semua pressure transmitter area coalmill
2024-02-19
2 years ago
NR.EL-02 Titok Pangesti Aji 444-2K2 oxigen tinggi
Ada kebocoran di sample line dan membran solenoid valve