304-3E2
AGUS SUMIAJI SARBINIProblem: MCC, Switchgear Maintenance
Action:
1. Clean Up MCC Room & Panel (100%)
2. Clean Up Switcgear Room & Panel (100%)
3. Clean Up Transformer (100%)
4. Clean up Capacitor & Panel (100%)
5. 364-MD1.M1 mesure capacitor (100%)
6. LV Protection Relay Tripping Test (100%)
7. LV Protection Relay Replacement (50%)
2. Clean Up Switcgear Room & Panel (100%)
3. Clean Up Transformer (100%)
4. Clean up Capacitor & Panel (100%)
5. 364-MD1.M1 mesure capacitor (100%)
6. LV Protection Relay Tripping Test (100%)
7. LV Protection Relay Replacement (50%)
Status: done